FOR A COURT READY (FEE REQUIRED) VERSION PLEASE FOLLOW THIS LINK
| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA483/2018 [2020] NZCA 113 |
| BETWEEN | BATHURST RESOURCES LIMITED |
| AND | L&M COAL HOLDINGS LIMITED |
| Hearing: | 21–23 August 2019; further submissions 27 and 30 August 2019 |
Court: | Kós P, Gilbert and Goddard JJ |
Counsel: | J E Hodder QC, R J Gordon and D P MacKenzie for Appellants |
Judgment: | 24 April 2020 at 10 am |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
B The appellants must pay the respondent costs for a complex appeal on a band B basis plus usual disbursements. We certify for second counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by Kós P)
Bathurst acquired coal mining rights on the West Coast of New Zealand’s South Island from L&M. Part of the purchase price was deferred. Two performance payments, each of US$40 million, were payable when 25,000 tonnes, and then one million tonnes, of coal had been shipped from the permit areas.
Although more than 50,000 tonnes of coal have now been mined by Bathurst from the permit areas, it says this does not trigger the first performance payment obligation. It says the coal has not been “shipped” from the permit areas.
Moreover, Bathurst has now mothballed the mining operation. It is focusing on mining opportunities elsewhere. It accepts liability to pay royalties to L&M on any coal mined and sold, although nothing now is being mined and little is being sold. But it denies any present liability for the first performance payment. It says cl 3.10 of the sale agreement enables it to postpone that payment so long as it pays royalties, at a higher 10 per cent rate, on the coal it sells.
L&M issued proceedings in December 2016. It sought a declaration that the first performance payment was due and owing, and an order that Bathurst pay US$40 million to L&M, together with interest and costs.
Dobson J held in favour of L&M.[1] Bathurst appeals.
Issues on appeal
[1]L&M Coal Holdings Ltd v Bathurst Resources Ltd [2018] NZHC 2127 [High Court judgment].
Three issues arise on appeal:
(a)What is the correct meaning of “shipped from the Permit Areas” in cl 3.4 of the sale agreement?
(b)What is the true effect of cl 3.10 of the same agreement?
(c)Should a term be implied requiring Bathurst to undertake substantive continuing levels of production?
Background
L&M is a company incorporated under Belize law. Its principal business office is in Hong Kong. It is effectively governed by its founder, Mr Geoff Loudon, a New Zealand-based geologist and investor in mineral resources. Bathurst is a company incorporated under New Zealand law. Its registered office is in Wellington. It has interests in the mining of natural resources, including coal. It is listed on the Australian stock exchange. Between September 2010 and July 2015 it was…
Keep reading for free
Create a free CaseChat account to read Bathurst Resources Ltd v L&M Coal Holdings Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NZCA 113
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.