QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Abbott Builders (Qld) Pty Ltd v Forrest & Anor [2023] QCATA 141
PARTIES:
ABBOTT BUILDERS (QLD) PTY LTD (appellant)
v
PHILLIP FORREST
(FIRST RESPONDENT)JAN FORREST
(second respondent)
APPLICATION NO/S:
APL166-22
ORIGINATING APPLICATION NO/S:
BDL280-19
MATTER TYPE:
Building matters
DELIVERED ON:
1 November 2023
HEARING DATE:
14 August 2023
HEARD AT:
Brisbane
DECISION OF:
Senior Member Brown
ORDERS:
1. The application by the applicant to rely upon further evidence is refused.
2. The application by the respondents to rely upon further evidence is dismissed.
3. Leave to appeal is granted.
4. The appeal is allowed.
5. Order 1 of the decision of the Tribunal dated 4 May 2022 is varied by substituting ‘$42,425.50’ with ‘$38,496.59’.
6. The parties are to file and exchange submissions on the costs of the appeal, not exceeding five (5) pages in length within 14 days of the date of this decision.
7. The costs of the appeal will be determined on the papers.
CATCHWORDS:
APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – RIGHT OF APPEAL – NATURE OF RIGHT – APPEALS IN THE STRICT SENSE AND APPEALS BY WAY OF REHEARING – APPEALS BY WAY OF REHEARING – WHEN REHEARING DOES NOT INVOLVE HEARING DE NOVO – where leave to appeal should be granted on the basis that there was error in the primary decision and is required to correct a substantial injustice – where the appeal tribunal gives consideration to the findings of fact of the primary tribunal – whether the rehearing is limited to a consideration of those matters raised in the grounds of appeal
APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – POINTS AND OBJECTIONS NOT TAKEN BELOW – WHEN ALLOWED TO BE RAISED ON APPEAL – OTHER MATTERS – OTHER CASES – where the appellant says the tribunal does not have jurisdiction to decide a building dispute on the basis that s 77(2) of the QBCC Act has not been complied with – where the matter was not raised in the proceeding below and neither party led evidence on the issue – whether the appellant may adduce fresh evidence – whether the tribunal had jurisdiction to decide the dispute
CONTRACTS – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – whether the tribunal erred in finding that a retaining wall was not constructed in accordance with the terms of the contract – whether the tribunal erred in finding that the contract required a solid stud wall in an ensuite – whether the tribunal erred in finding that the conduct of the appellant deprived the respondents of the ability to claim off–set for late completion damages under the contract – whether upon a proper construction of the contract payment of the final claim by the owners deprived them of the right to claim liquidated damages
DAMAGES – ASSESSMENT OF DAMAGES IN ACTIONS FOR BREACH OF CONTRACT – PARTICULAR HEADS OF LOSS – FUTURE LOSS – where the…
Continue reading Abbott Builders (Qld) Pty Ltd v Forrest
Sign in free to access the full text
- AGLC
- Abbott Builders (Qld) Pty Ltd v Forrest [2023] QCATA 141
- Case
- [2023] QCATA 141
- Decision Date
CaseChat Overview and Summary
The legal issues before the Appeal Tribunal included whether the QBCC Dispute Resolution Tribunal had jurisdiction to decide the building dispute, whether fresh evidence could be introduced on appeal, and whether the Tribunal had erred in interpreting the contract and assessing damages. Specifically, the Tribunal had to determine whether the contract required a solid stud wall for the ensuite, whether Abbott's conduct deprived Forrest of the ability to claim offset for late completion damages, and whether the method of calculating future costs of termite protection was erroneous.
The Appeal Tribunal held that the QBCC Dispute Resolution Tribunal had jurisdiction, and Abbott could not introduce fresh evidence on appeal. The Tribunal found that there was an error in the primary decision regarding the construction of the ensuite wall, which was not supported by the evidence and contradicted other findings. The Tribunal concluded that the contract required a solid stud wall in the ensuite and that the correct interpretation of the contract mandated this. Furthermore, the Tribunal found that the method of calculating future costs of termite protection did not result in a windfall and no discount rate should be applied. The Tribunal reduced the amount payable by Abbott to Forrest by $3,928.91, bringing the total to $38,496.59.
In summary, the Appeal Tribunal granted leave to appeal and allowed the appeal in part, varying the amount payable by Abbott to Forrest. The Tribunal ordered that Abbott's application to rely on further evidence was refused, Forrest's application to rely on further evidence was dismissed, and the costs of the appeal would be determined on the papers.
Orders
Orders of the court
1. The application by the applicant to rely upon further evidence is refused.
2. The application by the respondents to rely upon further evidence is dismissed.
3. Leave to appeal is granted.
4. The appeal is allowed.
5. Order 1 of the decision of the Tribunal dated 4 May 2022 is varied by substituting ‘$42,425.50’ with ‘$38,496.59’.
6. The parties are to file and exchange submissions on the costs of the appeal, not exceeding five (5) pages in length within 14 days of the date of this decision.
7. The costs of the appeal will be determined on the papers.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The relevant principles applicable to an application for leave to appeal are well established: is there is a reasonably arguable case of error in the primary decision?;[10] is there a reasonable prospect that the appellant will obtain substantive relief?;[11] is leave needed to correct a substantial injustice caused by some error?;[12] is there a question of general importance upon which further argument, and a decision of the Appeal Tribunal, would be to the public advantage?[13][10]QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41 (‘QUYD’).[11]Cachia v Grech [2009] NSWCA 232.[12]QUYD (n 10).[13]Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388; McIver Bulk Liquid Haulage Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577.Consideration For reasons that will become apparent, I will first address ground of appeal 3. Ground of appeal 3 The learned member found that the contract required Abbott to construct a solid (stud) wall for the ensuite shower.[14] Abbott says that the finding is contrary to other findings made by the learned member and was not supported by the evidence. [14]Reasons [176]. It was Abbott’s contention below that the plans indicated that the third wall in the ensuite was not a solid stud wall. The evidence of Mr Paterson, Abbott’s construction manager, was that it was industry practice for solid walls on a plan to be depicted by a double line. The Forrests’ quantity surveyor, Mr Burgess, gave similar evidence. The learned member accepted that the plan showed the third wall in the ensuite as only a single, and not a double, line and found that the single line drawing shown on the plan would not mean a solid stud wall.[15] However, the learned member found that the specification required the construction of a solid stud wall and that the specification took precedence over the plans.[16][15]Reasons [170].[16]Reasons [172]. It is not contentious in this appeal that, in construing the contract, the specification took precedence over the plans. Abbott says however that the specification must be relevant. It is therefore necessary to examine more closely the specification. Item 21.7 of the specification relates to ‘shower recess wall’. The specification provided for ‘stud wall, rectified tiles as per Beaumont tile spec.’ The Beaumont Tiles specification which pre-dates the contract was, by virtue of its being referred to in the principal specification, incorporated into the principal specification. Abbott says that the Beaumont Tiles specification was confined to tile selection and was not relevant to structural issues relating to the build. The learned member correctly identified that in construing the contract the specifications took precedence over the plans. The learned member correctly identified that the Beaumont Tiles specification formed part of the contractual specifications. The principles applicable to the construction of a contract are well established. The terms of a contract should be construed so as to give them the meaning intended by the parties. That meaning is to be determined objectively: what would a reasonable person think was intended by the term? Evidence of surrounding circumstances is admissible to assist in the interpretation of the contract if the language is ambiguous or susceptible of more than one meaning. But it is not admissible to contradict the language of the contract when it has a plain meaning.[17] [17]Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24.