Court of Appeal
Supreme Court
New South Wales
- Summary available
Medium Neutral Citation: AEA Constructions Pty Ltd v Wharekawa;; AEA Constructions Pty Ltd v Building Partners Pty Ltd [2019] NSWCA 176 Hearing dates: 14 November 2018 Decision date: 19 July 2019 Before: Basten JA at [1];
Gleeson JA at [22];
White JA at [23]Decision: (1) In appeal proceedings 2018/178977 order that the appeal be dismissed with costs.
(2) In appeal proceedings 2018/236109 order that the appeal be dismissed with costs.Catchwords: TORTS — negligence — apportionment of responsibility and damages — primary judge held that appellant vicariously liable for injury and breached duty of care owed to respondent — primary judge found no negligence on part of worker’s employer — whether primary judge erred in finding worker’s employer not in breach of duty and liable in damages to respondent such as to entitle appellant to contribution from employer — whether primary judge erred in assessment of non-economic loss by applying a 10% reduction to percentage of most extreme case to reflect for contingency — whether primary judge’s assessment as to past economic loss supported by evidence — whether primary judge’s estimation of working life of 60 years and application of 20 per cent buffer for vicissitudes sufficient to account for fact that surgery brought about by negligence would have been necessary at some point in future in any event Legislation Cited: Civil Liability Act 2002 (NSW), ss 3, 5B, 5D, 23, 16
Law Reform (Miscellaneous Provisions) Act 1946 (NSW), s 5
Workers Compensation Act 1987 (NSW), s 151ZCases Cited: Berkeley Challenge Pty Ltd v Howarth [2013] NSWCA 370
Clifton v Lewis [2012] NSWCA 229
Czatyrko v Edith Cowan University (2005) 214 ALR 349; [2005] HCA 14 at [12]
Dell v Dalton (1991) 23 NSWLR 528
Dib Group Pty Ltd (t/as Hill and Co.) v Cole [2009] NSWCA 210
Hall v State of New South Wales [2014] NSWCA 154
Hamilton v Nuroof (WA) Pty Ltd (1956) 96 CLR 18; [1956] HCA 42
House v The King (1936) 55 CLR 499; [1936] HCA 40
Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20
Muller v Sanders (1995) 21 MVR 309
Overseas Tankship (UK) Ltd v The Miller Steamship Co Pty Ltd (“Wagon Mound No 2”) [1967] AC 617
Warren v Coombes (1979) 142 CLR 531; [1979] HCA 9
Wharekawa v AEA Constructions Pty Ltd; Building Partners Pty Ltd v AEA Constructions Pty Ltd [2018] NSWSC 684
Wilson v Peisley (1975) 50 ALJR 207
Wyong Shire Council v Shirt (1980) 146 CLR 40; [1980] HCA 12Texts Cited: D Villa, Annotated Civil Liability Act 2002 (NSW) (3rd ed, 2018, Law Book Co) Category: Principal judgment Parties: AEA Constructions Pty Ltd (Appellant)
Raymond Wharekawa (First Respondent 2018/178977)
Building Partners Pty Ltd (Second Respondent 2018/178977; Respondent 2018/236109)Representation: Counsel:
Solicitors:
J E Maconachie QC with M Davis (Appellant)
D Higgs SC with A Davis (Wharekawa)
P Morris with F Costano (Building Partners)
McMahons…
Keep reading for free
Create a free CaseChat account to read AEA Constructions Pty Ltd v Wharekawa;; AEA Constructions Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] NSWCA 176
- Decision Date
CaseChat Overview and Summary
The appeal raised several legal issues. Firstly, the court was asked to determine whether the primary judge erred in finding that Building Partners Pty Ltd was not in breach of its duty of care to Mr Wharekawa, and consequently, whether AEA Constructions was entitled to contribution from Building Partners. Secondly, the court considered whether the primary judge erred in the assessment of non-economic loss by applying a 10% reduction to the percentage of the most extreme case to account for contingencies. Finally, the court examined whether the primary judge's assessment of past economic loss was supported by the evidence and whether the estimation of the worker's remaining working life and the application of a 20% buffer for vicissitudes adequately accounted for the fact that surgery necessitated by the negligence would have been required at some point in the future regardless of the incident.
The Court of Appeal dismissed the appeals. The judges found no error in the primary judge's determination that Building Partners Pty Ltd had not breached its duty of care. Furthermore, the court upheld the primary judge's assessment of damages, including the approach taken to non-economic loss and the consideration of future economic loss, finding that the evidence supported the conclusions reached.
Consequently, the appeals in both proceedings were dismissed with costs.
Orders
Orders of the court
(1) In appeal proceedings 2018/178977 order that the appeal be dismissed with costs.
(2) In appeal proceedings 2018/236109 order that the appeal be dismissed with costs.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi