Supreme Court
New South Wales
Medium Neutral Citation: Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 657 Hearing dates: 14 and 23 May 2013 Decision date: 30 May 2013 Jurisdiction: Equity Division - Technology and Construction List Before: Stevenson J Decision: Declaration that the determination is void
Catchwords: REMEDIES - adjudication determination void - jurisdictional error found in respect of only one issue - whether declaration that the determination is void should be made - whether certiorari should be issued setting aside or quashing the determination - whether, instead, that part of funds paid into Court not attributable to the jurisdictional error should be paid out to the claimant Legislation Cited: Building and Construction Industry Security of Payment Act 1999
Supreme Court Act 1970Cases Cited: Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 491
Asian Pacific Building Corporation Pty Ltd v Aircon Duct Fabrication Pty Ltd [2010] VSC 300
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2012] QSC 346
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd (No 2) [2013] QSC 67
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393
Emergency Services Superannuation Board v Davenport [2004] NSWSC 697
R v Commonwealth Court of Conciliation and Arbitration; Ex parte Ozone Theatres (Aust) Ltd (1949) 78 CLR 389
R v Ross-Jones; Ex parte Green (1984) 156 CLR 185
Solution 6 Holdings Ltd v Industrial Relations Commission of New South Wales [2004] NSWCA 200; (2004) 60 NSWLR 558
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2007] NSWSC 1298Texts Cited: Meagher, Heydon and Leeming, Meagher, Gummow and Lehane's, Equity: Doctrines & Remedies, 4th ed (2002) Category: Consequential orders Parties: Anderson Street Banksmeadow Pty Ltd (plaintiff)
Helcon Contracting Australia Pty Ltd (first defendant)
Adjudicate Today Pty Ltd (second defendant)
Melissa McCurdie (third defendant)Representation: Counsel:
R P V Carey (plaintiff)
F G Kalyk (first defendant)
Solicitors:
D Massey (plaintiff)
KQ Lawyers (first defendant)
Moray & Agnew Lawyers (second and third defendants)
File Number(s): SC 2013/92743 Publication restriction: Nil
Judgment
Introduction
On 3 May 2013 I published my reasons in this matter (Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 491).
I have now heard argument as to what orders should be made to give effect to those reasons. In this judgment, I shall use the abbreviations as in my reasons of 3 May 2013.
The Adjudicator made a determination under the Act that Anderson Street should pay Helcon a progress payment of $104,857.50.
In making the Determination, the Adjudicator decided that: -
(a) Anderson Street was not entitled to the Deduction; and
(b) Helcon was entitled to the Variation.
I have held that, in determining that Anderson Street was not entitled to the Deduction, the Adjudicator denied…
Keep reading for free
Create a free CaseChat account to read Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Aus... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2013] NSWSC 657
- Decision Date
CaseChat Overview and Summary
The court considered the nature of jurisdictional errors and their impact on the validity of an adjudication determination. It was held that a jurisdictional error that affects only one of multiple claims in an adjudication does not necessarily render the entire determination void. Instead, the court must determine if the error was so significant that it affected the overall fairness and correctness of the decision. In this case, the error was deemed to be confined to one issue, and the remaining claims were determined correctly. The court was tasked with finding a remedy that balanced the need for justice with the practicalities of the construction industry and the role of adjudication in resolving disputes.
The court found that issuing a writ of certiorari to set aside the entire determination would be disproportionate and unjust, given that only one issue was affected by the jurisdictional error. Instead, the court opted to declare that part of the adjudication determination affected by the jurisdictional error was void. The court also ordered that the portion of the funds paid into court, not attributable to the jurisdictional error, be paid out to the claimant. This approach was considered to be fair and practical, as it recognised the validity of the majority of the adjudicator's decision while also addressing the issue of the jurisdictional error.
In conclusion, the court declared the part of the adjudication determination affected by the jurisdictional error to be void. It also ordered that the portion of the funds paid into court, not attributable to the jurisdictional error, be paid out to the claimant. This decision provides guidance on the appropriate remedy when a jurisdictional error is found in relation to only one issue in an adjudication determination. It also highlights the importance of balancing the need for justice with the practicalities of the construction industry and the role of adjudication in resolving disputes.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi