QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Beatton v Strongbridge Homes Pty Ltd [2025] QCAT 184
PARTIES:
GEORGE BEATTON (applicant)
v
STRONGBRIDGE HOMES PTY LTD (respondent)
APPLICATION NO/S:
BDL104-22
MATTER TYPE:
Building matters
DELIVERED ON:
12 May 2025
HEARING DATE:
9 May 2024
HEARD AT:
Brisbane
DECISION OF:
Member Deane
ORDERS:
1. Strongbridge Homes Pty Ltd is to pay George Beatton damages in the sum of $19,500.00 (incl GST), by:
4:00pm on 20 June 2025.
2. Any application for costs is to be made by filing in the Tribunal two (2) copies and giving to the other party one (1) copy of any submissions and evidence relied upon, by:
4.00pm on 27 June 2025.
3. If any application for costs is made in accordance with order 2 above, then:
(a) The other party must file in the Tribunal two (2) copies and give to the party making the application for costs one (1) copy of any submissions and evidence in response, by:
4.00pm on 25 July 2025.
(b) The party making the application for costs must file in the Tribunal two (2) copies and give to the other party one (1) copy of any submissions and evidence in reply, by:
4.00pm on 15 August 2025.
(c) Unless otherwise directed, the application for costs will be decided on the papers and without an oral hearing after 15 August 2025.
4. If no application for costs is made in accordance with order 2 above, then there shall be no order as to costs.
CATCHWORDS:
TORTS – NEGLIGENCE – DUTY OF CARE – STANDARD OF CARE, SCOPE OF DUTY AND SUBSEQUENT BREACH – DAMAGES AND CAUSATION – GENERALLY – claim by subsequent homeowner – whether breach of duty by builder in undertaking building work – assessment of damages
LIMITATION OF ACTIONS – CONTRACTS, TORTS AND PERSONAL ACTIONS – where initial works were undertaken more than six years before the application was filed – where rectification works undertaken less than six years before the application was filed
Civil Liability Act2003 (Qld), s 4, s 9, s 11, sch 2
Human Rights Act2019 (Qld), s 9, s 11, s 13, s 24, s 25, s 31, s 48
Limitation of Actions Act 1974 (Qld), s 10
Queensland Building and Construction Commission Act 1991 (Qld), s 3, s 77, sch 1B s 4, sch 2
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 3, s 100, s 102, s 105Queensland Civil and Administrative Tribunal Rules 2009 (Qld), r 86
Atkinson & Anor v Van Uden [2020] QCAT 259
Bryan v Maloney (1995) 182 CLR 609
Campbell v Queensland Building and Construction Commission [2021] QCATA 34
Cerda v Jacob [2020] QCATA 57
Chau’s & Sons t/as Holiday Air Conditioning and Refrigeration Qld v Karam [2024] QCAT 476
Knox v Bellamy [2021] QCAT 192
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
Mallonland Pty Ltd v Advanta Seeds Pty Ltd [2024] HCA 25
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
P Burnitt, Director
REASONS FOR…
Continue reading Beatton v Strongbridge Homes Pty Ltd
Sign in free to access the full text
- AGLC
- Beatton v Strongbridge Homes Pty Ltd [2025] QCAT 184
- Case
- [2025] QCAT 184
- Decision Date
CaseChat Overview and Summary
The court determined that Strongbridge Homes Pty Ltd owed a duty of care to subsequent homeowners for defects in their building work. It found that the builder breached this duty by failing to properly waterproof the house, leading to water ingress and subsequent damage to Mr Beatton's property. The court assessed the damages and concluded that the breach directly caused the damage claimed. The court also considered the limitation periods and found that while the initial works were beyond the limitation period, the subsequent rectification works fell within the limitation period, allowing the claim to proceed.
Consequently, the Tribunal ordered Strongbridge Homes Pty Ltd to pay Mr Beatton damages in the sum of $19,500.00 (including GST) by 20 June 2025. The court outlined a process for any application for costs to be made, specifying deadlines for filing and responding to submissions and evidence. If no application for costs was made, there would be no order regarding costs.
Orders
Orders of the court
1. Strongbridge Homes Pty Ltd is to pay George Beatton damages in the sum of $19,500.00 (incl GST), by:
4:00pm on 20 June 2025.
2. Any application for costs is to be made by filing in the Tribunal two (2) copies and giving to the other party one (1) copy of any submissions and evidence relied upon, by:
4.00pm on 27 June 2025.
3. If any application for costs is made in accordance with order 2 above, then:
(a) The other party must file in the Tribunal two (2) copies and give to the party making the application for costs one (1) copy of any submissions and evidence in response, by:
4.00pm on 25 July 2025.
(b) The party making the application for costs must file in the Tribunal two (2) copies and give to the other party one (1) copy of any submissions and evidence in reply, by:
4.00pm on 15 August 2025.
(c) Unless otherwise directed, the application for costs will be decided on the papers and without an oral hearing after 15 August 2025.
4. If no application for costs is made in accordance with order 2 above, then there shall be no order as to costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.