Court of Criminal Appeal
Supreme Court
New South Wales
- Summary available
Medium Neutral Citation: ACE Demolition & Excavation Pty Ltd v Environment Protection Authority [2024] NSWCCA 4 Hearing dates: 22 November 2023 Decision date: 09 February 2024 Before: Leeming JA at [1];
Garling J at [121];
Cavanagh J at [122]Decision: In each appeal (357465, 357466, 357467 and 357468 of 2020), make the following orders:
1. Appeal allowed.
2. Quash order 3 made on 2 February 2023 and in lieu thereof, impose fines of:
(a) $216,000 in the case of each of 357465 and 357466 of 2020;
(b) $90,000 in the case of 357467 of 2020, and
(c) $252,000 in the case of 357468 of 2020.
3. Alter Annexure B by (a) inserting a new sentence at the end of the first paragraph “On 9 February 2024 the Court of Criminal Appeal allowed an appeal.” and (b) delete “$943,650” and replace with “$774,000”.
4. Discharge the stay of the orders for payment of the fines and publication of a notice with effect from 28 days of today.
5. Liberty to apply in respect of the form of Annexure B within 14 days of today.
Catchwords: CRIME – appeal against sentence – environmental offences – appellant pleaded guilty to three offences contrary to s 144AA(2) and one offence contrary to s 144AA(1) of the Protection of the Environment Operations Act 1997 (NSW) – transmission of false or misleading information during the course of dealing with waste – three offences of knowingly providing false information – hundreds of weighbridge documents falsified and provided to developers and site auditors – further false documents created to conceal earlier offending – whether primary judge erred in assessing harm and risk of re-offending – whether fines totalling $943,650 manifestly excessive – consideration of nature of ground alleging manifest excess – consideration of whether offending a “single course of conduct” and significance of that conclusion – whether errors in assessment of totality and parity – whether participation in statement of agreed facts a separate mitigating factor – appeal allowed and offender resentenced
Legislation Cited: Crimes (Sentencing Procedure) Act 1999 (NSW), ss 3A, 21A, 22, 32, 43
Criminal Appeal Act 1912 (NSW), ss 5AA, 5AB
Criminal Procedure Act 1986 (NSW), ss 257B, 257G
Environment Legislation Amendment Act 2022 (NSW)
Fines Act 1996 (NSW), s 6
Protection of the Environment Operations Act 1997 (NSW), ss 144AA, 169C, 241, 250
Cases Cited: Achurch v The Queen (2014) 253 CLR 141; [2014] HCA 10
Allesch v Maunz (2000) 203 CLR 172; [2000] HCA 40
Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union (2017) 254 FCR 68; [2017] FCAFC 113
Barbaro v The Queen; Zirilli v The Queen (2014) 253 CLR 58; [2014] HCA 2
Bulga Underground Operations Pty Ltd v Nash (2016) 93 NSWLR 338; [2016] NSWCCA 37
Keep reading for free
Create a free CaseChat account to read ACE Demolition & Excavation Pty Ltd v Environment Protection... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWCCA 4
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the primary judge had erred in their assessment of the harm caused by ACE's actions and the risk of re-offending. The appeal also challenged the excessiveness of the fines imposed. The court needed to consider whether the offending constituted a single course of conduct, the significance of that conclusion, and whether there were errors in the assessment of the totality and parity of the sentence. Additionally, the court had to determine whether ACE's participation in a statement of agreed facts should be considered a separate mitigating factor.
The court concluded that the primary judge had erred in several respects. The harm caused by ACE's actions was less severe than the primary judge had found, and the risk of re-offending was minimal. The court found that the fines imposed were manifestly excessive, particularly given the mitigating factors, including ACE's participation in the statement of agreed facts. The court accepted that the offending was a single course of conduct, which had significant implications for the assessment of the sentence. The appeal was allowed, and ACE was resentenced.
The final orders of the court were not detailed in the text, but typically such a decision would involve the resentencing of ACE for the environmental offences, with a focus on ensuring that the new sentence accurately reflected the harm caused, the risk of re-offending, and all relevant mitigating factors.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.