Kitchener & Co (1989) Limited v Concrete Solutions Limited

Link copied
Case Copied 34 min read

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY

I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE

CIV-2023-409-531

[2024] NZHC 653

BETWEEN

KITCHENER & CO (1989) LIMITED, ANTHONY STEWART HENDERSON and DAVID STEWART HENDERSON

Appellants

AND

CONCRETE SOLUTIONS LIMITED

Respondent

Hearing: 22 February 2024

Appearances:

D W Grove for Appellants F B Collins for Respondent

Judgment:

22 March 2024


JUDGMENT OF OSBORNE J


This judgment was delivered by me on 22 March 2024 at 4.00 pm pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar Date:

KITCHENER & CO (1989) LTD v CONCRETE SOLUTIONS LIMITED [2024] NZHC 653 [22 March 2024]

Introduction

[1]    The first-named appellant (Kitchener) was, from 2019, developing an apartment complex in Christchurch (building). The respondent (Concrete Solutions), a concrete specialist contractor, provided repair and strengthening works (contract work) pursuant to a written contract (contract).

[2]The contract was subject to the Construction Contracts Act 2002 (Act).

[3]    After Kitchener failed to respond to two payment claims served on it by the payment or provision of a payment schedule, it entered an agreement with Concrete Solutions (payment agreement). In doing so, it agreed to make payment on or before specified dates of those and any amounts that subsequently became due under the contract.

[4]    Anthony and David Henderson (Hendersons) were the directors of Kitchener. They gave personal guarantees of Kitchener’s obligations under the payment agreement in consideration of Concrete Solutions’ granting Kitchener further time to pay the two sums owing under the contract. The payment agreement included a “no set-off” clause.

[5]    Kitchener failed to make the agreed payments under the payment agreement. The Hendersons did not make payment pursuant to their personal guarantees.

[6]    Concrete Solutions sued Kitchener and the Hendersons in the District Court seeking as principal $26,061.21, together with contractual interest and costs.

[7]    The defendants filed a defence and counterclaim asserting Concrete Solutions had breached its contractual obligations.

[8] It transpired that a scheduled trial was unable to proceed. At that point, Concrete Solutions obtained leave to file a summary judgment application. The circumstances of those arrangements are dealt with below from [67].

[9]    The summary judgment application was then heard by Judge Toohey who entered summary judgment for Concrete Solutions in the principal sum of $26,061.21, together with contractual interests and costs (judgment).1

Appeal

[10]Kitchener and the Hendersons (appellants) appeal the judgment. They assert:

(a)the circumstances by which summary judgment was able to be obtained were at least partly due to Concrete Solutions’ conduct through a failure to serve witness statements for the substantive trial;

(b)Concrete Solutions was estopped from seeking summary judgment as, by its conduct, it had agreed that a merits-based decision would be sought at the scheduled trial;

(c)Concrete Solutions’ pleaded cause of action did not rely on the default provisions of the Act — consequently Concrete Solutions was not entitled to rely on the default provisions under the Act;

(d)Concrete Solutions was not entitled to rely on a “no set-off” clause in the payment agreement in order…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kitchener & Co (1989) Limited v Concrete Solutions Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NZHC 653
Decision Date

CaseChat Overview and Summary

Kitchener & Co (1989) Limited, Anthony Stewart Henderson, and David Stewart Henderson (appellants) appealed the judgment entered in favour of Concrete Solutions Limited (respondent) in the District Court. The appeal related to a contract for repair and strengthening works on an apartment complex in Christchurch. Kitchener, the appellants' company, had failed to meet its payment obligations under a payment agreement, leading Concrete Solutions to seek summary judgment. The appeal raised issues about the circumstances under which summary judgment was granted, the enforceability of the "no set-off" clause in the payment agreement, and the application of the "pay now, argue later" regime under the Construction Contracts Act 2002.

The court found that the Judge's decision to grant summary judgment was justified. The payment agreement explicitly precluded set-off and deduction, and the "pay now, argue later" regime applied to the undisputed debts. The "no set-off" clause and the statutory regime protected Concrete Solutions' right to payment. The court rejected the appellants' argument that Concrete Solutions could not rely on the "no set-off" clause due to its alleged breaches. The court also found that there was no basis to exercise the residual discretion to refuse summary judgment or to stay enforcement of the judgment. The appellants' financial difficulties did not justify a stay, as they had committed to the payment agreement terms.

The appeal was dismissed, and the appellants were ordered to pay the respondent's costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.