AUST EDUC UNION (FORMERLY SAIT INC) v GRIEVE
[2000] SASC 381
WILLIAMS J
1. The requirements of the Full Court’s order
On 4 June 1998, I dismissed the claim of the plaintiff for damages based upon an allegation that the defendant had failed properly to carry out the terms of his engagement as architect in connection with the removal of asbestos from the plaintiff’s building. By order dated 13 May 1999, the Full Court allowed an appeal against my decision and quashed my order of dismissal of the claim; the Full Court ordered that, subject to the grant of an extension of time for commencement of the proceedings pursuant to the Limitations of Actions Act 1936 (SA) (“The Act”) the plaintiff recover damages to be assessed. The matter has been referred back to me by the Full Court for further hearing of the issues arising under The Act and, (subject to the resolution thereof in favour of the plaintiff), the assessment of the damages payable by the defendant.
The essence of the Full Court’s decision which I am required to apply is as follows:
(1)... The defendant failed to make a personal inspection of work:
(a).... following the removal of asbestos and before the application of PVA
and
(b)... at the conclusion of the job.
The defendant failed to detect that the extent of asbestos removal and the extent of PVA treatment was inadequate. If Mr Grieve had detected these deficiencies he should have given directions to the asbestos contractor to undertake remedial work.
(2)... That by failing to inspect at the two critical stages abovementioned and by failing to give the consequential directions the defendant was liable (either in breach of contract or in negligence) in failing to ensure that the extent of the removal of the asbestos was “as complete as could practically be achieved” and that the affected areas were thereafter “adequately and completely sealed off with PVA paint”.
My decision of 4 June 1998 in favour of the architect was reached upon the basis that he was entitled to rely upon the assessment of another expert, in this instance, the independent asbestos monitor who had been contracted to the job, but the Full Court’s decision required that the plaintiff personally undertake an inspection upon the two critical occasions.
It is common ground between counsel for present purposes, that it is unnecessary to separately consider the two inspections which were required. If the architect had inspected on either occasion, then the need for further work would have been apparent. However, the failure to spray adequately with PVA paint would only have been apparent at the conclusion of the job.
The application of the Limitations of Actions Act
On 14 January 1994, the plaintiff became aware of the existence of loose asbestos in the ceiling cavity of Raggatt House; the present proceedings were commenced on 10 January 1995, that is within 12 months of the ascertainment by the plaintiff of what is claimed to be a “material fact”…
Keep reading for free
Create a free CaseChat account to read Aust Educ Union (Formerly Sait Inc) v Grieve No. Scgrg-95-29 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2000] SASC 381
- Decision Date
CaseChat Overview and Summary
The court had to decide whether to allow the plaintiff to adduce further evidence after the trial had concluded, considering the Full Court's decision in Australian Education Union (SA Branch) v Grieve. The plaintiff argued that the new evidence would provide a more accurate calculation of damages, while the defendant argued that the proposed evidence was speculative and would not provide a significant benefit. Additionally, the plaintiff was not willing to recall witnesses for further cross-examination, which could potentially lead to an unfair outcome.
The court ruled that the proposed evidence was of limited value and may make the task of the plaintiff's counsel a little easier in terms of providing the plaintiff with some additional material on which to hang an argument. However, the court was not persuaded that any such calculation was likely to be any more realistic than would be the case if the existing evidence was not supplemented. The plaintiff was not willing to give an undertaking to recall witnesses if required for further cross-examination, which was a significant fact. The equilibrium which was established at the close of the last trial would be upset if any re-opening of the evidence was now allowed. The court ruled accordingly, and the plaintiff was not allowed to adduce further evidence.
The court's ruling was that the proposed evidence was of limited value, and the plaintiff was not willing to give an undertaking to recall witnesses if required for further cross-examination. The court was not persuaded that any such calculation was likely to be any more realistic than would be the case if the existing evidence was not supplemented. The equilibrium which was established at the close of the last trial would be upset if any re-opening of the evidence was now allowed. The court ruled that the plaintiff was not allowed to adduce further evidence.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.