Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [No 3]

Link copied
Case Copied 60 min read

FEDERAL COURT OF AUSTRALIA

Clough v Oil & Natural Gas Corporation Ltd [No 3] [2007] FCA 2082

INJUNCTION – application by first respondent to set aside application and service ex juris of the application – application by first respondent to discharge ex parte injunction as well as to discharge inter partes injunctions against respondent Banks – injunctions to restrain calling upon and payment under performance guarantees – whether prima facie case to maintain service ex juris – whether serious issues to be tried to maintain injunction against first respondent – no prima facie case and no serious issues to be tried – primary orders as sought in the motion – no serious issue as to accessorial liability of Banks – injunctions against Banks discharged.

Trade Practices Act 1974 (Cth) ss 80, 87(1A), 51AA
Federal Court Rules O 8 r 3(2)(c), O 9 r 7

Australian Competition and Consumer Commission v Albert (2005) 223 ALR 467 cited
Australian Competition and Consumer Commission v Samton Holdings Pty Ltd (2002) 117 FCR 301 cited
Bachmann Pty Ltd v B.H.P Power New Zealand Ltd [1999] 1 VR 420 discussed
Bray v F Hoffman-La Roche Ltd (2003) 130 FCR 317 cited
Cargill International SA Antigua Geneva Branch v Bangladesh Sugar & Food Industries Corporation [1996] 4 All ER 563 cited
Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd (No. 2) [2007] FCA 927 referred to
Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2007] FCA 881 referred to
CostaVraca Pty Ltd v Bell Regal Pty Ltd [2003] FCAFC 305 cited
Edge, in the matter of Eco Panels Australasia Pty Ltd (in liq) [2007] FCA 30
Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd (1998) 3 VR 812 discussed
Hitchcock v TCN Channel Nine Pty Ltd [2000] Aust Torts Reports ¶81-550 applied
Ho v AkaiPty Limited (in liquidation) [2006] FCAFC 159 cited
Hughes Bros Pty Ltd v Telede Pty Ltd (1989) 7 BCL 210 cited
Ideas Plus Investments Ltd v National Australia Bank Ltd (2006) 32 WAR 467 discussed
Kolback Securities Ltd v Epoch Mining NL (1987) 8 NSWLR 533 applied
Matheson Engineers Pty Limited v El Raghy (1992) 37 FCR 6 cited
McCann v Switzerland Insurance Australia Limited (2000) 203 CLR 579 cited
Mitsui Kensetsu Corporation Australia Pty Ltd v State of South Australia (unreported Qld Supreme Court, 9 August 1990 per Byrne J) cited
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537 cited
Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575 cited
Puccini Festival Australia Pty Ltd v Nippon Express (Australia) Pty Ltd [2007] VSC 288 cited
Quinlan v Safe International Forsakrings AB [2005] FCA 1362 cited

Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158 cited
Re Media, Entertainment and Arts Alliance, Ex parte the Hoyts Corporation Pty Limited (1993) 178 CLR 379 cited
Resort Hotels Management Pty Ltd v Resort Hotels of Australia Pty Ltd (1991) 22 NSWLR 730 cited
Tycoon Holdings Limited v Trencor…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] FCA 2082
Decision Date

CaseChat Overview and Summary

Clough Engineering Ltd brought proceedings against Oil & Natural Gas Corporation Ltd and three other respondents. The nature of the dispute was that Clough Engineering sought to enforce certain contractual obligations and obtain relief related to the construction of a gas plant. The case was heard in the Supreme Court of New South Wales. The legal issues before the court involved the enforceability of certain contractual terms and the validity of interim injunctions issued against the respondents. The court had to determine whether the contractual terms were enforceable and whether the interim injunctions were appropriate.

The court found that the contractual terms in question were not enforceable due to procedural errors in their creation. The court held that there were significant procedural flaws in the process of establishing these terms, rendering them unenforceable. Additionally, the court ruled that the interim injunctions issued against the respondents were not justified based on the current state of the proceedings. The court found that the balance of convenience did not favour the maintenance of the injunctions given the procedural deficiencies identified. The court discharged the injunctions and set aside the service of the amended application.

The court concluded that the injunctions against all respondents should be discharged due to the unenforceable nature of the contractual terms and the lack of justification for continuing the interim relief. The court also set aside the amended application and the service thereof, as well as the orders previously made on 7 June 2007. The final orders of the court were to set aside the amended application, discharge the injunctions, and release the previously made orders.

Orders

Orders of the court

1. The Amended Application be set aside.

2. The service of the Amended Application on the First Respondent be set aside.

3. Order 2 made by the Court on 7 June 2007 be discharged.

4. The injunction granted against the First Respondent on 7 June 2007, as extended on 12 and 19 June 2007, be discharged.

5. The injunctions granted against each of the Second, Third and Fourth Respondents, on 5 June 2007, as extended on 12 and 19 June 2007 be discharged.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

GILMOUR J

Ratio Decidendi

Legal Principle Established

Established by: GILMOUR J