Vector Ltd v Transpower New Zealand Ltd

Link copied
Case Copied 16 min read

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY

CIV-2014-485-7098 [2014] NZHC 3411

BETWEEN

VECTOR LIMITED

Plaintiff

AND

TRANSPOWER NEW ZEALAND LIMITED

First Defendant

ELECTRICITY AUTHORITY Second Defendant

Hearing: 12 November 2014

Counsel:

D J Goddard QC and A Kraack for Plaintiff
I Millard QC and C Browne for First Defendant
A Galbraith QC and L O'Gorman for Second Defendant

Judgment:

24 December 2014

JUDGMENT OF WILLIAMS J

Introduction

[1]      Between 2013 to 2014, Transpower built its North Auckland and Northland (NAaN)  network.    This  was  an  upgrade  providing  a  further  cable  connection between its Albany and Penrose substations.  The NAaN upgrade was built in three stages: the Albany substation to a grid exit point at Wairau Road; Wairau Road to a second grid exit point at Hobson Street; and then Hobson Street to close the loop at the Penrose substation.

[2]      The original intention was to commission the entire upgrade (essentially) at the same time, but construction delays led to staged commissioning.  There was a nine month delay between the commissioning of the first link south to Wairau Road,

and the simultaneous commissioning of the remaining two stages.

VECTOR LIMITED v TRANSPOWER NEW ZEALAND LIMITED & ANOR [2014] NZHC 3411 [24 December 2014]

[3]      It is common ground that once the NAaN upgrade was connected at both ends to the grid, it was an “interconnection asset” according to the Electricity Authority’s Transmission Pricing Methodology (TPM).   This meant Transpower’s standard  annual  charges  under  the  TPM  could  from  that  point  forward  be “socialised” to all grid takers in New Zealand; that is, all lines companies and a few large electricity users.  The issue in this case is the proper treatment under the TPM of the Albany-Wairau Road link for the nine months during which the upgrade was effectively only a spur; connected to the grid at one end only, and whose sole taker was Vector.

[4]      Vector says the link should be treated as an interconnection asset and its charges fully socialised.   The authority says that for the relevant nine months the upgrade was a spur and, in accordance with the requirements of the TPM, Vector must pay all costs of that period.

[5]      Transpower abides since, either way, it gets paid.

[6]      The relevant charge for the nine months at issue is $3.2 million.

Background

Relevant facts

[7]      The NAaN comprises a 220 kV cable connecting the Penrose and Albany substations.   It was approved by the (then) Electricity Commission (now the Electricity Authority) on 1 May 2009.  Its purpose is to provide secure transmission capacity to the northern side of the Auckland harbour by providing transmission path diversity through Auckland.  I understand that prior to the NAaN upgrade, this load was served primarily by a single double circuit 220 kV line.

[8]      The   original   timetable   foresaw   the   entire   project   completed   and commissioned at the same time (in 2013 or 2014).  However, delays in construction meant that the first section of the cable to Wairau Road was completed well ahead of links…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Vector Ltd v Transpower New Zealand Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 3411
Decision Date

CaseChat Overview and Summary

In the High Court of New Zealand, Vector Limited brought an action against Transpower New Zealand Limited and the Electricity Authority to determine the proper treatment of the Albany-Wairau Road link for the nine months it functioned as a spur within Transpower's network. The primary legal issue was whether the link should be classified as an interconnection asset, allowing for the socialisation of charges among all grid takers, or as a connection asset, which would require Vector to bear the full cost. The court had to interpret the Electricity Authority’s Transmission Pricing Methodology (TPM) to resolve this dispute.

The court held that the Authority's interpretation of the TPM, which classified the link as a connection asset during the nine-month period in question, was consistent with the statutory objectives and the plain meaning of the TPM. The court found that the Authority's approach, which applied the definitions at the time of assessment, was more aligned with the purpose of promoting competition, reliable supply, and efficient operation of the electricity industry. The court rejected Vector's argument for a purposive interpretation that would have considered the link's final intended use, emphasizing the need for clarity and certainty in the pricing regime. The court concluded that any exceptional circumstances should be addressed through the exemption process rather than altering the TPM definitions.

Accordingly, the court dismissed Vector's application, upholding the Authority's decision and finding that Vector must pay the full cost of using the Albany-Wairau Road link during the nine-month period in question. The Authority was also awarded costs on a 2B basis.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.