FEDERAL COURT OF AUSTRALIA
Basetec Services Pty Ltd v Leighton Contractors Pty Ltd [2014] FCA 991
Citation: Basetec Services Pty Ltd v Leighton Contractors Pty Ltd [2014] FCA 991 Parties: BASETEC SERVICES PTY LTD ABN 30 086 798 361 v LEIGHTON CONTRACTORS PTY LTD ABN 98 000 893 667 File number: SAD 84 of 2014 Judge: BESANKO J Date of judgment: 12 September 2014 Catchwords: PRACTICE AND PROCEDURE – security for costs – where company operates on “cash surplus” basis – where company did not disclose up-to-date financial information – where company did not disclose the person or persons who stand behind it – where company claims providing security would adversely affect the future conduct of its business – Federal Court of Australia Act 1976 (Cth) s 56, Corporations Act 2001 (Cth) s 1335.
Held: Application granted. Security to be provided for period up to the proceeding being set down for trial.
Legislation: Building Work Contractors Act 1995 (SA)
Competition and Consumer Act 2010 (Cth) Sch 2 ss 21, 22
Corporations Act 2001 (Cth) s 1335
Federal Court of Australia Act 1976 (Cth) s 56
Federal Court Rules 2011 (Cth) r 19.01Cases cited: Ariss and Another v Express Interiors Pty Ltd (in liquidation) [1996] 2 VR 507
Beach Petroleum NL and Another v Johnson and Others (1992) 7 ACSR 203
Health Information Pharmacy Franchising Pty Ltd v Khoo [2010] FCA 438
Livingspring Pty Ltd v Kliger Partners (2008) 20 VR 377
Smart Company Pty Ltd v Clipsal Australia Pty Ltd [2009] FCA 1253
Soul Pattinson Telecommunications Pty Ltd v Subex Americas Inc [2009] FCA 651Date of hearing: 8 August 2014 Place: Adelaide Division: GENERAL DIVISION Category: Catchwords Number of paragraphs: 54 Counsel for the Applicant: Mr D Riggall Solicitor for the Applicant: Ms A Forsyth, Basetec Services Pty Ltd Counsel for the Respondent: Ms G Walker Solicitor for the Respondent: Herbert Smith Freehills
IN THE FEDERAL COURT OF AUSTRALIA
SOUTH AUSTRALIA DISTRICT REGISTRY
GENERAL DIVISION
SAD 84 of 2014
BETWEEN: BASETEC SERVICES PTY LTD ABN 30 086 798 361
Applicant/Cross‑RespondentAND: LEIGHTON CONTRACTORS PTY LTD ABN 98 000 893 667
Respondent/Cross‑Claimant
JUDGE:
BESANKO J
DATE OF ORDER:
12 SEPTEMBER 2014
WHERE MADE:
ADELAIDE
THE COURT ORDERS THAT:
1.The respondent’s interlocutory application dated 17 June 2014 be adjourned for further consideration to 19 September 2014 at 2.15 pm.
Note:Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
IN THE FEDERAL COURT OF AUSTRALIA
SOUTH AUSTRALIA DISTRICT REGISTRY
GENERAL DIVISION
SAD 84 of 2014
BETWEEN: BASETEC SERVICES PTY LTD ABN 30 086 798 361
Applicant/Cross‑RespondentAND: LEIGHTON CONTRACTORS PTY LTD ABN 98 000 893 667
Respondent/Cross‑Claimant
JUDGE:
BESANKO J
DATE:
12 SEPTEMBER 2014
PLACE:
ADELAIDE
REASONS FOR JUDGMENT
INTRODUCTION
This is an application by the respondent for security for costs. The respondent relies on the powers given to this Court to make such an order in s 56 of the Federal Court of Australia Act 1976 (Cth) (“Federal Court Act”) (see…
Keep reading for free
Create a free CaseChat account to read Basetec Services Pty Ltd v Leighton Contractors Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] FCA 991
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining the appropriate amount of security for costs that Basetec Services should provide to Leighton Contractors. This decision was influenced by the complexity of the case, the significant amount of money at stake, and the potential for escalating costs as the litigation progresses. The court had to balance the interests of both parties, considering the risk of significant financial exposure if the case were to proceed to trial and the possibility of an unfavorable outcome for Leighton Contractors.
In its reasoning, the court acknowledged the numerous variables in the case and the substantial amount sought by Leighton Contractors. The court estimated that the costs up to the point where the case would be ready for trial would be approximately $300,000. This estimate was based on the current evidence and the potential for further discovery and development of the case. Consequently, the court ordered that Basetec Services provide security for costs in the amount of $300,000. The court also allowed the parties an opportunity to agree on the form of security, with the matter to be relisted for final orders if an agreement was reached or for the determination of the form of security if no agreement was made.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.