Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd

Link copied
Case Copied 53 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Application for Judicial Review)

AUSENCO OPERATIONS PTY LTD & ANOR v FERRETTI INTERNATIONAL OTTOWAY PTY LTD & ANOR

[2020] SASC 46

Judgment of The Honourable Justice Doyle

1 April 2020

ADMINISTRATIVE LAW - JUDICIAL REVIEW - GROUNDS OF REVIEW - JURISDICTIONAL MATTERS

ADMINISTRATIVE LAW - JUDICIAL REVIEW - GROUNDS OF REVIEW - PROCEDURAL FAIRNESS - HEARING - NATURE OF HEARING - OPPORTUNITY TO PRESENT CASE

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS

The plaintiffs seek an order in the nature of certiorari quashing an adjudication determination made by the second defendant (the Adjudicator) under the Building and Construction Industry Security of Payment Act 2009 (SA) (the SOP Act) on 12 November 2019 (the Determination).

The plaintiffs (Ausenco Operations Pty Ltd and Downer EDI Engineering Power Pty Ltd (relevantly trading as the Ausenco Downer Joint Venture (ADJV)) and the first defendant (Ferretti International Ottoway Pty Ltd (Ferretti)) entered into a written contract on or about 23 November 2018 that provided for Ferretti to fabricate and supply piping for the construction of mining infrastructure.

On 2 September 2019, Ferretti served ADJV with a payment claim in the sum of $678,081.18 (including GST) for works done under the Contract.  On 20 September 2019, ADJV responded by serving a payment schedule which stated that the sum payable was “Nil”, and included a claim that it was entitled to set off $201,110 by way of liquidated damages under the contract.

On 11 October 2019, Ferretti lodged an application for adjudication under the SOP Act. It served the adjudication application upon ADJV on 14 October 2019, and it was accepted by the Adjudicator on 18 October 2019. On 22 October 2019, ADJV lodged its adjudication response.

On 12 November 2019, the Adjudicator made the Determination, which required that ADJV pay Ferretti the sum of $410,118.75.  This sum was paid by ADJV to Ferretti on 19 November 2019. 

In arriving at the sum payable in the Determination, the Adjudicator rejected ADJV’s claim that it was entitled to liquidated damages.  The Adjudicator did so on the basis that because he was not able to identify the “Date for Delivery” contemplated by the contract, ADJV had not established any entitlement to liquidated damages under the contract. 

In these judicial review proceedings, ADJV contends the Adjudicator failed to afford it procedural fairness in that he rejected its claim for liquidated damages on a basis not contended for by either party, and in respect of which neither party was given an opportunity to make submissions.  ADJV contends that the Adjudicator thus fell into jurisdictional error, entitling it to the relief sought.

Held, per Doyle J, allowing the application:

1. In considering ADJV’s claimed entitlement to liquidated damages, the Adjudicator was constrained to a consideration of the matters raised by the parties. The only grounds available for rejecting that claim, without at least requesting further submissions from the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ausenco Operations Pty Ltd v Ferretti International Ottoway... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2020] SASC 46
Decision Date

CaseChat Overview and Summary

Ausenco Operations Pty Ltd has sought judicial review of a decision made by an adjudicator under the Building and Construction Industry Security of Payment Act 1999 (NSW). The subject of the dispute is a claim for progress payments under a contract between the parties, which was referred to adjudication by the respondent, Ferretti International Ottoway Pty Ltd. The parties disagree on the amount of the progress payment due and Ferretti was awarded $1,124,538. Ausenco contends that the adjudicator’s decision was legally flawed and should be set aside. The court was required to consider whether the adjudicator had made a jurisdictional error, whether the decision breached the rules of natural justice, and whether the adjudicator had the requisite expertise to make the determination.

The court found that the adjudicator had made a jurisdictional error by misinterpreting the contract and applying an incorrect legal test. The court also found that the adjudicator had breached the rules of natural justice by not providing the parties with an opportunity to make submissions on a particular clause in the contract that was relevant to the payment claim. The court held that the adjudicator’s decision was therefore invalid and should be set aside. The court also found that the adjudicator did not have the requisite expertise to make the determination, as he was not a qualified building practitioner. The court held that the adjudicator’s decision was therefore also invalid on this ground.

The court held that the adjudicator’s decision should be set aside and that the monies paid by Ausenco to Ferretti should be repaid. The court also held that the adjudicator’s decision was not severable from the other components of the determination and that if the court was persuaded that the determination was infected by jurisdictional error warranting the court’s intervention, then the court should set aside the determination and order repayment of the sum paid to Ferretti by Ausenco. The court ordered that the adjudicator’s determination be set aside and that Ausenco be repaid the sum of $1,124,538 by Ferretti within 28 days.

Background

Background to the litigation

Decision

Reasons for decision

Finally, and for completeness, it was not suggested by Ferretti that the Adjudicator’s decision in relation to liquidated damages was severable from the other components of the Determination. It was accepted that if I was persuaded that the Determination was infected by jurisdictional error warranting the Court’s intervention, then I should set aside the Determination and order repayment of the sum paid to Ferretti by ADJV pursuant to that Determination. Conclusion and orders For the reasons set out, I have concluded that the Adjudicator’s Determination was infected by jurisdictional error warranting orders that it be set aside, and that the monies paid by ADJV to Ferretti should be repaid.

Ratio Decidendi

Legal principle established