Rout v Southern Response Earthquake Services Ltd
[2013] NZHC 3262
•6 December 2013
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV-2013-409-000586 [2013] NZHC 3262
BETWEEN PAUL JOHN ROUT AND GEORGINA ANN KNOX ROUT
Plaintiffs
ANDSOUTHERN RESPONSE EARTHQUAKE SERVICES LIMITED Defendant
Hearing: 7-16 October 2013
Appearances: GDR Shand and D S Maclaurin for Plaintiffs
C M Stevens and PJL Leman for Defendant
Judgment: 6 December 2013
JUDGMENT OF D GENDALL J
Table of Contents
Para No Introduction/background [1] Summary of findings [9] Events leading to the claim [10] Pleadings and issues [17] The policy [22] Approach to interpreting the policy [27] Issue 1 – Did the designation of the “red zone” of itself engage the policy? [30] Issue 2 – Is the damage to the house repairable in terms of the policy? [38] Positions taken by the parties from September 2010 to February 2013 [45]
The Southern Response 13 February 2013 letter [67] Experts’ evidence on whether the house is economically repairable [74] Mr Bruggers’ evidence [75]
Further Arrow DRRA assessments [81]
ROUT v SOUTHERN RESPONSE EARTHQUAKE SERVICES LIMITED [2013] NZHC 3262 [6 December
2013]
Lewis Bradford reports [82] Mr Anderson’s evidence [83] Mr Rakovic’s evidence [84] Mr Lewis’ evidence [91]
The MBIE Guidance Document (the Guidance Document) [98] Mr Hutt’s evidence [102] Mr Higgins’ evidence [108]
Other experts’ evidence [112] Mr Cowie’s evidence – surveyor [112] Mr Maiden’s evidence – building consultant [121]
Quantum Evidence [125] Mr Betts’ evidence [126] Mr Gibson [127] Mr Farrell’s evidence [129] Mr Stanicich’s evidence (Fowler Homes) [134]
Is the house “economically repairable” in terms of the policy? [141]
Issue 3 – As the house is uneconomic to repair what are the Routs’ options
under clause 1(c) of the policy?
[160]
Issue 4 – Relief sought and quantum [170] Judgment sought for rebuild costs [173] Judgment sought by way of a declaration [182]
Issue 5 – General damages [198] Result [205] Costs [207]
Introduction/Background
[1] The plaintiffs, Paul John Rout and Georgina Anne Knox Rout (together the Routs) currently own and live at a property containing 3429m2 in Brooklands, Christchurch (the property). In 2005/2006 they built a house (the house) on the property. The house is a single storey dwelling with attached garage and comprises approximately 241m2. It has been, and continues to be, used as their family home.
[2] Christchurch suffered two major earthquakes on 4 September 2010 and 22
February 2011 and other significant aftershocks. These events damaged the Routs’
house and property, but not to such an extent that they could no longer continue living there. Their property however was “red zoned” in July 2011. “Red zoning” had been a decision (amongst others) taken by the Crown in June 2011, the background to which I outline at [14] below.
[3] In response to an 8 February 2013 offer under this “red zoning” scheme, on
22 March 2013, the Routs chose to sell the land on which their house was built to the Crown, at a sale price of $396,000. In January 2014 they are to move from the property.
[4] The Routs have brought these proceedings against the defendant, their present insurer, Southern Response Earthquake Services Limited (Southern Response) (previously AMI Insurance) under their house policy (the policy). The policy, an AMI “Premier House Cover Policy”, taken out in January 2009 was in force at the time of the earthquake events. It insures the Routs’ house for full
replacement cost to a floor area of 241m2 but not their land. As I understand it, AMI
experienced serious financial difficulty. Southern Response has now taken over and accepts all liability for AMI under the policy.
[5] Southern Response also accepts first, that the policy is a valid contract of insurance for the house for unforeseen and sudden physical loss or damage, and secondly, that there has been damage to the Routs’ property. There is a dispute over the severity of this damage however.
[6] To date, the Routs have received a maximum payout from the Earthquake Commission (EQC) for damage to their house of $113,850.00. In January 2014 they are due to receive the Crown payment for the land of $396,000.
[7] It appears that right up to February 2013 at least Southern Response had considered and said consistently that this property was not economically repairable and constituted a demolish and rebuild. In July 2012 the cost of rebuilding elsewhere was estimated by the Routs’ experts at $548,277.00. Southern Response rejected this however and made settlement offers of $443,000.00 and then
$453.187.00 based upon what it said at the time its own experts had priced as a
rebuild. Lengthy negotiations ensued which came to a point finally when the Routs considered that those offers were too low by about $95,000. In March 2013 the Routs then elected to issue these proceedings, under which they claimed effectively balance rebuild costs of $760,327.30. At the hearing before me, however, Mr Shand for the Routs indicated that total rebuild costs were now in excess of $1.29 million.
[8] Several issues arise in this proceeding:
(a) Does the creation of the red zone and, the fact that the Routs’ property
is in the red zone itself give rise to a claim under the policy here?
(b) Was the Routs’ house repairable under the policy (either actually
repairable or on a notional basis)?
(c) If it was repairable, what is a proper quantification of that (notional)
repair?
(d) If the house was not repairable, what policy options apply?
(e) Based on those relevant policy options, what is to be included in the quantification figure for either a rebuild or the purchase of another property, and what is that final figure?
(f) Has an election under the policy been made in this case?
(g)If Southern Response is in breach of its obligations under the insurance contract, are the Routs also entitled to an award of general damages here?
Summary of findings
[9] For ease of reference and convenience, I summarise at the outset the reasoning and conclusions I have reached below:
(a) The creation of the red zone did not give rise to a claim under the primary insurance clause in the policy. The policy covers physical loss or damage to the house. The red zone “designation” itself did not require physical alteration or repair to the house, and at this point it does not prohibit habitation, repair or rebuilding, or the grant of a building consent. The house at this point has not been deprived of water, electricity, sewerage or other services and can be, and is being, inhabited.
(b)Southern Response appeared to accept up to February 2013 that the house was uneconomic to repair and this was a rebuild case. From that time Southern Response’s position changed and it contended that this was a simple repair.
(c) Since March 2013 therefore, Southern Response has elected to offer the Routs a cash settlement on a repair basis rather than on the basis of a rebuild or the purchase of another property. It has attempted to settle by making a payment rather than having actual work done. But I have found first, that the house was uneconomic to repair and secondly, that, in offering to pay based only on the costs of repairing the house using a low mobility grout (LMG) injection method to re- level the concrete base, there is a possibility that Southern Response may not have been acting in accordance with its obligations under the policy. On the evidence presented, an issue remained that, even if the house had been economically repairable, the proposed method might well encounter problems.
