Burwood Council v Ralan Burwood Pty Ltd (No 3)

Link copied
Case Copied 75 min read

Court of Appeal


Supreme Court


New South Wales

Medium Neutral Citation: Burwood Council v Ralan Burwood Pty Ltd (No 3) [2014] NSWCA 404
Hearing dates:14, 15, 16 October 2014
Decision date: 27 November 2014
Before: McColl JA at [1];
Barrett JA at [2];
Sackville AJA at [3]
Decision:

1. Subject to the orders made on 6 June 2014, the motion filed by the first respondent (Ralan) on 3 April 2014 be dismissed.

2. The appeal be dismissed.

3. The appellant (the Council) pay Ralan's costs of the appeal, including Ralan's costs thrown away by reason of the vacation of the hearing on 9 April 2014 and the costs of the motions filed by Ralan on 3 April 2014 and by the Council on 28 May 2014.

[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]

Catchwords:

ENVIRONMENT AND PLANNING - validity of construction certificates - primary judge erred in finding that construction certificates were not inconsistent with development consent - whether finding of inconsistency would render construction certificates invalid - scope and purpose of statutory regime construed as a whole does not require a finding of invalidity where construction certificates found to be inconsistent with development consent

ENVIRONMENT AND PLANNING - where construction certificates found to be inconsistent with development consent - whether development was carried out otherwise than in accordance with the development consent - application of s 80(12) of the Environmental Planning and Assessment Act - construction certificates deemed to form part of development consent

ENVIRONMENT AND PLANNING - responsibility for carrying out development - whether respondent could be held responsible for any failure to carry out the development in accordance with the Environmental Planning and Assessment Act

ENVIRONMENT AND PLANNING - exercising a function under the Environmental Planning and Assessment Act - respondent developer was not exercising a power, authority or duty directly conferred or imposed by the Act

APPEAL - where primary judge in the Land and Environment Court erred in finding construction certificates were inconsistent with development consent - whether Court of Appeal can make findings to resolve the factual question - whether Court of Appeal can proceed assuming that factual finding to resolve question of law as to validity of challenged construction certificates
Legislation Cited:

Building Professionals Act 2005 (NSW) ss 5, 5A, 7, 8, 19, 21, 22, 31, 39, 40, 85, sch 3
Environmental Planning and Assessment Act 1979 (NSW)
Environmental Planning and Assessment Amendment Act 1997 (NSW)
Environmental Planning Legislation Amendment Act 2006 (NSW)
Interpretation Act 1987 (NSW) s 9(2)
Supreme Court Act 1970 (NSW) s 75A
Trade Practices Act 1974 (Cth) s 75B

Environmental Planning and Assessment…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Burwood Council v Ralan Burwood Pty Ltd (No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWCA 404
Decision Date

CaseChat Overview and Summary

In the case of *Burwood Council v Ralan Burwood Pty Ltd (No 3)*, the dispute concerned the validity of construction certificates issued by Burwood Council in relation to a development carried out by Ralan Burwood Pty Ltd. The Council appealed a decision of the primary judge in the Land and Environment Court, who had found that the construction certificates were not inconsistent with the development consent. The appeal was heard by McColl and Barrett JJA, and Sackville AJA.

The Court of Appeal was required to determine whether the primary judge erred in finding that the construction certificates were not inconsistent with the development consent. A further issue was whether, if such inconsistency were found, it would render the construction certificates invalid. The Court also considered whether the development had been carried out otherwise than in accordance with the development consent, and the application of section 80(12) of the *Environmental Planning and Assessment Act* (EPA Act), which deems construction certificates to form part of the development consent. The Court also examined the responsibility of the respondent developer for carrying out the development in accordance with the EPA Act.

The Court of Appeal reasoned that the scope and purpose of the statutory regime, when construed as a whole, did not necessitate a finding of invalidity where construction certificates were found to be inconsistent with the development consent. The Court noted that the primary judge had erred in their factual finding regarding the inconsistency. While the Court of Appeal had the capacity to make findings to resolve factual questions, it proceeded by assuming the primary judge's factual finding of inconsistency to address the legal question of the validity of the construction certificates. The Court ultimately dismissed the appeal and ordered the Council to pay Ralan's costs.

Orders

Orders of the court

1. Subject to the orders made on 6 June 2014, the motion filed by the first respondent (Ralan) on 3 April 2014 be dismissed.

2. The appeal be dismissed.

3. The appellant (the Council) pay Ralan's costs of the appeal, including Ralan's costs thrown away by reason of the vacation of the hearing on 9 April 2014 and the costs of the motions filed by Ralan on 3 April 2014 and by the Council on 28 May 2014.

[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

The fifth respondent (Owners Corporation) was created by virtue of registration of the strata scheme in respect of the development. The Owners Corporation was served with the amended notice of appeal but did not wish to be heard on the appeal. Despite being encouraged to file a submitting appearance, the Owners Corporation did not do so. The hearing of the appeal was listed for two days, commencing on 9 April 2014. On 3 April 2014, Ralan filed a notice of motion seeking an order that the appeal be dismissed for want of necessary parties, namely the owners and occupiers of lots in the Strata Plan. In the alternative, Ralan sought an order requiring the Council to serve notice of the proceedings on all owners and occupiers of the lots. On 9 April 2014, the Court vacated the hearing and gave directions for the hearing of Ralan's motion before me. The Council ultimately filed a motion seeking representative orders as a mechanism to overcome the difficulty that the orders for rectification work, if granted, would affect the interests of the proprietors and occupiers of lots in the Strata Plan. In a judgment delivered on 6 June 2014 (Burwood Council v Ralan Burwood Pty Ltd (No 2) [2014] NSWCA 179) I made the following orders: The hearing of the appeal took place over three days, from 14 to 16 October 2014. No owner or occupier took advantage of the opportunity to be joined as a party to the appeal or to make submissions. Both parties sought to adduce further evidence on the appeal in reliance on s 75A(7) of the Supreme Court Act 1970 (NSW). Although there was some debate, ultimately the further evidence was admitted without objection. The Council's further evidence included photographs of the façades of the completed building which were clearer than similar photographs in the Appeal Books. Ralan's further evidence was an affidavit upon which it relied to support its contention that if the Council's appeal should succeed, the matter should be remitted to the L & E Court. A considerable number of statutory provisions and regulations were referred to in submissions. It is convenient to set out here the provisions of particular significance to the appeal. The Council brought these proceedings pursuant to s 123(1) and seeks relief pursuant s 124 of the EPA Act. These sections are in Div 3 of Part 6 of the EPA Act and relevantly provide as follows: Section 122(a) of the EPA Act states that in Div 3 of Part 6 a reference to "a breach of this Act" is a reference to The foundation of the Council's claim for relief is that Ralan breached s 76A(1) of the EPA Act. The sub-section provides as follows: Division 2 of Part 4 of the EPA Act establishes detailed procedures, including the opportunity for public submissions, for the consideration and determination of a development application. In determining a development application, a consent authority (in this case the Council) is to take into account a number of matters specified in s 79C(1) of the EPA Act, including: