IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2024-404-1120
[2025] NZHC 578
BETWEEN
DHARMENDRA MEHTA
Appellant/Cross Respondent
AND
EMENUWAL CHANDRA
Respondent/Cross Appellant
Hearing:
26 November 2024
Appearances:
S Carey for Appellant
M Taylor for Respondent
Judgment:
19 March 2025
JUDGMENT OF WILKINSON-SMITH J
This judgment was delivered by me on 19/03/2025 at 3 pm Pursuant to Rule 11.5 of the High Court Rules
…………………………
Registrar/Deputy Registrar
Solicitors/Counsel: S Carey, Auckland M Taylor, Auckland
MEHTA v CHANDRA [2025] NZHC 578 [19 March 2025]
Introduction [1]
Background[8]
The District Court decision [26]
The costs decision[69]
The grounds of appeal[79]
Mr Mehta’s substantive appeal[79]
Mr Mehta’s appeal in relation to costs[97]
Relief sought[107]
Mr Chandra’s position [108]
Mr Chandra’s position on the substantive matters[108]
Mr Chandra’s position in relation to costs[128]
Relief sought[137]
Approach on appeal[138]
Issues[140]
Discussion[141]
Construction defects[141]
The off-centre pillar[158]
Should the Judge have relied on the Kaizon report in relation to delay?[160]
Should damages for delay have been awarded other than as a consequence of a breach of contract given the liquidated damages clause of the
Project Management Contract, and given that Mr Chandra was not a party to that contract?[163]
Should responsibility for delay have been apportioned; and if so, was the
apportionment correct?[164]
Mr Chandra’s liability[167]
Was the award of general damages correct?[175]
Should the cost of the Kaizon report have been apportioned?[180]
Was the Judge correct to award costs on a 2B basis, and only for steps taken after June 2019?[183]
Should interest be payable on the judgment sum from October 2010?[189]
Orders[196]
Introduction
[1] On 16 April 2024, Judge K Davenport KC issued a decision on a claim for damages against Mr Emenuwal Chandra in respect of building and project management work which Mr Chandra/his company carried out at Mr Dharmendra Mehta’s Mount Roskill home in 2010.1
[2] Mr Chandra was the owner and sole director of Habitat Builders Ltd (Habitat), a company now removed from the New Zealand Companies Register (Companies Register), which was engaged on a labour-only basis to do carpentry work on Mr Mehta’s house, and to project manage the build.
[3] Mr Mehta claimed that Habitat and Mr Chandra failed to carry out the building and project management work properly and in a timely manner.
[4] Mr Mehta was partially successful in his claim but appeals the aspects of the judgment in which he was unsuccessful. Mr Mehta also appeals a subsequent costs decision dated 15 July 2024.2
[5] Mr Chandra opposes Mr Mehta’s appeal and cross-appeals the District Court Judge’s decision in relation to:
(a)the award of damages for delays in the building works;
(b)the finding of liability made against Mr Chandra personally; and
(c)the award of $10,000 in general damages to Mr Mehta.
[6] Mr Chandra also appeals the costs decision and submits that costs should lie where they fall.
[7]Mr Mehta resists the cross-appeal.
1 Mehta v Habitat Builders Ltd [2024] NZDC 4779.
2 Mehta v Habitat Builders…
Grounds of appeal
[14] The appellant contends that the primary judge erred in finding that the respondent had discharged the onus of establishing the matters required under the relevant provision.
[15] It was submitted that his Honour failed to give adequate weight to the evidence of the second witness, and that the findings of fact were not reasonably open on the material before the Court.
[16] The respondent, for its part, submits that no error is disclosed, and that the conclusions reached were well within the range of outcomes available to the primary judge.
Consideration
[17] It is convenient to deal first with the question of construction, as the resolution of that issue informs the remaining grounds advanced by the appellant.
[18] For the reasons that follow, we are of the view that the appeal should be allowed in part and the matter remitted for further determination.
Continue reading Mehta v Chandra
Sign in free to access the full text
Details
AGLC
Mehta v Chandra [2025] NZHC 578
Case
[2025] NZHC 578
Decision Date
CaseChat Overview and Summary
Dharmendra Mehta appeals against the District Court’s judgment in his claim against Emenuwal Chandra, which was dismissed in part. Mr Chandra cross-appeals the award of general damages and the costs decision. The court finds that Mr Mehta’s appeal in relation to the substantive judgment should be dismissed, but that the award of general damages should be reduced from $10,000 to $2,000. Mr Chandra’s appeal in relation to liability is dismissed. The appeal in relation to costs is allowed, and the court orders that costs lie where they fall. Interest on the compensatory damages will run from 19 June 2019 until the date of judgment at the rate of five per cent per annum. Post-judgment interest will apply in the usual way.