(d)It is explicit in the policy that if the house is damaged beyond economic repair, it is the Routs’ option whether they rebuild on the same site, rebuild on another site, buy another house or accept a cash payment based on the market value of the house at the time of the loss. In selling the land to the Crown, the Routs have elected not to rebuild on the same site but, other than this, the Routs have not as yet
elected any of the other options, given the disagreement over quantum.
(e) If there is a payment made based on the costs of rebuilding the Routs’ home, that payment must be on the basis of the cost of rebuilding on a good site, not on the present weakened and vulnerable section. This is because the Routs have chosen not to repair/rebuild on the existing damaged site. The Routs are not entitled to a windfall payment in excess of the true cost of replacing the house.
(f) On the available evidence before the Court, the cost the Routs have put forward for rebuilding the house on a sound site they own and in a comparable position elsewhere is no more than $673,330.90 (including GST).
(g)The terms of the policy relating to a rebuild or purchase of another property require Southern Response only to pay that cost when it is incurred and provided it is not greater than rebuilding the house on its present site.
(h)As I have noted at [9](c) above, the Routs have succeeded in proving two things. These are first, that Southern Response’s belated insistence that the Routs’ house was no longer a rebuild but was economically repairable was wrong and not properly established. And secondly, that a possible argument remains open that Southern Response’s informal cash settlement offer based on the LMG repair may not have met its contractual obligations here.
(i)The Routs have not succeeded with their red zone argument, nor on their claim that Southern Response must pay on the basis of a potential rebuild elsewhere with substantial extra foundation cost factored in, as if it was a rebuild on the existing Brooklands site. This would result in the Routs receiving a windfall under the policy which is not appropriate under a replacement policy of this type.
(j)As a result, the Routs have succeeded in part and failed in part with respect to the relief sought in their present claim in the following way:
(i)As to the declaration sought in their statement of claim (as amended to include the substantially increased quantum notified by Mr Shand throughout this trial) this is not to be made. Instead a declaration is to be made that, in terms of clause 1(c) of the policy, when the Routs make an election to choose to rebuild their house on another site or to buy another house, they will be entitled to incur costs of doing so up to a maximum figure of $673,330.90 on the basis that they will be reimbursed by Southern Response for this figure, less the
$113,850 already received from EQC in terms of Southern
Response’s obligations under the policy;
(ii)The Routs’ alternative claim in their statement of claim for relief by way of a cash payment of rebuild costs of
$760,327.30 (or indeed the amended figure noted at the hearing of approximately $1.2 million) is dismissed;
(iii) The Routs’ claim for general damages fails.
Events leading to the claim
[10] Between 2005 and 2007 the Routs had the house built for them they say to an architectural design. It is a single storey house and garage with a 241m2 floor area with timber frame, primarily brick veneer cladding and iron roof. The foundation is generally unreinforced concrete slab and reinforced perimeter foundation built on top of an engineered filled building platform. There are also several outdoor concrete patios and a concrete parking pad at the entranceway.
[11] The property suffered damage in the earthquakes. There is evidence that the house has dropped or sunk in places to a maximum level of around 59 millimetres. Some lateral movement in the house is thought to have occurred. There is also
evidence of some cracking in the concrete slab in several locations. A full inspection of the base slab has not been possible due to the presence of floor coverings, which have not been lifted. There is some cracking and movement in the wall linings and patios and a patio support pole has clearly moved out of its vertical position.
[12] The Routs made an initial claim under their present policy. They also lodged claims with the EQC under the Earthquake Commission Act 1993 (ECA) after each earthquake.
[13] In March 2012 the Routs received the maximum payout from the EQC for damage to the house of $113,850.00. It related to building damage as distinct from land damage, and it did not relate to the creation of the red zone. It is accepted that the total deduction Southern Response is entitled to take into account in calculating its payment obligation under the policy is thus $113,850.00.
[14] As noted above, the property was red zoned in July 2011.1 Turning now to this issue and associated matters regarding the creation of the Canterbury Earthquake Recovery Authority (CERA), by way of background it is useful here to repeat Asher J’s discussion of this in O’Loughlin v Tower Insurance Limited:2
[12] On 28 March 2011, the Canterbury Earthquake Recovery Authority (CERA) was established by Order in Council. The Canterbury Earthquake Recovery Act 2011 (CER Act) was enacted on 12 April 2011, with one of its purposes being to provide for CERA’s role in the recovery from the earthquakes.
[13] In June 2011, Cabinet decided as part of the Government’s response to the earthquakes to create zones in the Christchurch area. The Cabinet papers had identified four zones, based on the severity and extent of land damage, as well as the cost effectiveness and social impacts of land remediation. Those four zones were the green, orange, red and white zones. The red zone was for the worst affected areas. The zones were announced on
23 June 2011. As part of the decision, it was decided that CERA would offer to buy properties in the red zone.
[14] CERA carried out Cabinet’s red zone initiative. Under s 53 of the CER Act, the Chief Executive of CERA had the power to acquire property in the name of the Crown. CERA made two alternative offers to homeowners in
1 And, in a decision given on 3 December 2013 (since the hearing in this proceeding concluded) the Court of Appeal in The Minister for Canterbury Earthquake Recovery & Anor v Fowler Developments Limited and Quake Outcasts [2013] NZCA 588 held that the June 2011 decision to declare the red zone was lawfully made.
2 O’Loughlin v Tower Insurance Limited [2013] NZHC 670 at [12]-[14].
the red zone: the first to buy the property entirely for a set price, the second to purchase just the land.
[15] In the present case, this meant that potentially, option one would have resulted in the Crown buying the Routs’ entire property for its $656,000 rating valuation at the time. If this had been the option chosen, the Crown would then take over the Routs’ insurance and EQC claims for damage to the house. Alternatively, option two would have resulted in the Crown buying the land only at its rating valuation of $396,000, and for the Routs themselves as the insured to pursue compensation for damage to their home from their insurer.
[16] As I have noted above, the Routs adopted option two, agreeing to sell the land to the Crown for $396,000. On 22 March 2013 they signed an agreement for sale and purchase with the Crown and are now contractually obliged to settle and leave their home in January 2014. On settlement in January 2014 the Routs will receive $396,000.00 for their land. That payment is for the land as distinct from the house.
Pleadings and issues
[17] What remedies do the Routs seek in this case? First, their statement of claim sets out details of the insurance policy and then asserts that their house is a “total loss.” Then, it is claimed that the house could have been rebuilt on the current site to the same condition and extent as when new for $874,177.30. The Routs then seek one of two alternative remedies. The first is a declaration that Southern Response is liable to pay to them either the cost to rebuild the house on another site or the cost to buy another house, in each case up to a maximum of $760,327.30 (being a total cost of $874,177.30 minus the EQC payment of $113,850). The second, in the alternative, simply seeks judgment for rebuild costs amounting to the net sum of
$760,327.30. In addition, in each case, general damages of $50,000.00 are sought.
[18] In its statement of defence, Southern Response admits that the Routs’ house suffered natural disaster damage as a result of the earthquakes, but otherwise denies the bulk of the Routs’ contentions. Southern Response goes on to plead that it
offered to settle the Routs’ claim by paying them a sum based on rebuild costs of
$453,187.00, but that this offer was rejected.
[19] The argument here according to the Routs essentially boils down to one over the quantum that Southern Response is obligated to pay the Routs under their insurance contract.
[20] As I have noted above, the parties agree that:
(a) The payment by the EQC of $113,850.00 is a proper deduction from
the Routs’ claim in terms of the policy; and
(b)The offer by the Crown to pay $396,000 for the land is an entirely separate matter to the present claim under the policy and should not be deducted from any amount properly due to the Routs.
[21] The parties are in dispute in relation to a number of matters (which are essentially the overarching issues for determination noted at [8] above).
The Policy
[22] I turn now to the specific terms of the AMI/Southern Response policy. These differ to an extent from the Tower policy terms that were at issue in O’Loughlin, a decision of this Court earlier this year involving a similar insurance claim for an earthquake damaged red zone house in another part of Christchurch. The Southern Response policy, under the heading “what is covered by this policy” sets out the following (which I will refer to as “the primary insurance clause”):
Cover for your house
Your house is covered for any unforeseen and sudden physical loss or damage that is not excluded by this policy.
There are some circumstances where you are not covered – please refer to
‘What is not covered by this policy’ on page 5 and the Policy Schedule.
1 What we will pay
a. We will pay to repair or rebuild your house to an ‘as new’ condition,
up to the floor area stated in the Policy Schedule.
b.We will use building materials and construction methods in common use at the time of repair or rebuilding.
c.If your house is damaged beyond economic repair you can choose any one of the following options: (my emphasis)
ito rebuild on the same site. We will pay the full replacement cost of rebuilding your house.
ii to rebuild on another site. We will pay the full replacement cost of rebuilding your house on another site you choose. This cost must not be greater than rebuilding your house on its present site.
iii to buy another house. We will pay the cost of buying another house, including necessary legal and associated fees. This cost must not be greater than rebuilding your house on its present site.
iv a cash payment. We will pay the market value of your house at the time of the loss.
d.If your house is damaged and can be repaired, we can choose to either:
i repair your house to an ‘as new’ condition, or
ii pay you the cash equivalent of the cost of repairs.
[23] After the primary insurance clause in the policy, there are provisions headed “cover for additional costs” and “cover for earthquake damage”. Cover for additional costs is as follows:
We will pay for the following additional costs.
1 Professional fees
a.We will pay the reasonable cost of any architects’ and surveyors’ fees to repair or rebuild your house. These expenses must be approved by us before they are incurred.
2 Demolition and debris removal
a.We will pay the reasonable cost of demolition and debris removal. These expenses must be approved by us before they are incurred.
3 Removal of household contents
a.We will pay the reasonable cost of removing your household contents from your house when this is necessary to carry out repair or reinstatement of your house.
4 Compliance with building legislation and regulations
a.If additional work is required, we will pay the reasonable costs for compliance with building legislation and rules.
b. However, we will not cover the additional work required if:
ia notice has been served requiring compliance with the Building Act 1991 or the Resource Management Act 1991 before the loss or damage occurred, or
ii your house did not comply with the relevant governing building controls when it was built or at the time of any alteration.
[24] And the section on cover for earthquake damage states:
If the Earthquake Commission agrees to pay a claim for loss or damage to your house, we will provide Earthquake top-up cover for loss or damage not covered by the Earthquake Commission.
1 Earthquake top-up cover
a.If your house is damaged by earthquake, natural landslip, tsunami, volcanic eruption or hydrothermal activity (as defined in the Earthquake Commission Act 1993 and any amendments) we will pay the difference between the maximum amount payable by the Earthquake Commission and your sum insured stated on the Policy Schedule.
b.Cover is provided on the same basis as ‘Cover for your house’ on page 2.
c.This cover does not include any excess you may have to pay to the Earthquake Commission.
d. You will not have to pay any excess to us.
[25] The essential starting point in applying these provisions is to consider whether the house is regarded as “economically repairable”. If it is, then Southern Response can elect in terms of clause 1(d) whether to repair the property itself (which needs to be to an “as new” condition) or to pay the cash equivalent of the cost of repairs. From about February 2013 for the first time (for reasons which will become apparent later in this judgment) a dispute arose in this case as to whether the house was capable of economic repair at all. On this aspect, before me, the evidence has suggested that most insurance companies involved in Christchurch earthquake damage claims presently operate a rule of thumb that a house is only economic to repair if the actual repair costs are less than about 80% of a full rebuild estimate.
[26] If a house is not considered to be “economically repairable,” then the position changes and clause 1(c) of the policy noted at [22] above kicks in. This triggers four possible options. All of these options are at the election of the insured, the Routs. It is clear that the first clause 1(c)(i) option, in the circumstances of the present case, (providing for a rebuild on the site) is unavailable to the Routs, as they have sold their land to the Crown. Next, the Routs are unlikely to elect the fourth option under clause 1(c)(iv), as the market value of the house at the time of the loss would simply be its pre-earthquake value, (taking into account wear and tear and depreciation) and this is likely to be at a figure which would leave them unable to rebuild or purchase elsewhere. That leaves open the second and third options 1(c)(ii) and 1(c)(iii). These allow the Routs to elect to rebuild on another site of their choosing, or to buy another house providing that, in each of those cases, the total cost is not to be greater than the cost of rebuilding their house on its present Brooklands site.
Approach to interpreting the Policy
[27] The starting point here must be the words of the policy. The AMI/Southern Response policy at issue is worded in the new easy-to-understand form, without paragraph numbers and without long sentences that in the past often dominated insurance policies. The policy simply has page numbers, headings and bullet points. It has an introductory section, a definitions section, a statement of what is and what is not insured, information on excess, claims, the insured’s responsibilities, changing or ending the policy and general policy information.
[28] In New Zealand, insurance contracts are interpreted in the same way as all other contracts. There are no special rules that apply. Thus, the initial focus is on the words and their plain meaning. The context of the words in the policy and the matrix of surrounding facts are also relevant to the process of interpretation. While it makes sense to start with the actual words of the contract, there is no presumption in favour of ordinary meaning. A meaning that appears plain and unambiguous when devoid of context may not ultimately be what the parties intended when considered in that context and other relevant circumstances. The doctrine of contra proferentem, by which a Court may resolve a clear ambiguity against the party who prepared the contract, can be applied.
[29] I must attempt to interpret the policy in a way that correlates with the presumed mutual intention of the parties, construed objectively. The parties’ views as to what they subjectively thought and intended are irrelevant.
Issue 1 - Did the designation of the “red zone” of itself engage the policy?
[30] Asher J in O’Loughlin answered this question “no” in the circumstances prevailing in that case. I agree, and find also that the answer to this question relating to the Routs’ property and the policy in the present case must also be “no”.
[31] The policy here insures for “unforeseen and sudden physical loss or damage” to the house. It does not cover damage to the land. This is set out at [22] above in the primary insurance clause.
[32] In considering the question whether the creation of the red zone after the earthquakes falls within the policy definition of “unforeseen and sudden physical loss or damage that is not excluded by this policy”, I am satisfied the red zone designation itself did not cause any loss or damage to the Routs’ house. The creation of the red zone could not be said to have any physical effect on this or any other house. Rather, it simply affected the way in which land and houses might be regarded in a particular area, and it also gave property owners in the zone a specific option for a time to sell to the Crown.
[33] In his submissions, Mr Shand for the Routs endeavoured to summarise the loss or damage he says has occurred here, purely as a consequence of the creation of the red zone. He identified this as:
(a) The house he says is no longer able to be insured;
(b) Outside services to the house may not be maintained;
(c) The house is at serious risk of being compulsorily acquired by CERA; (d) The house is no longer able to function as a home/house;
(e) The house it is suggested has no value.
[34] Whilst considerable sympathy must be expressed for the Routs and other red zone property owners in the situation in which they find themselves, it is difficult to see how the insurance industry generally can be regarded as being responsible in any way for that red zoning, or be liable to shoulder the burden to property owners that might flow from red zoning alone.
[35] These factors outlined at [33] above, in any event, as I see it do not involve physical loss or damage to the Routs’ home itself. They are effects which may have economic consequences to the Routs but they cannot be said to fall within the terms of the policy here.
[36] There is also an exclusion in this particular policy for loss or damage arising from “confiscation or destruction by the order of Government or by any person or body legally authorised to seize, confiscate or destroy your house”. Mr Stevens for Southern Response submitted that this particular aspect of the policy applies here and also reinforces the voluntary nature of the Routs’ sale of their land to the Crown. I agree. It would be anomalous if that exclusion could be nullified by an event that was in the control of a third party.
[37] For all these reasons, the Routs’ claim to loss or damage arising from the
creation of the red zone itself must fail.
Issue 2 - Is the damage to the house repairable in terms of the policy?
[38] As noted at [22] above, clause 1(d) of the primary insurance clause in the policy states:
d. If your [the Routs] house is damaged and can be repaired, we
[Southern Response] can choose to either:
i repair your house to an “as new” condition, or
ii pay you the cash equivalent of the cost of repairs.
[39] In determining under the policy whether the house “can be repaired” it is
useful to note clause 1(c) of the primary insurance clause which goes on to provide
options for the Routs in the event that the house is “damaged beyond economic
repair”. (Emphasis added).
[40] The first issue to determine under the policy therefore is whether or not, in terms of clause 1(d), the “house” can be “economically” repaired. It is also useful to note the definition clause on page 1 of the policy. This relates to “Property covered by this policy”, and says the following are all to form part of the Routs’ “house” and are covered by the policy:
- the dwelling and its permanent fixtures
- carpets and floor coverings that are permanently glued to the floor
- kitchen stove and hob, range hood, waste disposal unit, permanently fixed dishwasher
...
- domestic outbuildings (such as garage, shed) and domestic glass houses
- fences, gates, walls, decks and bridges
- domestic paths and driveways constructed of concrete, stone, brick, pavers or tar seal
...
- domestic underground and overhead services at the address stated in the Policy Schedule.
[41] On this question as to whether the house can be repaired, viewed in a purely technical sense, it might be said that almost every house which has been the subject of damage in an earthquake can be “repaired”. But of course, this is at a certain cost, and does not answer the question whether it is “economic” for that repair to be undertaken. The test in clause 1(d) of the policy, as I see it, requires that the damaged house can be “economically repairable” in an objective sense, before Southern Response has the 1(d)(i) option to choose to repair it or the 1(d)(ii) option to pay the cash equivalent of the repair cost.
[42] It is clear also from clause 1(d)(i) of the policy that the repair of the house must be to an “as new” condition. These words “as new” were considered in the decision of Dobson J in this Court in Turvey Trustee Ltd v Southern Response
Earthquake Services Limited3 when dealing with the identical AMI/Southern
Response policy terms. There, Dobson J found:4
The insurer’s obligation under this policy is not an absolute one to pay for replacement of the existing structure. The primary constraint on that obligation is that the insurer is obliged to pay for building materials and construction methods that are in common use at the time of the rebuilding. That constraint, together with the comparative connotation of “as new” conveys the sense of the new structure being the equivalent of the old, rather than a replication of the original. Adopting the approach to equivalents in the Full Court decision in D’Aloia, it would be measured by size, functionality, relative quality and reasonably addressing the re-creation of character and appearance.
A component of that equivalent is considered by reference to materials or construction methods that are “in common use”. I do not see that as requiring that the materials or methods be used in, for instance, any particular proportion of house building nationally or in the locality of the insured property. The requirement for them to be “in common use” is likely to have been included so that the insurer would not be liable for rare materials or outdated construction methods that would now be substantially more expensive in relative terms than more recently introduced methods or materials.
...
I accordingly answer question one that the insurer’s obligation is to meet the cost of constructing a new house of the same style and quality of materials as the property insured. That is subject to the requirement that the materials and methods proposed are in common use in the erection of Edwardian-style villas in Christchurch in 2012...and the requirement for reasonable consideration of substitute materials or methods of construction where that would not affect the quality or character of the replacement structure.
[43] These comments of Dobson J in Turvey Trustee Ltd in part mirror the provisions as to repair or rebuild in clause 1(b) of the policy, which provide for the use of building materials and construction methods “in common use at the time of repair or rebuilding.”
[44] Shortly, I will turn to consider the evidence placed before the Court by the Routs and Southern Response as to this question of whether the house may be “economically repairable”. But first, it is useful to consider the claim negotiations
and the positions adopted by the parties from the time of the September 2010 and
3 Turvey Trustee Ltd v Southern Response Earthquake Services Limited [2012] NZHC 3344.
4 At [24], [25] and [39].
February 2011 earthquakes, right up to February 2013 when as we will see, a significant change in approach was to occur.
Positions taken by the parties from September 2010 to February 2013
[45] Following the earthquakes, AMI/Southern Response engaged Arrow International (NZ) Limited (Arrow) to assist it in processing claims. As I understand the position, Arrow had been engaged by AMI and then Southern Response as project manager for the assessment and management of all repair and rebuild projects of AMI insured houses.
[46] On 10 September 2010, after the first 4 September 2010 earthquake, an inspection of the property was performed by insurance assessors, McLarens Young. This found that the claim was accepted and the claim cost was estimated then at
$343,505.00.
[47] On 26 September 2010, EQC undertook an assessment of the property. That assessment found that the concrete foundations and floor had cracked and moved apart. It was noted in their report that there was “substantial damage to dwelling resulting in repair costs reaching maximum entitlement”. Essentially, the Routs’ property in Brooklands was seen as a likely demolition and rebuild. The repair cost on the EQC assessment form is stated to be $463,278.42. The scope of works assessed the overall total as $500,302.44.
[48] An AMI/Southern Response document dated 6 October 2010 entitled “House Description and Elemental Estimate” is before the Court. It notes that there is to be total demolition of the house including the front driveway and that there are substantial cracks on the ground slab. The document states that salvage items are to include the rear reinforced concrete paving and steps, the metal garden shed and the water heater. Noted also is that there has been movement between the concrete driveway and the residence of up to 75mm. The total replacement estimate given is
$458.505.00. Subtracted from this is the EQC cap of $115,000.00 making a total policy amount due of $343,505.00.
[49] Then, an inspection of the property by Arrow was carried out on or about
9 November 2010. The Details Repair/Rebuild Analysis (DRRA) cost was assessed at $434,106.66 for a total rebuild excluding GST.
[50] A further revised Arrow DRRA is before the Court, which puts the total project figure at $539,339.00 excluding GST.
[51] On 25 March 2011, a visual structural review of the property was carried out for Southern Response by Lewis Bradford Consulting Engineers. A number of structural conclusions were noted. First, the site was identified as being in a zone C area; with evidence of earthquake induced ground damage and large scale settlements. The building it is said had settled a maximum of 222mm. Decisions from the government/EQC/local authorities regarding the extent and type of land remediation were required, and the results of those decisions it is noted could affect the type of repair that was appropriate or could necessitate a rebuild. Damage to building superstructure was observed, including widespread lining damage, minor wall racking and framing movement due to a combination of seismic shaking and earthquake induced ground damage. Levels provided indicated widespread differential settlement of the floor slab and foundations. Floor and foundation repairs were recommended to involve a combination of the following – levelling perimeter foundation by either jacking and concrete underpinning or using urethane/grout injection, epoxy injection of perimeter footing cracks, re-levelling of slab on grade using urethane/grout injections and repair of floor slab cracking either by replacement of slab section or by urethane form or epoxy injection. It was noted at the end of the report that it was based only on a visual walk through inspection of the building, and that did not prove that latent defects might not exist.
[52] Also on 25 March 2011, Golder Associates (NZ) Limited carried out a geotechnical assessment on the property for Southern Response. A report dated
11 April 2011 authored by Andrew Smith of Golder Associates was provided. It noted vertical cracking in the concrete slab, surface cracking in and around the property and cracking in the ground due to differential settlement across the raised building platform. The report said that more information on total and differential
settlement of the house and surrounding land, and whether or not the house was to be rebuilt, was required before appropriate remedial options could be recommended.
[53] A further Southern Response document dated around 5 May 2011 and headed “Premier House – Decision Request” records a decision for the property as a rebuild. The total “house policy customer offer” was recorded there as $323,528. Taking into account demolition costs and other professional fees and damage breakdown, the total cost then was increased to $351,048.00.
[54] It appears from AMI/Southern Response’s Guidewire ClaimCenter information that a further assessment was completed on 20 June 2011. A new total costing and scope of works was assessed.
[55] On 11 July 2011, an email was sent by Blair Milne, a claims specialist within the AMI Christchurch Earthquake Management Team, confirming that the Routs’ property was to be demolished as a result of the September 2010 quake.
[56] A further note dated 15 July 2011 in AMI/Southern Response Guidewire ClaimCenter documents before the Court, states that the February 2011 claim will be declined by the insurers. This is said to be because there is no further EQC entitlement on the house as the insurer’s report confirms the building to be a total loss post the September 2010 earthquake.
[57] On 21 March 2012, an Arrow email was sent to the Routs indicating that they should contact Mr Richard Redpath at Arrow International regarding items that may have been missed from the original DRRA completed on 9 November 2010. There are further follow up emails to the Routs, asking if they have made contact with Mr Redpath.
[58] Then it seems the Routs engaged an independent earthquake damage assessor, EQ East Limited to estimate the cost of rebuilding their house. An inspection of the property was undertaken on 10 April 2012. A report was completed on 13 April 2012. This concluded that the property was not economic to repair. The total cost of rebuilding was said to be $548,276.84 while a repair estimate was put at
$531,373.89. The report summary also noted that most insurance companies would determine a house to be uneconomic to repair if the repair costs were more than 80% of a re-build estimate. It went on to state that “based on the above calculations, the repair costs for your dwelling exceed 80% of the rebuild estimate for a similar dwelling. This confirms that a rebuild is the most economical option.”
[59] On 3 July 2012, the Routs sent an email to Mr Redpath of Arrow and Mr Milne of Southern Response confirming they had commissioned an independent assessment report from EQ East Ltd of the damage, cost of repair and estimate of costs for a rebuild of the house. The email notes the costs of the rebuild and repair and that the report confirms the house is not economically viable to repair and is therefore a rebuild. It states that the Routs are therefore seeking a revised settlement amount. Attached also were a list of features of the current property that were above or extra to standard specifications.
[60] Arrow then undertook a further DRRA which was issued on 10 August 2012. This stated that “due to the extent of damage to this property and the complexity involved in any repair of this property it is our recommendation that this property is demolished and rebuilt. The global settlement was not a factor in this decision.” The figure for a total rebuild excluding GST was noted as $524,735.00.
[61] Further material of additional Arrow DRRAs is also in evidence before the Court. All this is rather confusing however. These DRRAs, all of which appear to have an “issue date” of 10 August 2012, specify figures for a total rebuild of the house varying from $451,784.65 to $450,618.26 to $358,821.15 to $493,373.08 to
$591,014.00.
[62] And, a “decision request document” was also issued by Arrow either on 5 or
8 September 2012. This showed a rebuild figure of $453,187.00.
[63] Then, during September 2012, further email correspondence passed between the Routs and representatives of Southern Response and Arrow. It appears that a requested face to face meeting took place on 1 October 2012 between the Routs, two EQ East representatives and Mr Wayne Hurrell of Southern Response. Southern
Response, it seems at that point, was offering an increased all-up settlement payment to the Routs under the policy of $453.187.00. The Routs in turn were disputing the various Arrow DRRA costings and seeking a settlement figure of $548,276.84. The parties were thus $95,089.84 apart.
[64] Through late 2012 and early 2013, further email correspondence was exchanged between the parties but no settlement agreement was reached. To an extent the tone of this correspondence appears to have become increasingly hostile. The Routs say they were experiencing increasing frustration with what they described as continuous delays in having their claim properly settled. Southern Response in turn denies this, and says the Routs were endeavouring to maintain an entirely intractable and unacceptable position.
[65] A document dated 24 January 2013, being a further review by Arrow of their costings is before the Court. An email was sent to the Routs that day confirming that all items on a list of the house features provided earlier by the Routs had been allowed for in the Arrow report and the DRRA. But it appears this may not have been the case. The document dated 24 January 2013 clearly provided that “no allowance” had been made for four specific items in the Routs’ house – underfloor insulation, acoustic batts in the interior walls, a retractable patio awning and insect screens attached to the doors. That day, Mr Rout emailed Mr Hurrell requesting the amounts Arrow had costed for the individual item lines Mr Rout had submitted, so that they could be compared against cost estimates from suppliers contacted by the Routs. The response from Mr Hurrell on 28 January 2013 it would seem was somewhat unhelpful. It said simply that, due to commercial sensitivity, Southern Response and Arrow were unable to provide a breakdown of the individual items. All these aspects are suggested by the Routs now as being deceptive and unacceptable on the part of Southern Response. At this stage, however, I leave these matters to one side.
[66] What is important to note at this point is that by early February 2013 no agreement by way of negotiated settlement between the parties had been able to be reached. This resulted in what can only be seen as a considerable change in position adopted by Southern Response.
The Southern Response 13 February 2013 letter
[67] This change in position was reflected in a letter from Southern Response to the Routs dated 13 February 2013. That letter, which in my view is significant here was also emailed to the Routs on 15 February 2013. It is useful to set out in full the text of this letter:
13 February 2013
Mr P and Mrs G Rout
............................. Brooklands
Christchurch 8083
Claim No. ................
We refer to our recent discussions and confirm that we are unable to resolve and settle your claim with Southern Response
Previous correspondence
On 1 October 2012, a meeting was held with you advising that the insured property under your policy was ‘beyond economic repair’ and a revised settlement figure was presented to you.
The estimate of cost was based on the Detailed Repair / Rebuild Analysis (‘DRA’) done by Arrow on 10 August 2012. The purpose of providing an estimate of cost is to allow you to make an informed decision.
Southern Response have also provided you with a Construction Budget Breakdown to review as requested. Arrow have also reviewed another list of items you provided and have confirmed the cost of these items is covered in the DRA.
We understand that now, having reviewed the DRA, Construction Budget Breakdown and confirmation that other items are included, you do not accept our estimate of the cost to reinstate your insured property. At the time that DRA was done, we maintain that the estimate fairly reflected the cost to reinstate your damaged insured property.
Request for re-assessment
If you remain unhappy with the DRA, you may request in writing that it is reviewed. On receipt of your request in writing, you will receive confirmation from Southern Response that:
§ As at the date of receiving your request, our claim determination that
the insured property is ‘beyond economic repair’ is withdrawn.
§As at the date of receiving your request, the estimate of cost provided in the previous applicable DRA is also withdrawn.
Until the re-assessment process is completed, the previous settlement options identified in your decision pack are no longer available, including the ‘buy another house’ option. Any re-assessment will consider all aspects, including the viability of repair of the earthquake damage to your insured property.
Re-assessment process
If you request a re-assessment, we will instruct Arrow to undertake a complete review of the damage to your insured property and to re-assess:
§the earthquake damage to your insured property, including viability of repairing that damage; and
§the estimate of cost to reinstate the earthquake damage to your insured property.
Arrow’s re-assessment will be based on current engineering expertise (both geotechnical and structural), current legislative requirements and any guidance that may be drawn upon from the Department of Building and Housing. We will also take into account the building materials and construction methods in common use at the time of the re-assessment.
Arrow’s re-assessment will provide an estimate of cost to repair or rebuild your earthquake damaged insured property based on current rates for the construction of residential property in Canterbury. Construction and labour rates have the potential to change over time, particularly as new or revised construction methods that respond to the challenges of building in Canterbury are adopted.
Issues to be aware of when re-assessment takes place
A re-assessment conducted by Arrow could result in no change to Southern
Response’s original decision regarding your claim. Equally, there could be:
§an increase or reduction of the estimate of cost to reinstate your earthquake damaged insured property.
§ a revised reinstatement methodology.
§a determination that the insured property previously thought to be beyond economic repair, is now repairable.
When Arrow has completed the re-assessment, Southern Response will write to you and advise you of the outcome of your re-assessment.
Further considerations for you
Any re-assessment will be subject to Arrow’s capacity and we will
communicate this to you.
Once you request us to review the DRA assessment as outlined above, the original claim determination is withdrawn and a new claim determination will be sent to you. Arrow will complete the required investigation and validation of the reinstatement of your insured property.
If you wish to settle your claim based on the original claim determination and estimate of cost you received in your most recent DRA, Southern Response is prepared to adhere to that original determination until you formally request (in writing) a review of the DRA assessment.
If you wish to pursue settlement without seeking a re-assessment, please contact Wayne Hurrell by phone or email.
Before making any decision that may influence how your claim will now progress, we suggest you take professional advice as necessary.
Yours sincerely
Wayne Hurrell
[Southern Response] Claims Specialist
[68] It must be remembered also at this point that it was only on 8 February 2013 that the Crown had made its red zone offer to the Routs outlining the two options for purchase of their land or purchase of their entire property. And it was on 22 March
2013, following the Routs’ election of option two under the offer, that the agreement
for the sale to the Crown of the land was signed.
