| IN THE SUPREME COURT OF NEW ZEALAND |
| SC 134/2017 [2018] NZSC 19 |
| BETWEEN | MANCHESTER SECURITIES LIMITED |
| AND | BODY CORPORATE 172108 |
| Court: | William Young, Glazebrook and Ellen France JJ |
Counsel: | M C Harris and H E McQueen for Applicant |
Judgment: | 14 March 2018 |
JUDGMENT OF THE COURT
A The application for leave to appeal is dismissed.
B Costs of $2,500 are awarded to the respondent.
____________________________________________________________________
REASONS
This application for leave to appeal concerns a leaky high-rise apartment complex. Almost all of the top floor (level 12) is a penthouse privately owned by Manchester Securities Ltd (Manchester) with the remaining areas, such as the stairwell and lift, being common property.
In 2009 the Body Corporate applied to the High Court, under s 48 of the Unit Titles Act 1972, to sanction a scheme for integrated repairs to all levels of the building, including level 12. This was necessary because otherwise the Body Corporate could only carry out repairs to common property. Manchester opposed the scheme.
The application was eventually successful,[1] the order sanctioning the scheme being sealed on 13 April 2011. Under the scheme Manchester’s liability was capped at 11.88 per cent of the total cost of repairs to levels 1-11 less the cost of repairs to level 12 to reflect their unit entitlement.[2]
[1]Body Corporate 172108 v Meader (No 2) HC Auckland CIV 2009-404-6868, 19 August 2010 (Heath J).
[2]Body Corporate 172108 v Meader & Ors HC Auckland CIV 2009-404-6868, 3 March 2010 at [48]-[50] per Heath J; Body Corporate 172108 v Meader, above n 1, at [36] per Heath J.
The work, however, took longer and was more expensive than contemplated at the time of the scheme. This meant that, instead of Manchester making a contribution to the common property repairs, the owners would be contributing to Manchester’s repairs.
The Body Corporate applied to vary the scheme. Manchester opposed the application.
The High Court amended the scheme, lifting the cap of 11.88 per cent and reinstating the unit title statutory scheme.[3] A provisional sum was ordered to be paid to the Body Corporate by Manchester to be adjusted on completion of remediation.[4] The Court of Appeal dismissed Manchester’s appeal.[5]
[3]Body Corporate 172108 v Manchester Securities Ltd [2017] NZHC 329 at [155]-[157] per Fogarty J
[4]At [157] per Fogarty J.
[5]Manchester Securities Ltd v Body Corporate 172108 [2017] NZCA 527 (French, Cooper and Brown JJ).
Manchester argues that the following issues of general and public importance arise:
(a)The jurisdiction for varying (as against settling) a scheme.
(b)Whether a court can vary a scheme by effectively starting again. It is argued in this case that it should have been varied only to the extent of costs relating to Manchester’s “dilatory remediation”.
(c)The relationship between the power to vary a scheme and the arbitration clause. Manchester argues that the proper approach was to quantify the additional remediation costs under the arbitration clause.
The Body Corporate submits that these are largely factual issues or depend on factual issues. We accept that submission.
Whether or not it was appropriate to vary the scheme depended on an assessment of all the particular circumstances of this case. It follows that no issue of general or public importance arises. Nor does the material put forward by Manchester suggest any risk of a miscarriage of justice.[6]
Result
[6]Junior Farms Ltd v Hampton Securities Ltd (in liq) [2006] NZSC 60, (2006) 18 PRNZ 369 at
[4]–[5].
The application for leave to appeal is dismissed. Costs of $2,500 are awarded to the respondent.
Solicitors:
Gilbert/Walker, Auckland, for Applicant
Grove Darlow & Partners, Auckland, for Respondent
- AGLC
- Manchester Securities Ltd v Body Corporate 172108 [2018] NZSC 19
- Case
- [2018] NZSC 19
- Decision Date
CaseChat Overview and Summary
The legal issues that arose in this case were whether the jurisdiction for varying a scheme, whether a court can vary a scheme by effectively starting again, and the relationship between the power to vary a scheme and the arbitration clause. Manchester argued that the proper approach was to quantify the additional remediation costs under the arbitration clause. The Body Corporate submitted that these were largely factual issues or depended on factual issues. The court accepted that submission and found that whether or not it was appropriate to vary the scheme depended on an assessment of all the particular circumstances of this case. It follows that no issue of general or public importance arises.
The court dismissed the application for leave to appeal, and costs of $2,500 were awarded to the respondent. The court found that the Body Corporate's application to vary the scheme was appropriate, given the particular circumstances of this case. The court also found that the material put forward by Manchester did not suggest any risk of a miscarriage of justice.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.