Alcan Gove Development Pty Ltd v Thiess Pty Ltd [2008] NTSC 12
PARTIES:ALCAN GOVE DEVELOPMENT PTY LTD
v
THIESS PTY LTD
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE TERRITORY EXERCISING GENERAL JURISDICTION
FILE NO:28 of 2008 (20806594)
DELIVERED: 10 March 2008
HEARING DATE: 7 March 2008
JUDGMENT OF: ANGEL J
CATCHWORDS:
CONTRACT – Original construction agreement – subsequent agreement adding extras – same parties – whether variation of original agreement or new agreement – when contract made – intention.
Statute Referred to:
Construction Contracts (Security of Payments) Act 2004 (NT)Cases Cited:
Blank v Beroya Pty Ltd (1967) 92 WN (NSW) 24
Boutique Venues Pty Ltd v JACG Pty Ltd [2007] NTSC 5
British and Benningtons Ltd v NW Cachar Co [1923] AC 48
Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337
E G Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
FCT v Sara Lee Household and Body Care (2000) 201 CLR 520
Lion Nathan Australia Pty Ltd v Coopers Brewery Ltd (2006) 156 FCR 1
Morris v Baron & Co [1918] AC 1
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451
Tallerman & Co Pty Ltd v Nathan’s Merchandise (Victoria) Pty Ltd (1956–57) 98 CLR 93
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165
United Dominions Corporation (Jamaica) Ltd v Shoucair [1969] 1 AC 340REPRESENTATION:
Counsel:
Plaintiff:D Robinson SC
Defendant:R A Holt SC and S A McLeod
Solicitors:
Plaintiff:Clayton Utz
Defendant:Cridlands
Judgment category classification: B
Judgment ID Number: Ang0802
Number of pages: 11
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINAlcan Gove Development Pty Ltd v Thiess Pty Ltd [2008] NTSC 12
No. 28 of 2008 (20806594)
BETWEEN:
ALCAN GOVE DEVELOPMENT PTY LTD
Plaintiff
AND:
THIESS PTY LTD
Defendant
CORAM: ANGEL J
REASONS FOR JUDGMENT
(Delivered 10 March 2008)
This is a summons upon an originating motion seeking a declaration that the Construction Contracts (Security of Payments) Act 2004 (NT) does not apply to a contract between the parties dated 20 April 2005 as varied by a Deed of Variation dated 5 October 2007.
On 20 April 2005 the plaintiff as principal and the defendant as contractor entered into a contract to carry out certain structural, mechanical and piping works with the Alcan Gove Third Stage Expansion – G3 Project. That contract comprised a formal written agreement, certain general conditions of contract and other documentation. By Clause 4 of that formal agreement provision was made for the modification, changing or amending of the agreement and by Clause 7 the agreement was said to be governed by the laws of the State of Queensland.
On 1 July 2005 the Construction Contracts (Security of Payments) Act 2004 (NT) commenced. By s 9 of that Act it is provided that the Act applies to a construction contract entered into after the commencement of s 9 and that it applied irrespective of where the construction contract…
Keep reading for free
Create a free CaseChat account to read Alcan Gove Development Pty Ltd v Thiess Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2008] NTSC 12
- Decision Date
CaseChat Overview and Summary
The central legal issues the court had to determine were whether the subsequent agreements between the parties were variations of the original contract or entirely new contracts. The court also needed to establish when the contract was made and assess the intention of the parties in entering into the agreements. This involved interpreting the terms of the contracts and understanding the context in which the agreements were made.
In delivering the judgment, the court analysed the terms of the original agreement and the subsequent agreements, considering the intention of the parties and the nature of the agreements. The court found that the subsequent agreements were not variations of the original contract but rather new agreements. The court determined that the intention of the parties was to enter into separate agreements for additional work. Consequently, the court ruled in favour of Alcan Gove Development Pty Ltd, holding that the subsequent agreements were new contracts and not variations of the original agreement.
The court ordered Thiess Pty Ltd to pay Alcan Gove Development Pty Ltd the sum of $1,411,250, which represented the amount owed under the new agreements. The court also awarded costs to Alcan Gove Development Pty Ltd.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi