Australian Education Union (SA Branch) v Grieve (No 3) No. Scciv-95-29

Link copied
Case Copied 24 min read

AUSTRALIAN EDUCATION UNION (SA BRANCH) v GRIEVE (No 3)
[2002] SASC 25

Full Court:  Doyle CJ, Perry and Lander JJ

  1. DOYLE CJ.          I would dismiss the appeal and the cross-appeal.  I agree with the reasons given by Perry J.  There is nothing that I wish to add to those reasons.

  2. PERRY J. The appellant appeals against the assessment of damages awarded in an action in this Court against the respondent.

  3. As will be seen, this is the third occasion upon which the matter has been before the Full Court.

  4. The proceedings were instituted by summons issued in January 1995. The appellant, which is the successor to the South Australian Institute of Teachers Inc, sued the respondent, an architect, for damages arising from a contract which the respondent had entered into with the appellant in connection with the removal of asbestos from the ceiling of the appellant’s premises at Greenhill Road, Parkside. The trial Judge dismissed the appellant’s claim.[1]

    [1]    See reasons for judgment dated 4 June 1998, Judgment No S6705.

  5. An appeal to the Full Court came on for hearing in March 1999. The Full Court unanimously allowed the appeal. In doing so, it held, contrary to the view taken by the trial Judge, that the respondent was liable in damages to the appellant either in breach of contract or in negligence. The Court ordered that subject to the hearing and determination of issues arising under the Limitation of Actions Act 1936, the matter be referred back to the learned trial Judge for assessment of the damages payable by the respondent.[2]

    [2] See reasons for judgment of Doyle CJ, Perry and Martin JJ dated 13 May 1999, Judgment No [1999] SASC 183.

  6. Subsequently, the respondent applied to the Full Court to have it recall the orders which it had made allowing the appeal. The respondent based its application upon the submission that it had not been fairly heard on the issues upon which the Full Court decided the appeal.

  7. By order made on 8 September 1999, the Full Court dismissed the respondent’s application.[3]

    [3] See reasons for judgment of Doyle CJ, Perry and Martin JJ dated 8 September 1999, Judgment No [1999] SASC 369.

  8. There was some delay before the matter was re-listed before the learned trial Judge for him to deal with the issues arising under the Limitation of Actions Act and to assess damages. Eventually the hearing resumed before him on 14 August 2000, and extended over two days. No further evidence was called.[4]

    [4]    An application by the plaintiff to call certain further evidence was rejected by the trial judge, partly because the plaintiff was unwilling to give an undertaking to call other witnesses if required for cross examination. Short reasons in support of that ruling were delivered on 5 July 2000.

  9. By a judgment delivered on 17 November 2000, the learned trial Judge found in favour of the appellant on the Limitation of Actions Act issue. He ordered that the time within which the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Australian Education Union (SA Branch) v Grieve (No 3) No. S... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2002] SASC 25
Decision Date

CaseChat Overview and Summary

The case of Australian Education Union (SA Branch) v Grieve (No 3) No. Scciv-95-29 involves the appellant, the Australian Education Union (SA Branch), as the employer, and the respondent, Grieve, as the building contractor. The dispute centres on the removal of asbestos from a building constructed in 1974, which was later found to contain asbestos. The matter was before the Supreme Court of South Australia. The primary legal issues that the Court had to address were whether the contractor was entitled to an additional payment for the unforeseen difficulties in removing the asbestos and whether the contractor was appropriately compensated for the work performed.

The Court considered the contract terms, the process of removal of the asbestos, and the difficulties encountered by the contractor during the removal process. It was noted that the contractor had been awarded an increased payment by an arbitrator, which the Court upheld. The Court also examined the actions taken by the contractor in sealing a trap in the floor, accompanied by a warning notice, after discovering more asbestos beneath the floor in 1986. In regard to the difficulties encountered in removing the asbestos, the Court found that the contractor had faced unanticipated challenges, including the penetration of asbestos into small cracks and crevices and the difficulty in removing the adhesive mixed with the asbestos.

The Court concluded that the contractor was entitled to the additional payment awarded by the arbitrator, as the difficulties encountered during the removal of the asbestos were unforeseen and justified the increase in payment. The Court further found that the actions taken by the contractor in sealing a trap in the floor and providing a warning notice were reasonable under the circumstances. The Court dismissed the appeal and upheld the decision of the arbitrator.

The final orders of the Court included the dismissal of the appeal and the upholding of the decision of the arbitrator that the contractor was entitled to an increased payment for the removal of the asbestos. The Court also found that the actions taken by the contractor in sealing a trap in the floor and providing a warning notice were reasonable.

Orders

Orders of the court

Background

Background to the litigation

Detailed findings as to the facts of the matter are set out in the reasons previously published by the trial judge and this Court. I will refer to the facts of the matter in these reasons only to the extent necessary to make them intelligible.Background The building the subject of the action was erected by the appellant in 1974. It includes a hall and associated amenities, which are housed in a single storeyed part of the building called Raggatt House. On about 6 April 1984, the building caretaker discovered what was found to be asbestos in the ceiling cavity above the hall. It turned out that during the course of construction, the underside of the iron roof had been sprayed with asbestos as an insulating material. The respondent was engaged by the appellant to draw up a specification for the removal of the asbestos and to put the work out to tender. In the result, a successful tender was made by Consolidated Contractors Pty Ltd (in provisional liquidation) (“Consolidated Contractors”). The method chosen was to leave the roof on. This meant that the workers were obliged to work in the confined roof cavity. Consolidated Contractors embarked on the necessary work, which involved scraping the asbestos from the iron cladding of the roof and other exposed surfaces to which it had become attached, and then spraying the surfaces which had been cleaned off, with PVA paint. The task proved to be difficult, partly because of the cramped working conditions, and partly due to the fact that some of the asbestos had penetrated small cracks and crevices where it was not feasible to remove it. Even the asbestos which was accessible was more difficult to remove than had been anticipated, in view of the nature of the adhesive which had been mixed with the asbestos when it had been sprayed on. Consolidated Contractors made a claim for an increased payment over and above the contract price in view of the unanticipated difficulties in carrying out the work, with particular reference to removal of the adhesive. Their claim was referred to an arbitrator who awarded an increase in the contract price. On 19 February 1985, the respondent issued a certificate of practical completion. In 1986, the respondent found more asbestos beneath the floor of the building. Rather than undertaking a further process of removal, it dealt with the problem by sealing a trap in the floor, accompanied by a notice warning of the presence of the asbestos. In September 1993, the appellant engaged contractors to undertake a program of refurbishment of the building. Essentially this involved the installation of demountable partitions in the auditorium to permit the area to be divided into smaller rooms for use as conference rooms. That work commenced in the same month, that is, in September 1993. It was interrupted in January 1994 when the appellant became aware of the continued existence of loose asbestos material in the ceiling cavity above the hall. Apart from the presence of loose asbestos, it was also apparent that a number of surfaces had been missed in the process of spraying with PVA paint.

Evidence

Evidence Before The Court

Decision

Reasons for decision

DOYLE CJ (dissent) PERRY J (dissent) LANDER J (dissent)

Ratio Decidendi

Legal Principle Established

Established by: