AUSTRALIAN EDUCATION UNION (SA BRANCH) v GRIEVE (No 3)
[2002] SASC 25Full Court: Doyle CJ, Perry and Lander JJ
DOYLE CJ. I would dismiss the appeal and the cross-appeal. I agree with the reasons given by Perry J. There is nothing that I wish to add to those reasons.
PERRY J. The appellant appeals against the assessment of damages awarded in an action in this Court against the respondent.
As will be seen, this is the third occasion upon which the matter has been before the Full Court.
The proceedings were instituted by summons issued in January 1995. The appellant, which is the successor to the South Australian Institute of Teachers Inc, sued the respondent, an architect, for damages arising from a contract which the respondent had entered into with the appellant in connection with the removal of asbestos from the ceiling of the appellant’s premises at Greenhill Road, Parkside. The trial Judge dismissed the appellant’s claim.[1]
[1] See reasons for judgment dated 4 June 1998, Judgment No S6705.
An appeal to the Full Court came on for hearing in March 1999. The Full Court unanimously allowed the appeal. In doing so, it held, contrary to the view taken by the trial Judge, that the respondent was liable in damages to the appellant either in breach of contract or in negligence. The Court ordered that subject to the hearing and determination of issues arising under the Limitation of Actions Act 1936, the matter be referred back to the learned trial Judge for assessment of the damages payable by the respondent.[2]
[2] See reasons for judgment of Doyle CJ, Perry and Martin JJ dated 13 May 1999, Judgment No [1999] SASC 183.
Subsequently, the respondent applied to the Full Court to have it recall the orders which it had made allowing the appeal. The respondent based its application upon the submission that it had not been fairly heard on the issues upon which the Full Court decided the appeal.
By order made on 8 September 1999, the Full Court dismissed the respondent’s application.[3]
[3] See reasons for judgment of Doyle CJ, Perry and Martin JJ dated 8 September 1999, Judgment No [1999] SASC 369.
There was some delay before the matter was re-listed before the learned trial Judge for him to deal with the issues arising under the Limitation of Actions Act and to assess damages. Eventually the hearing resumed before him on 14 August 2000, and extended over two days. No further evidence was called.[4]
[4] An application by the plaintiff to call certain further evidence was rejected by the trial judge, partly because the plaintiff was unwilling to give an undertaking to call other witnesses if required for cross examination. Short reasons in support of that ruling were delivered on 5 July 2000.
By a judgment delivered on 17 November 2000, the learned trial Judge found in favour of the appellant on the Limitation of Actions Act issue. He ordered that the time within which the…
Keep reading for free
Create a free CaseChat account to read Australian Education Union (SA Branch) v Grieve (No 3) No. S... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2002] SASC 25
- Decision Date
CaseChat Overview and Summary
The Court considered the contract terms, the process of removal of the asbestos, and the difficulties encountered by the contractor during the removal process. It was noted that the contractor had been awarded an increased payment by an arbitrator, which the Court upheld. The Court also examined the actions taken by the contractor in sealing a trap in the floor, accompanied by a warning notice, after discovering more asbestos beneath the floor in 1986. In regard to the difficulties encountered in removing the asbestos, the Court found that the contractor had faced unanticipated challenges, including the penetration of asbestos into small cracks and crevices and the difficulty in removing the adhesive mixed with the asbestos.
The Court concluded that the contractor was entitled to the additional payment awarded by the arbitrator, as the difficulties encountered during the removal of the asbestos were unforeseen and justified the increase in payment. The Court further found that the actions taken by the contractor in sealing a trap in the floor and providing a warning notice were reasonable under the circumstances. The Court dismissed the appeal and upheld the decision of the arbitrator.
The final orders of the Court included the dismissal of the appeal and the upholding of the decision of the arbitrator that the contractor was entitled to an increased payment for the removal of the asbestos. The Court also found that the actions taken by the contractor in sealing a trap in the floor and providing a warning notice were reasonable.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: