Mehta v Chandra

Case [2025] NZHC 578


IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2024-404-1120

[2025] NZHC 578

BETWEEN

DHARMENDRA MEHTA

Appellant/Cross Respondent

AND

EMENUWAL CHANDRA

Respondent/Cross Appellant

Hearing: 26 November 2024

Appearances:

S Carey for Appellant

M Taylor for Respondent

Judgment:

19 March 2025


JUDGMENT OF WILKINSON-SMITH J


This judgment was delivered by me on 19/03/2025 at 3 pm Pursuant to Rule 11.5 of the High Court Rules

…………………………

Registrar/Deputy Registrar

Solicitors/Counsel: S Carey, Auckland M Taylor, Auckland

MEHTA v CHANDRA [2025] NZHC 578 [19 March 2025]

Introduction  [1]

Background[8]

The District Court decision  [26]

The costs decision[69]

The grounds of appeal[79]

Mr Mehta’s substantive appeal[79]

Mr Mehta’s appeal in relation to costs[97]

Relief sought[107]

Mr Chandra’s position  [108]

Mr Chandra’s position on the substantive matters[108]

Mr Chandra’s position in relation to costs[128]

Relief sought[137]

Approach on appeal[138]

Issues[140]

Discussion[141]

Construction defects[141]

The off-centre pillar[158]

Should the Judge have relied on the Kaizon report in relation to delay?[160]

Should damages for delay have been awarded other than as a consequence of a breach of contract given the liquidated damages clause of the

Project Management Contract, and given that Mr Chandra was not a party to that contract?[163]

Should responsibility for delay have been apportioned; and if so, was the

apportionment correct?[164]

Mr Chandra’s liability[167]

Was the award of general damages correct?[175]

Should the cost of the Kaizon report have been apportioned?[180]

Was the Judge correct to award costs on a 2B basis, and only for steps taken after June 2019?[183]

Should interest be payable on the judgment sum from October 2010?[189]

Orders[196]

Introduction

[1]    On 16 April 2024, Judge K Davenport KC issued a decision on a claim for damages against Mr Emenuwal Chandra in respect of building and project management    work    which    Mr Chandra/his     company     carried     out     at   Mr Dharmendra Mehta’s Mount Roskill home in 2010.1

[2]    Mr Chandra was the owner and sole director of Habitat Builders Ltd (Habitat), a company now removed from  the  New  Zealand  Companies  Register  (Companies Register), which was engaged on a labour-only basis to do carpentry work on Mr Mehta’s house, and to project manage the build.

[3]    Mr Mehta claimed that Habitat and Mr Chandra failed to carry out the building and project management work properly and in a timely manner.

[4]     Mr Mehta was partially successful in his claim but appeals the aspects of the judgment in which he was unsuccessful. Mr Mehta also appeals a subsequent costs decision dated 15 July 2024.2

[5]    Mr Chandra opposes Mr Mehta’s appeal and cross-appeals the District Court Judge’s decision in relation to:

(a)the award of damages for delays in the building works;

(b)the finding of liability made against Mr Chandra personally; and

(c)the award of $10,000 in general damages to Mr Mehta.

[6]    Mr Chandra also appeals the costs decision and submits that costs should lie where they fall.

[7]Mr Mehta resists the cross-appeal.


1      Mehta v Habitat Builders Ltd [2024] NZDC 4779.

2      Mehta v Habitat Builders…

Continue reading Mehta v Chandra

Sign in free to access the full text

Details
AGLC
Mehta v Chandra [2025] NZHC 578
Case
[2025] NZHC 578
Decision Date

CaseChat Overview and Summary

Dharmendra Mehta appeals against the District Court’s judgment in his claim against Emenuwal Chandra, which was dismissed in part. Mr Chandra cross-appeals the award of general damages and the costs decision. The court finds that Mr Mehta’s appeal in relation to the substantive judgment should be dismissed, but that the award of general damages should be reduced from $10,000 to $2,000. Mr Chandra’s appeal in relation to liability is dismissed. The appeal in relation to costs is allowed, and the court orders that costs lie where they fall. Interest on the compensatory damages will run from 19 June 2019 until the date of judgment at the rate of five per cent per annum. Post-judgment interest will apply in the usual way.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.