[69] The Routs’ reaction to this 13 February 2013 Southern Response letter was decisive. The thrust of the letter clearly was to the effect that, if the Routs were unhappy with Southern Response’s approach, they could seek a re-assessment. If, however, they chose that option, all previous offers were said to be off the table and they could potentially face a revised assessment on a repair rather than a demolish and rebuild basis. This it was noted could leave the Routs significantly worse off than if they had accepted an offer on a rebuild basis.
[70] The Routs saw this as a subtle threat, and it seems they simply took the view then that all negotiations were over. The present proceeding was issued by them on
21 March 2013.
[71] So far as the 13 February 2013 letter is concerned, before me Mr Stevens, counsel for Southern Response, rejected the Routs’ claims and contended that this letter contained no threat. It was simply a prudent insurer advising its insured on what was likely to happen.
[72] Notwithstanding this, in considering the 13 February 2013 letter in its entirety, it is difficult to escape the conclusion that, in so far as it appears to suggest a “take it or leave it” offer, Southern Response were endeavouring to exert an element of pressure on the Routs. More on this aspect later.
[73] I return now to the initial question posed at [39] to [40] above as to whether or not the damage to the house is “economically repairable” in terms of the policy. In doing so I repeat that, if the evidence is that the house can be notionally repaired, Southern Response in theory has the option under clause 1(d) to either carry out the repairs or pay the cash equivalent. But as the land is now sold to the Crown, the only actual option if the house does prove to be economically repairable is to make a repair cost payment to the Routs.
Experts’ evidence on whether the house is economically repairable
[74] Following the issue of the Routs’ statement of claim in this proceeding, additional expert reports were obtained. These reports and the evidence surrounding them were before the Court, and I now address these.
Mr Bru ggers’ eviden ce
[75] A report dated 21 June 2013 was prepared by geotechnical engineers, Geoscience (NZ) Limited (Geoscience) in response to a request by Arrow to complete shallow soil testing at the property. Mr Donald Bruggers, a geotechnical engineer and consultant to Geoscience with 35 years experience, gave evidence before me on the Geoscience report. The report noted initially that “for properties in the flat land residential red zone areas, CERA considers being zoned red means that the land has been so badly damaged by the earthquakes it is unlikely that it can be rebuilt on”. Geoscience then confirmed that their scope of works had been strictly limited by Arrow to providing a shallow soil Ultimate Bearing Capacity (UBC) test for a strip footing. This was to be based on shallow soil investigations. There was no engagement for deep soil testing to be carried out which might have provided, amongst other things, an assessment of liquefaction potential at the site. The report specifically noted that “founding directly below topsoil may place foundations on undocumented fill. We recommend Geoscience inspect the base of the excavation to
confirm suitability of the fill as a bearing layer.” The report appeared to clearly set out its limitations. These included that Geoscience was following a brief, that its recommendations were based on ground conditions indicated from published sources, and that subsurface conditions relevant to construction works should be assessed by contractors with additional tests performed as necessary. The report went on to say that, while repair of the existing shallow foundations may reduce differential settlement of the structure in future seismic events, there was still a risk of damage occurring to the foundations.
[76] Mr Bruggers in relying on the Geoscience report, noted in his oral evidence that Geoscience had been engaged to undertake limited shallow soil testing on the Routs’ site. This he confirmed again was to determine the ultimate shallow bearing capacity (UBC) for repairs to the house foundations.
[77] He noted that deep soil testing could have been performed, but suggested it was probably not necessary or mandated by the MBIE Guidelines in this case, because of what he considered was reasonable performance of the site here and measured settlements.
[78] Mr Bruggers considered that the Routs’ land and house settlement was in line with a TC3 site classification. He was of the opinion that the repair as proposed by Southern Response was acceptable in terms of the MBIE Guidelines and the Building Code. He stated he was confident that the geotechnical investigations conducted for this site were appropriate for the proposed repair strategy.
[79] Mr Bruggers said he was familiar with the repair methodology that Southern Response’s engineers proposed to use to re-level the house, and that he had no concerns about whether it would be effective for this house.
[80] He also stated that it would be possible to lift the house to its assumed original elevation of 11.4m RL using the current repair methodology. Additional geotechnical testing under the MBIE guidelines was not required to implement this additional lifting he suggested because this methodology did not increase the bearing loads required for lifting the structure.
Further Arrow DRRA assessments
[81] Next, in chronological terms, there is a further Arrow DRRA dated 26 June
2013, (but with an issue date said to be 10 August 2012 and a visitation date of
9 November 2010) which is before the Court. It contains more details about the damage to the property in a site summary and assessor’s report. Further, it refers to a repair methodology. It concludes that the property should be priced for repair as well as a rebuild with a decision made once pricing has been completed. It puts the total rebuild figure at $493,373.09 excluding GST and includes an estimate for repairs, putting this at $312,018.39 excluding GST.
Lewis Bradford Reports
[82] A second structural engineering report from Lewis Bradford Consulting Engineers Ltd dated 27 June 2013 is also before the Court. Mr Craig Lewis, a founding director of that company, gave evidence before me on that and the earlier Lewis Bradford report. The reports note that site visits were conducted on 25 March
2011 and 21 May 2013. The 27 June 2013 report states essentially that there was some minor earthquake related structural damage that had been identified to the house. Repair and reinstatement to some structural elements was proposed. It said that the proposed repair works were appropriate and would ensure that the building would continue to comply with the provisions of clause B1 of the building code at least to the same extent as prior to the damage. Mr Lewis’ evidence is further discussed below at [91].
Mr Ande rson’s evidenc e
[83] Southern Response then called as an expert witness, one further geotechnical engineer, Mr Clive Anderson, a principal at Golder Associates in Christchurch. Mr Anderson relies on the Golder Associates geotechnical assessment report dated
11 April 2011 in his evidence. That report notes that the site has experienced differential settlement of the concrete founding slab probably caused by liquefaction ejection of material from beneath the building platform and subsequent settlement of the building foundation. External and internal damage in the house, including vertical cracking of the exposed concrete founding slab, the varying orientations of
ground cracking between the house, driveway and landscaped areas are said to be a direct result of this movement. The report suggests that the fill material upon which the house was founded was essentially “good ground”. It was noted that due to the likelihood of settlement having occurred however, the current level of the house in relation to the flood plain needed to be re-assessed. The report stated that more information on total and differential settlement of the house and surrounding land, and whether the house was to be rebuilt, was required before appropriate remedial options could be considered. The report essentially referred to the damage that the house and property had suffered, but did not discuss repair methodologies as it said this would have required further information.
Mr Rakovic’s evidenc e
[84] The Routs chose to call no geotechnical engineering evidence. Instead, their only engineering evidence was provided by Mr Zoran Rakovic, a qualified structural engineer working in Christchurch.
[85] Mr Rakovic in his evidence began by suggesting there was extensive damage to the property and the house. He said this included significant and widespread differential settlements to the ground floor slab and perimeter foundation; large areas identified from a drop-hammer test with likely voids formed under the slab due to shaking-down of fill; evidence of slab and foundation cracks, as well as exterior separation between the house and the paved areas; residual tensile and flexural stresses in the slab and foundation, due to lateral stretch; unevenness in the ground floor slab, most likely caused by relative vertical displacement of slab parts; cracking to the perimeter foundation; cracking to timber framed walls and cracking to the exterior brick veneer. This differed markedly in extent from the opinions expressed in the evidence before the Court from Mr Lewis, Mr Bruggers and Mr Anderson.
[194] There is also to be no addition made for demolition costs as argued by Mr Shand. This is in line with the decision of MacKenzie J in Avonside Holdings Limited v Southern Response Earthquake Services Limited.6 As no demolition costs will actually be incurred by the Routs here, it would be wrong to make allowance for these.
[195] One final adjustment to the Fowler Homes figure in my view is appropriate and should be made. This is the addition of an amount for engineering, architectural
6 Avonside Holdings Limited v Southern Response Earthquake Services Limited [2013] NZHC
1433 at [37].
and other professional fees not included in the estimate. A sum of $5000 for this in my view is appropriate here.
[196] The final rebuild figure is therefore to be calculated as follows. From the initial Fowler Homes estimate of $618,719.00 is to be deducted $11,600.00 as agreed for carpets, leaving a figure of $607,119.00. Then the additional $5000 for professional fees is to be added bringing this total to $612,119.00. The 10% contingency is to be calculated on this amount and totals $61,211.90. Adding this contingency leaves a final rebuild figure of $673,330.90 (including GST).
[197] A declaration is now made that, in terms of clause 1(c) of the policy, when the Routs make an election to choose to rebuild their house on another site or to buy another house, they will be entitled to incur costs of doing so up to a maximum figure of $673,330.90 on the basis that they will be reimbursed by Southern Response for this figure less the $113,850.00 already received from EQC in terms of Southern Response’s obligations under the policy.
Issue 5 - General damages
[198] In their statement of claim the Routs seek an award of general damages of
$50,000.00 ($25,000.00 for each of them). This is made on the basis of what they say was Southern Response’s unacceptable conduct here and the effects of this on them both personally, emotionally and mentally.
[199] Mr Shand contends the quantum of general damages sought is in line with “leaky home” awards of general damages. He says it relates to the length of time taken by Southern Response to process the Routs’ claim, the alleged failings of Southern Response to fulfil its obligations under the policy and the claim process in accordance with best practice, the late change in position by Southern Response from a rebuild to a repair decision, as well as the real additional stress suffered by the Routs as a result of their ongoing difficulties.
[200] Both Mr and Mrs Rout provided evidence before the Court of the difficult situation they have found themselves in since the earthquakes. There can be no
doubt that the stresses and anxiety they have suffered since those events, compounded by the difficulties over their house, are very real.
[201] Whilst there must be considerable sympathy expressed towards the Routs regarding these aspects, in my view however this is not a case where general damages are appropriate. Southern Response and the Routs for some time agreed to negotiate on a voluntary basis to endeavour to achieve a cash payment settlement which would conclude Southern Response’s obligations under the policy. This proved not to be possible. This however cannot be said to affect Southern Response’s legal obligations under the policy which, as I have outlined above, were somewhat different. And, by persisting with their negotiations, to an extent both parties knowingly and willingly contributed to the length of time taken to process the Routs’ claim.
[202] The obligation of Southern Response throughout was to act fairly and in good faith as insurer in terms of the policy requirements. General damages claims against insurers in the past have involved situations, for example, where claims have been unjustifiably declined on grounds of fraud or gross delay.7 In addition, s 30
Consumer Guarantees Act 1993 requires services such as those provided here by Southern Response to be provided “in a reasonable time”. That section might well apply in this case. On these aspects, Southern Response’s actions here in a number of ways must invite some criticism. First the time taken by it to process this claim being nearly three years, although not entirely their responsibility, nevertheless must be of some concern. Secondly, allegations are made that Southern Response has constantly changed its position with multiple DRRA assessments being undertaken and new reports obtained, and particularly in making a direct change in its position earlier this year from a rebuild to a “notional” repair. Thirdly, its decision to instruct its geotechnical and structural engineers to consider and report only on the capability of the site for a foundation repair, must also invite some criticism. And finally, the contention that Southern Response and/or Arrow in the earlier negotiations were
deceptive to an extent in confirming their inclusion in their costings of some minor
7 Kerr & Kerr v State Insurance General Manager [1987] 4 ANZ Ins Cas 60/781, and Stuart v Guardian Royal Exchange Assurance Company of New Zealand Limited (No 2) [1988] 5 ANZ Ins Cas 60-844.
items in the Routs’ house which later proved not to be the case may well need further
explanation.
[203] On the other hand, the major decision by the Routs and their advisors to persist in what might be seen as an entirely unprincipled way with their approximately $1.2 million claim in this proceeding, despite their unexplained decision very much at the 11th hour to withdraw any possibly supporting quantum evidence for this claim, in my view, can only be seen as both unjustified and ill- advised. And, the unexplained failure by the Routs until mid way through the trial in
this proceeding to inform the Court (and presumably also Southern Response) that some time earlier they had received a Fowler Homes rebuild estimate valid until
17 August 2013 for $557,000, must also count against their claim here for general damages.
[204] For all these reasons, I reject the Routs’ claim here for general damages.
Result
[205] The Routs’ application in their statement of claim for a declaration to an extent succeeds although not in the form they have sought. The declaration I have noted at [197] is now made.
[206] Regarding their second pleaded claim for relief by way of judgment for rebuild costs initially of $760,327.30 then increased to $1,291,508.31, as noted above at [181] this was entirely inappropriate and fails.
Costs
[207] As to costs I reserve the question of costs here. Both counsel indicated they wished to make submissions to me with respect to costs. This did not occur at the hearing.
[208] I direct that, in the absence of the parties being able to agree the issue of costs between them, they are to file submissions on this question on a sequential basis which are to be referred to me and in the absence of either party indicating they wish
to be heard on the question of costs, I will decide that issue on the basis of the submissions and the material then before the Court.
........................................................
D Gendall J
Solicitors:
Grant Shand, Christchurch
David Maclaurin, Christchurch
Craig Stevens, Wellington
DLA Phillips Fox, Wellington
11
3
0