IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2018-404-2555
[2019] NZHC 2094
UNDER the Judicial Review Procedure Act 2016 IN THE MATTER
of an application for judicial review
IN THE MATTER
of the Construction Contracts Act 2002
BETWEEN
ACE STRUCTURAL LIMITED
Applicant
AND
JOHN GREEN
First Respondent
FIRMA CONSTRUCTION LIMITED
Second Respondent
Hearing: On the papers Counsel:
B Martelli for the Applicant
K Badcock for the Second Respondent
Judgment:
23 August 2019
JUDGMENT OF GORDON J
[As to costs]
This judgment was delivered by me
on 23 August 2019 at 3.00 pm, pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar Date:
Solicitors: Heaney & Partners
K A Badcock, Rotorua
ACE STRUCTURAL LTD v GREEN [2019] NZHC 2094 [23 August 2019]
Introduction
[1] On 4 July 2019, I gave judgment in favour of the applicant, Ace Structural Ltd (Ace), against the respondents, John Green and Firma Construction Ltd (Firma).1
[2] The first respondent, Mr Green, adjudicated a dispute between Ace and the second respondent, Firma, in the Building Disputes Tribunal (BDT). Mr Green found in favour of Ace, but did not to award costs to Ace. Mr Green also ordered that the parties were to meet his fees in equal proportions. Ace applied to judicially review the costs decision and the quantum of Mr Green’s fees. Firma opposed the application. Mr Green was not represented at the hearing (the usual procedure for an adjudicator). He advised he would abide the decision of the Court.
[3] Ace sought an order quashing Mr Green’s findings as to costs and an order that this Court set costs for the BDT adjudication in favour of Ace. It also sought an order that Mr Green’s fees be limited to an amount considered appropriate by the Court or
$20,000.
[4] I found in favour of Ace in relation to the costs decision (on the basis of no or inadequate reasons) and made orders quashing Mr Green’s findings on costs as sought by Ace. I declined to make an order setting costs for the BDT adjudication. Instead, I remitted the matter back to Mr Green to re-determine costs with reasons to be given. I did not uphold Ace’s claim in relation to Mr Green’s fees, being a matter for appeal, not judicial review.
[5] The parties have been unable to agree on costs in this Court. Ace seeks costs and disbursements as set out in Annexure A to this judgment.2
1 Ace Structural Ltd v Green [2019] NZHC 1558.
2 There have been changes to the appropriate daily recovery rate and time allocations under schs 2 and 3 to the High Court Rules 2016. These changes apply to steps taken on or after 1 August 2019. The most recent step for which Ace seeks costs is the preparation of its memorandum on costs. That memorandum is dated 15 July 2019. Therefore, the new costs schedules do not apply to the present case.
The law
Continue reading Ace Structural Ltd v Green
Sign in free to access the full text
- AGLC
- Ace Structural Ltd v Green [2019] NZHC 2094
- Case
- [2019] NZHC 2094
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.