Supreme Court
New South Wales
Medium Neutral Citation: Buildcorp Group Pty Ltd v Strata Plan 125 [2025] NSWSC 501 Hearing dates: 22 May 2025 Date of orders: 17 June 2025 Decision date: 17 June 2025 Jurisdiction: Equity - Commercial List Before: Peden J Decision: At [90]
Catchwords: CONTRACTS — Construction — Interpretation — Whether plaintiff entitled to payment from defendant under special condition for what plaintiff contends is additional work — Scope within contract sum
Legislation Cited: Supreme Court Act 1970 (NSW) s 63
Cases Cited: AFC Holdings Pty Ltd v Shiprock Holdings Pty Ltd [2010] NSWSC 985
Ainsworth v Criminal Justice Commission (1992) 175 CLR 564
Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
Laundy Hotels (Quarry) Pty Ltd v Dyco Hotels Pty Ltd (2023) 276 CLR 500
Lohar Corp Pty Ltd v Dibu Pty Ltd (1975) 1 BPR 9177
Madsen v Darmali (No 3) [2024] NSWSC 582
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104
Strike Australia Pty Ltd v Data Base Corporate Pty Ltd [2019] NSWCA 205
XL Insurance Co SE v BNY Trust Company of Australia Ltd [2019] NSWCA 215
Category: Principal judgment Parties: Buildcorp Group Pty Ltd (plaintiff)
Strata Plan 125 (defendant)Representation: Counsel:
Solicitors:
M Ashurst SC with L Corbett (plaintiff)
D Miller SC with B Le Plastrier (defendant)
BCP Lawyers & Consultants (plaintiff)
Crisp Law (defendant)
File Number(s): 2023/00426245 Publication restriction: Nil
JUDGMENT
-
In December 2021, Buildcorp Group Pty Ltd agreed to provide work pursuant to a “design and build contract” for the Owners of Strata Plan 125, which is located at Blues Point Tower in McMahons Point, New South Wales.
-
The Owners sought primarily the replacement of all the building’s external windows and doors, which had reached the end of their working life. The heritage status of the building meant that the façade (significantly comprising masonry walls and sills below the windows) had to be replaced with “like” materials.
-
On 8 March 2021, the Owners’ agent invited Buildcorp to tender for the “Heritage Façade Maintenance works”. The Owners provided Buildcorp with various reference documents, including the Council’s approval for the works and various reports by consultants dated between 2018 and 2021, detailing the Owners’ lengthy investigation into the defects in the façade and their rectification.
-
Buildcorp won the tender. It has since completed all the remediation work required by the Owners and has been paid the contract sum. In completing the work, Buildcorp carried out some strengthening work to windowsills with brackets and by way of steel beams. It claimed those works were not included in the contract sum and instead fell within Special Condition in item 2 of Annexure Part G of the contract (“Clarifications and Exclusions”), and entitled it to be paid for the “variation” works. That clause provides (emphasis added):
The parties agree that [the Owners’] project requirements is subject to the following clarifications and…
Keep reading for free
Create a free CaseChat account to read Buildcorp Group Pty Ltd v Strata Plan 125 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NSWSC 501
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were primarily concerned with the interpretation of the construction contract, specifically whether certain additional work performed by Buildcorp fell within the scope of the contract sum or if it constituted additional work for which extra payment should be made. The court had to consider the terms of the contract, including special conditions, and whether the additional work was reasonably within the scope of what was expected under the contract.
The court found that the additional work performed by Buildcorp was within the scope of the original contract. It determined that the special conditions of the contract did not entitle Buildcorp to additional payment, as the work in question was not beyond what was reasonably expected under the terms of the contract. The court relied on the principle that additional work should be clearly identified and outside the scope of the original contract for additional payment to be warranted. Consequently, the court ruled in favour of Strata Plan 125 and against Buildcorp's claim for additional payment.
The court ordered that Buildcorp was not entitled to the additional payment claimed and that Strata Plan 125 was only liable for the contract sum as originally agreed. The decision highlights the importance of clear contract terms and the need for any additional work to be explicitly identified and agreed upon to justify additional payment.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.