IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA
TE WHANGANUI-Ā-TARA ROHE
CIV-2017-485-000436 [2017] NZHC 2636
IN THE MATTER of the Judicial Review Procedure Act 2016 IN THE MATTER
of an application for Judicial Review
BETWEEN
GRAEME MARTIN CONTRACTING LIMITED
Applicant
AND
DISPUTES TRIBUNAL First Respondent
DISTRICT COURT AT WELLINGTON Second Respondent
CHORUS NEW ZEALAND LIMITED Third Respondent
Hearing: 25 October 2017 Counsel:
E J Tait for Applicant
No appearance for First and Second Respondents
R L Goss for Third RespondentJudgment:
27 October 2017
JUDGMENT OF COLLINS J
Introduction
[1] On 16 January 2015 Graeme Martin Contracting Ltd (GMCL) severed a fibre optic cable owned by Chorus New Zealand Ltd (Chorus). The incident occurred on McCormacks Bay Road in Christchurch whilst GMCL was excavating a deep trench to install replacement sewer mains that had been damaged in the Christchurch
earthquakes.
GRAEME MARTIN CONTRACTING LIMITED v DISPUTES TRIBUNAL [2017] NZHC 2636 [27 October
2017]
[2] Chorus incurred costs of $17,172.91 for the repair of the cable and commenced proceedings in the Disputes Tribunal (the Tribunal) in March 2016 to recover $15,000, being the maximum sum that can be recovered in that jurisdiction.
[3] The Tribunal ordered GMCL to pay Chorus $15,000.1 That decision was upheld by the District Court.2 A subsequent application for a rehearing of the Disputes Tribunal’s decision was declined.3 GMCL has now applied to judicially review both the Tribunal and District Court decisions alleging that the processes followed by the Tribunal were procedurally unfair and that the decisions of the Tribunal and the District Court were unreasonable.
[4] This judgment explains why none of the grounds for judicial review have been established.
Background
[5] GMCL is a well established contractor in Christchurch that at the relevant time was carrying out a sub-contract for Fulton Hogan. Before excavating the trench on McCormacks Bay Road, GMCL obtained plans of the area from Fulton Hogan that had in turn been supplied by Chorus (the Chorus plans). Those working on the site comprised three employees of GMCL and one from Fulton Hogan. The workers excavated by hand to a depth of about 0.5 metres and located two cable ducts. Because the land in the area was just above the high tide level and the soil very unstable, GMCL had to protect the edges of the trench with sheet piles to stop the trenches collapsing.
[6] After exposing the two ducts at about 0.5 metres, GMCL used mechanical devices to dig the rest of the trench but in doing so severed a third cable lying at a
depth of about 2.5 metres.
1 Chorus New Zealand Ltd v Graeme Martin Contracting Ltd DT Wellington CIV-2016-085-176,
24 June 2016.
2 Graeme Martin Contracting Ltd v Chorus New Zealand Ltd [2017] NZDC 1622.
3 Chorus New Zealand Ltd v Graeme Martin Contracting Ltd DT Wellington CIV-2016-085-176,
12 April 2017.
[7] The key factual issue was whether the Chorus plans disclosed the existence of two or three ducts. If…
Keep reading for free
Create a free CaseChat account to read Graeme Martin Contracting Limited v Disputes Tribunal and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 2636
- Decision Date