JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CIVIL
CITATION: SANDVIK MINING AND CONSTRUCTION AUSTRALIA PTY LTD -v- FISHER [No 2] [2020] WASC 123
CORAM: ARCHER J
HEARD: 28 OCTOBER 2019
DELIVERED : 16 APRIL 2020
FILE NO/S: CIV 1842 of 2019
BETWEEN: SANDVIK MINING AND CONSTRUCTION AUSTRALIA PTY LTD
Applicant
AND
JOHN FISHER
Respondent
CIVMEC CONSTRUCTION & ENGINEERING PTY LTD
Other Party
Catchwords:
Judicial review - Construction Contracts Act 2004 (WA) - Payment claim - Payment dispute - Whether permissible to bring two applications involving different items under the same progress claim - Where an assumption was made for the purposes of the total amount to be paid, was the matter assumed 'determined'
Legislation:
Construction Contracts Act 2004 (WA) s 3, s 6(2), s 25(a), s 31(2)(b), s 41(1)(b)
Result:
Application dismissed
Category: A
Representation:
Counsel:
| Applicant | : | M J Feutrill SC |
| Respondent | : | No appearance |
| Other Party | : | M N Solomon SC & L S Panotidis |
Solicitors:
| Applicant | : | Squire Patton Boggs |
| Respondent | : | No appearance |
| Other Party | : | Tottle Partners |
Case(s) referred to in decision(s):
Alliance Contracting Pty Ltd v James [2014] WASC 212
Clough Projects Australia Pty Ltd v Floreani [2018] WASC 101
Cooper & Oxley Builders Pty Ltd v Steensma [2016] WASC 386
Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91
Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2018] WASCA 28; (2018) 52 WAR 323
Forrest & Forrest Pty Ltd v The Honourable William Richard Marmion, Minister for Mines and Petroleum [2017] WASCA 153; (2017) 51 WAR 425
Hossain v Minister for Immigration and Border Protection [2018] HCA 34; (2018) 254 CLR 123
Mohammadi v Bethune [2018] WASCA 98, 13
O'Donnell Griffin Pty Ltd v John Holland Pty Ltd [2009] WASC 19
Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217
Re Refugee Review Tribunal; Ex parte Aala [2000] HCA 57; (2000) 204 CLR 82
Salini-Impregilo SPA v Francis [2020] WASC 72
Sandvik Mining and Construction Australia Pty Ltd v Fisher [2019] WASC 352
Table of Contents
Background
The ground of review
Sandvik's initial argument
The issues
Legal principles
Judicial review
Approach to statutory construction
The construction question
Overview of legislative framework
Object and purpose
The adjudication process under the Act
Time limit for adjudicator's decision
Deemed dismissal
Determinations
Simultaneous adjudications
Multiple applications in relation to the same dispute
Payment disputes and payment claims
Prohibition on repeated adjudications of the same payment dispute
The relevant provisions
The effect of the provisions
Sandvik's contentions
Res judicata, issue estoppel and Anshun estoppel
Reliance on O'Donnell Griffin
Multiplicity of proceedings
Multiple determinations
Simultaneous adjudication
Act intends to exclude complex disputes
Certainty
The Alliance construction
Conclusion
Further issue arising on the facts
The factual issues
What was the payment dispute in the First Application?
What was decided in the First Determination?
Was there a conflict between the First Determination and the Second Application?
Conclusion
ARCHER J:
Background
The applicant (Sandvik) seeks judicial review of…
Keep reading for free
Create a free CaseChat account to read Sandvik Mining and Construction Australia Pty Ltd v Fisher [... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] WASC 123
- Decision Date
CaseChat Overview and Summary
Sandvik initially argued that a progress claim can only give rise to a single payment claim and a single payment dispute. This meant that once any part of a progress claim was subject to adjudication, it defined the 'payment dispute' for that progress claim, and no subsequent adjudication could be made regarding other disputed items within the same progress claim. However, Sandvik later modified its position, accepting that each itemised amount in a progress claim could be treated as a separate 'payment claim'. The court therefore had to address whether the First Determination, which involved some items from Progress Claim 26, precluded the Second Determination from being made.
The court considered the relevant statutory provisions and the established case law, particularly the decision in Duro Felguera Australia Pty Ltd v Samsung C&T Corporation. The court found that a progress claim could indeed give rise to multiple 'payment claims', each of which could be the subject of separate adjudications. Furthermore, the court determined that the First Determination did not encompass all items in Progress Claim 26, and therefore the Second Determination was not precluded. The court concluded that Mr Fisher had the jurisdiction to make the Second Determination.
As a result of the court's findings, the application for judicial review was dismissed. The decision underscored the importance of correctly interpreting the statutory provisions and highlighted the flexibility in adjudicating on different items within the same progress claim. The court's ruling reinforced the principle that each itemised amount in a progress claim can be treated as a separate 'payment claim', thereby allowing for multiple adjudications on different items under the same progress claim.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
This submission was inconsistent with the Court of Appeal's decision in Duro Felguera Australia Pty Ltd v Samsung C&T Corporation.[8] The court said that, where a progress claim contains a number of itemised amounts, each may itself be a 'payment claim' as defined in the Act and each may be treated as its own separate 'payment claim'. Had Sandvik maintained its original submission, I would have rejected it. However, in its written reply and when making oral submissions, Sandvik modified its position.[8] Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2018] WASCA 28; (2018) 52 WAR 323 [146]. In its reply, Sandvik accepted that 'payment claim' could refer to an individual item in a progress claim and, if it did, the 'payment dispute' would be about that individual item.[9] However, Sandvik contended that, once any part of a progress claim was the subject of an adjudication, that defined the 'payment dispute' and 'payment claim' in relation to that progress claim, and the Act did not permit any subsequent adjudication in relation to that progress claim. In other words, Sandvik contended that a progress claim could only give rise to a single payment dispute. Sandvik contended that, as both determinations involved the same progress claim, they both involved the same payment dispute and therefore Mr Fisher did not have jurisdiction to adjudicate the Second Application.[10] [9] See Applicant's Outline of Submissions in Reply on Application for Judicial Review filed 9 September 2019 (Sandvik's Written Reply) [43] ‑ [45].[10] See, for example, ts 105 ‑ 106. Sandvik further contended that, factually, each of the items challenged in the Second Application had been determined in the First Determination.[11] Three questions arise. The first is a construction issue, while the second and third are factual. The first question is: on a proper construction of the Act, can a progress claim only give rise to a single payment claim and a single payment dispute? That is, once any part of a progress claim is the subject of an adjudication, does that define the 'payment dispute' in relation to that progress claim, with the result that an adjudicator would not have jurisdiction to subsequently adjudicate any of the other disputed items arising from that progress claim? If the answer to the first question is 'yes', Mr Fisher did not have the jurisdiction to make the Second Determination. If the answer to the first question is 'no', the second question is: what was the 'payment dispute' that was determined in the First Determination? Factually, was it a payment dispute in relation to only those five items Civmec challenged or was it a payment dispute in relation to the whole of Progress Claim 26 and Payment Notice 26? If the answer to the second question is that it was a payment dispute in relation to the whole of Progress Claim 26 and Payment Notice 26, Mr Fisher did not have the jurisdiction to make the Second Determination. If the answer to the second question is that it was a payment dispute in relation to only those items Civmec challenged, the third question is: on the facts in this case, had each of the items the subject of the Second Adjudication been determined in the First Determination.