IN THE COURT OF APPEAL OF NEW ZEALAND
CA457/2009
[2010] NZCA 345AND BETWEEN AUCKLAND CITY COUNCIL
Appellant
ANDPETER HARDIE MCNAMARA AND PATRICK STURGEON MCNAMARA AS TRUSTEES OF THE P H MCNAMARA FAMILY TRUST
Respondent
Hearing:19 May 2010
Court:Hammond, Arnold and Baragwanath JJ
Counsel:D J Goddard QC and M A Cavanaugh for Appellant
B O'Callahan and G S G Erskine for Respondent
Judgment:3 August 2010 at 9.30am
JUDGMENT OF THE COURT
A The appeal is allowed.
B Summary judgment is entered in favour of the appellant.
CThe respondents must pay the appellant costs for a standard appeal on a band A basis and usual disbursements in the Court of Appeal.
DThe respondents must pay the appellant costs on a 2B basis and disbursements in the High Court.
____________________________________________________________________
REASONS OF THE COURT
(Given by Baragwanath J)
[1] This is a leaky building case, concerning the liability of the appellant territorial authority where an independent building certifier has purported to certify compliance with the building code made under the Building Act 1991.[1] The building certifier, although duly appointed and authorised to certify compliance with a broad range of building work, could certify compliance with the Building Code’s external moisture provisions only if the building complied with Approved Standard E2/AS1, which the respondents say it did not. Is there a residual liability on the authority under the principles stated in Invercargill City Council v Hamlin[2] and Sunset Terraces[3] for negligence in the inspection or otherwise?
The scheme
[1] Now repealed.
[3] Sunset Terraces [2010] NZCA 64.
[2] The Act forbade the performance of building work except in accordance with a building consent issued by the territorial authority.[4] All building work was required to comply with the building code.[5] Once it was completed the owner was required as soon as practicable to advise the local authority of that fact.[6] The Act contemplated that a satisfactorily completed building would be the subject of a code compliance certificate (CCC) issued to the owner.[7]
[4] Section 32(1).
[5] Section 7(1).
[6] Section 43(1).
[7] Section 43.
[3] The Act provided two alternative means by which a CCC could be obtained. One was by paying the authority its charge for satisfying itself that the building work complied with the building code and so should receive a CCC, in which case the CCC was issued by the authority. In such case it was the responsibility of the authority to exercise reasonable care to satisfy itself that issue of the CCC was justified. That would require it either to carry out its own inspections or to receive from a building certifier building certificates vouching for the due performance of the work. In the latter event the italicised portions of s 50 applied:
(1) A territorial authority shall accept the following documents as establishing compliance with the provisions of the…
Keep reading for free
Create a free CaseChat account to read Auckland City Council v McNamara and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] NZCA 345
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi