Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Owners Corporation SP 82076 v Taricon Pty Ltd [2017] NSWCATCD 37 Hearing dates: 20 December 2016; written submissions 17 January, 3 February 2017 Decision date: 04 May 2017 Jurisdiction: Consumer and Commercial Division Before: L Pearson, Principal Member Decision: 1. The application is dismissed.
2. Any application for an order for costs is to be made within 14 days of the date of these reasons and to be accompanied by any submissions and evidence in support of such an application.
3. The party against whom an application for an order for costs is made is to file and serve submissions and any evidence in reply no later than 14 days after the date in order 2.
4. Any application for costs will be determined on the papers. If either party wishes to be heard in person, that party must notify the Registrar within 7 days of the date in order 3, and the Registrar will advise the parties.Catchwords: HOME BUILDING: Breach of statutory warranties – whether claim lodged within time – practical completion – issue of occupation certificate – estoppel – additional cause of action in contract Legislation Cited: Building Professionals Act 2005 (NSW)
Building Professionals Amendment Act 2008 (NSW)
Civil and Administrative Tribunal Act 2013 (NSW)
Environmental Planning and Assessment Act 1979 (NSW)
Environmental Planning and Assessment Regulation 2000 (NSW)
Environmental Planning and Assessment Further Amendment Regulation 2008
Home Building Act 1989 (NSW)
Home Building Amendment Act 2011 (NSW)
Home Building Amendment Act 2014 (NSW)
Limitation Act 1969 (NSW)Cases Cited: Amaya v Estate Property Holdings Pty Ltd [2010] NSWSC 32
Amaya v Everest Property Holdings Pty Ltd [2010] NSWCA 315
Bankstown City Council v Ramahi (No 2) [2016] NSWLEC 34
Burwood Council v Ralan Burwood Pty Ltd (No 3) [2014] NSWCA 404
Cessnock City Council v Laila Investments Pty Ltd [2012] NSWLEC 206
Griffith v Gates (Home Building) [2013] NSWCTTT 302
Karan v Champion Homes Sales Pty Ltd [2016] NSWCATCD 84
Port of Melbourne Authority v Anshun Pty Ltd (1981) 147 CLR 589
Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28; 104 CLR 355
Ryde Developments Pty Ltd v The Property Investors Alliance Pty Ltd (No 4) [2017] NSWSC 436
Smithers v Parisi (Home Building) [2008] NSWCTTT 1299
Tudor Developments Pty Ltd v Makeig (2008) 72 NSWLR 624; [2008] NSWCA 263
Windy Dropdown Pty Ltd v Warringah Council [2000] NSWLEC 240Category: Principal judgment Parties: Owners Corporation SP82076 (Applicant)
Taricon Pty Ltd (Respondent)Representation: Counsel: Mr N Silva (Applicant)
Solicitors: Mr J Karacan, Hutchison Lawyers (Applicant)
Mr D Indevar, O’Brien Lawyers (Respondent)
File Number(s): HB 16/13982 Publication restriction: Nil
Reasons for decision
-
On 17 March 2016 Mr Con Veneziano, Secretary of the Owners Corporation SP 82076, applied on behalf of the Owners Corporation to the Tribunal under the Home Building Act 1989 (NSW) (the HB Act) seeking “an order regarding incomplete rectification works for SP 82076 being residential premises at 35-39 Deakin…
Keep reading for free
Create a free CaseChat account to read Owners Corporation SP 82076 v Taricon Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWCATCD 37
- Decision Date
CaseChat Overview and Summary
The legal issues before the court encompassed the interpretation and application of statutory warranties under the Home Building Act 1989, specifically focusing on the definition of 'practical completion' and the issuance of an occupation certificate. Additionally, the court had to consider whether estoppel principles applied to prevent Taricon from raising certain defences and whether the owners corporation could introduce an additional cause of action based on contract law.
The court meticulously examined the statutory provisions and case law to determine the meaning of 'practical completion' and whether the occupation certificate issued was valid. It concluded that the claim was not lodged within the required timeframe, rendering it invalid. Furthermore, the court found that estoppel did not apply to preclude Taricon from raising its defences, and the additional cause of action based on contract was deemed inadmissible. Consequently, the application was dismissed, and the court outlined the procedure for any subsequent applications for costs.
The final orders mandated the dismissal of the application and stipulated a timeframe for any subsequent applications for costs, including the requirement for submissions and evidence to be provided within 14 days. The court also indicated that any request for a personal hearing regarding the costs application must be communicated within seven days of the order date.
Orders
Orders of the court
1. The application is dismissed.
2. Any application for an order for costs is to be made within 14 days of the date of these reasons and to be accompanied by any submissions and evidence in support of such an application.
3. The party against whom an application for an order for costs is made is to file and serve submissions and any evidence in reply no later than 14 days after the date in order 2.
4. Any application for costs will be determined on the papers. If either party wishes to be heard in person, that party must notify the Registrar within 7 days of the date in order 3, and the Registrar will advise the parties.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi