IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE
CIV-2019-425-000087
[2021] NZHC 2865
BETWEEN JUDITH GAY DAVIES and SIMON BERNARD DAVIES
Plaintiffs
AND
K M SMITH BUILDER LTD
First Defendant
AND
KERRY MICHAEL SMITH
Second Defendant
Hearing: 12, 13, 14 April, 28 May and 28 October 2021 Appearances:
L A Andersen QC for Plaintiffs
A D G Hitchcock and K L Rusher for Defendants
Judgment:
2 November 2021
JUDGMENT OF DOOGUE J
This judgment was delivered by me on 2 November 2021 at 2.30 pm pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar Date:
DAVIES v K M SMITH BUILDER LTD [2021] NZHC 2865 [2 November 2021]
TABLE OF CONTENTS
Introduction [1]
Preliminary interlocutory issue [15]
The substantive issues for determination [17]
The background
Early days [18]
Initial engagement with Mr Smith and the company [23]
The contract [26]
November 2014 to December 2015 [28]
Changes made by the Davies [36]
Hard landscaping [43]
Late 2015 to August 2016 [46]
Request for some costs of completion [47]
Letter to the BNZ [49]
Deterioration in the relationship between the Davies and Mr Smith [51]
Did Mr Smith make the representations alleged by the Davies? [56]
Mr Smith’s credibility in the broader context [58]
The letter Mr Smith wrote to the BNZ [67]
When and in what context were the representations alleged to have been made?
[86]
Did Mr Smith represent he had the time and ability to project manage the construction? [90]
Did Mr Smith represent the construction of the house (including landscaping) would cost between $2.5 and $2.8 million (inclusive of GST)? Did Mr Smith represent that the cost of construction would not exceed $3 million? [95]
Did Mr Smith represent to the Davies that construction would be completed by March 2016? [119]
Summary of findings on the alleged representations [126]
Was there an implied term in the contract that the cost of construction of the house would be reasonable? [138]
Did the company and/or Mr Smith fail to properly project manage the construction of the house? [153]
The law [155]
Discussion [156]
Alleged acts or omissions [158]
Failure to account for the ongoing costs of construction [159]
Unauthorised variations [163]
CS Roofing variation [165]
Balustrade variation [167]
Failure to ensure competitive quotes from subcontractors [176]
Delivery of material in excess of requirements and failure to obtain refunds for excess materials [178]
Defective work [183]
Roofing defects [185]
Defective tiling [193]
Defective plumbing [197]
Joinery defect and excessive efflorescence [199]
Defects in the installation of the mudroom and front doors [216]
Powder room and master bedroom [222]
Atrium beams and leakage [226]
Balcony master bedroom/paver staining [228]
Summary of findings on project management [230]
Summary of overall findings [236]
The counterclaim [242]
Result [243]
Introduction
[1] In 2001 the Plaintiffs, Dr and Mrs Davies (the Davies), purchased a property at Closeburn Station, a high-country station in the Queenstown Lakes area (the area). Soon thereafter they commissioned a well-known architect,…
Continue reading Davies v K M Smith Builder Ltd
Sign in free to access the full text
- AGLC
- Davies v K M Smith Builder Ltd [2021] NZHC 2865
- Case
- [2021] NZHC 2865
- Decision Date
CaseChat Overview and Summary
The court found that Kerry Smith did not make the alleged representations and there were no implied terms in the contract regarding the cost of construction or completion date. The court found that there was an implied term in the contract that the cost of construction would be reasonable, and the plaintiffs had failed to prove it was not. The court found that the company breached the contract by failing to properly project manage the construction and Kerry Smith breached his duty of care in failing to adequately project manage the construction. The court found the company and/or Kerry Smith were liable to the plaintiffs for some defective work, but the plaintiffs had failed to prove any loss associated with other alleged failures to adequately project manage the construction. The court granted leave to the plaintiffs to amend the pleadings to include a fourth alleged representation and ordered the plaintiffs to pay the company $94,934.74 plus interest. The court reserved the question of costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.