Clough Projects Australia Pty Ltd v Floreani

Link copied
Case Copied 30 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   CLOUGH PROJECTS AUSTRALIA PTY LTD -v- FLOREANI [2018] WASC 101

CORAM:   TOTTLE J

HEARD:   28 FEBRUARY 2018

DELIVERED          :   10 APRIL 2018

FILE NO/S:   CIV 2976 of 2017

BETWEEN:   CLOUGH PROJECTS AUSTRALIA PTY LTD

Applicant

AND

NICHOLAS FLOREANI

Respondent

OCEANIC OFFSHORE PTY LTD

Other Party


Catchwords:

Judicial review - Application for writ of certiorari - Determination made by adjudicator under Construction Contracts Act 2004 (WA) - Whether adjudicator exceeded jurisdiction - Whether denial of procedural fairness - Where adjudication of multiple payment disputes between same parties - Where determination made on basis that implied contract arose outside of contract - Where determination made on basis not argued for by parties

Legislation:

Construction Contracts Act 2004 (WA), s 32(3)(b), s 32(3)(c)
Interpretation Act 1984 (WA)

Result:

Application granted

Category:    A

Representation:

Counsel:

Applicant : Mr J M Healy
Respondent : No appearance
Other Party : Mr C P K Russell

Solicitors:

Applicant : HFW Australia (Perth)
Respondent : No appearance
Other Party : Baker & McKenzie (Victoria)

Case(s) referred to in decision(s):

Cape Range Electrical Contractors Pty Ltd v Austral Construction Pty Ltd [2012] WASC 304

Commissioner for ACT Revenue v Alphaone Pty Ltd [1994] FCA 1074; (1994) 49 FCR 576

Delmere Holdings Pty Ltd v Green [2015] WASC 148

John Holland Pty Ltd v Chidambara [2017] WASC 179

Kioa v West [1985] HCA 81; (1985) 159 CLR 550

Lampson (Australia) Pty Ltd v Fortescue Metals Group Ltd [No 3] [2014] WASC 162

Liebe v Molloy [1906] HCA 67; (1906) 4 CLR 347

Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221

Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217; (2011) 43 WAR 319

Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR 355

Thiess v Collector of Customs [2014] HCA 12; (2014) 250 CLR 664

Zurich Bay Holdings Pty Ltd v Brookfield Multiplex Engineering and Infrastructure Pty Ltd [2014] WASC 40

TOTTLE J:

Introduction

  1. The applicant, Clough, applies for a writ of certiorari to quash a determination made by the respondent, an adjudicator appointed under the provisions of the Construction Contracts Act 2004 (WA) (the Act). The determination was made on 13 November 2017. The adjudicator determined that Clough should pay the Other Party, Oceanic, $465,658.[1]

    [1] All figures have been rounded to the nearest dollar.

  2. The principal issues are:

    (i)Did the adjudicator have the power to adjudicate more than one payment dispute between the parties simultaneously without Clough's consent?

    (ii)Did the adjudicator determine the payment disputes on a basis that was not argued by the parties, thus denying Clough procedural fairness?

    (iii)Did the adjudicator exceed his jurisdiction by determining the payment disputes on the basis of findings that one or more implied contracts had been made between the parties?

Background

  1. The background is not contentious and is as follows.

  2. Clough and Oceanic entered into a lump-sum subcontract dated…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Clough Projects Australia Pty Ltd v Floreani and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] WASC 101
Decision Date

CaseChat Overview and Summary

The case involved Clough Projects Australia Pty Ltd, the applicant, and Floreani, the respondent. The matter was heard in the Supreme Court of Western Australia, where Clough Projects sought a judicial review of a decision made by an adjudicator under the Construction Contracts Act 2004 (WA). The primary dispute centred on whether the adjudicator had exceeded their jurisdiction and whether there had been a denial of procedural fairness in the adjudication process.

The legal issues before the court were whether the adjudicator's determination was valid, specifically focusing on whether it was based on an implied contract that arose outside of the main contract, and whether the adjudicator had made a decision on a basis that was not argued for by the parties. The applicant argued that the adjudicator's decision was flawed because it was based on a premise not presented by either party, and that this constituted a failure to provide procedural fairness.

The court found that the adjudicator had indeed exceeded their jurisdiction by making a determination on a basis not argued by the parties. Furthermore, the court held that this failure to adhere to the arguments presented by the parties resulted in a denial of procedural fairness. The court emphasised that an adjudicator must base their decision on the submissions made by the parties, and any deviation from this principle could lead to the annulment of the decision. The court granted the applicant's application for judicial review and quashed the adjudicator's determination.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.