Medium Neutral Citation: Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 491 Hearing dates: 1 May 2013 Decision date: 03 May 2013 Jurisdiction: Equity Division - Technology and Construction List Before: Stevenson J Decision: Adjudication determination void
Catchwords: BUILDING AND CONSTRUCTION - whether adjudication determination void - breach of natural justice - decision on basis not foreshadowed to the parties Legislation Cited: Building and Construction Industry Security of Payment Act 1999 Cases Cited: Brodyn Pty Ltd t/as Time Cost and Quality v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421
John Goss Projects Pty Ltd v Leighton Contractors [2006] NSWSC 798; (2006) 66 NSWLR 707
Laing O'Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818
Musico v Davenport [2003] NSWSC 977
O'Reilly v Mackman [1983] 2 AC 237
Pacific General Securities Ltd v Soliman & Sons Pty Ltd [2006] NSWSC 13Category: Principal judgment Parties: Anderson Street Banksmeadow Pty Ltd (plaintiff)
Helcon Contracting Australia Pty Ltd (first defendant)
Adjudicate Today Pty Ltd (second defendant)
Melissa McCurdie (third defendant)Representation: Counsel:
R P V Carey (plaintiff)
F G Kalyk (first defendant)
Solicitors:
D Massey (plaintiff)
KQ Lawyers (first defendant)
Moray & Agnew Lawyers (second and third defendants)
File Number(s): SC 2013/92743 Publication restriction: Nil
Judgment
Introduction
These proceedings relate to a dispute under the Building and Construction Industry Security of Payment Act 1999 ("the Act").
The plaintiff, Anderson Street Banksmeadow Pty Limited ("Anderson Street") is a builder. By a construction contract dated 1 November 2012 ("the Contract"), Anderson Street retained the first defendant, Helcon Pty Limited ("Helcon"), to perform piling work at a property in Banksmeadow.
The third defendant ("the Adjudicator") is an adjudicator appointed under the Act. On 13 February 2013, the Adjudicator made a determination under the Act that Anderson Street should pay to Helcon a "progress payment" within the meaning of s 8 of the Act of $104,857.50 ("the Determination").
In determining the amount of the progress payment the Adjudicator decided that: -
(a) Anderson Street was not entitled to deduct an amount of $50,006.40 from the amount due to Helcon ("the Deduction"); and
(b) Helcon was entitled to an amount of $54,000 in relation to a variation claimed under the construction contract ("the Variation").
An Adjudication Certification pursuant to s 24 of the Act was issued on 1 March 2013. On the same day, Helcon filed the Adjudication Certificate as a judgment in the District Court of New South Wales pursuant to s 25 of the Act.
Anderson Street commenced these proceedings on 26 March 2013.
On 12 April 2013 Hammerschlag J: -
(a) ordered Anderson Street to pay into Court $115,000 to abide the determination of these proceedings;
(b) noted the undertaking of Helcon that, subject to compliance by Anderson Street with the order in (a) above, it would not seek to enforce its judgment in the District Court until the determination of these proceedings; and
(c) made…
Keep reading for free
Create a free CaseChat account to read Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Aus... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2013] NSWSC 491
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the adjudication determination was void due to a breach of natural justice and whether the adjudicator's decision was based on a matter not previously disclosed to the parties. The respondent contended that the adjudicator had acted outside the scope of the issues raised in the adjudication by considering a new basis of argument, which was not foreshadowed during the proceedings. The court needed to determine if such a breach occurred and if it rendered the determination void. The court also had to consider whether the principles of natural justice were upheld throughout the adjudication process.
The court held that the adjudicator's decision was indeed based on a new argument not previously disclosed to the parties, which constituted a breach of natural justice. The court found that the adjudicator had acted outside the scope of the issues raised in the adjudication, and this failure to adhere to the principles of natural justice rendered the determination void. Consequently, the court ruled that the adjudication determination was invalid and could not be enforced against the respondent. The court's reasoning was based on the necessity for fairness and transparency in adjudication processes, ensuring that all parties are aware of the basis on which decisions are made.
The final orders of the court were that the application by the applicant to enforce the adjudication determination was dismissed. The court declared that the adjudication determination was void due to the breach of natural justice. The court also ordered that the applicant pay the respondent's costs of the proceedings. This outcome underscored the importance of adherence to natural justice principles in adjudication and the need for adjudicators to remain within the scope of issues raised by the parties.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision