| For a Court ready (fee required) version please follow this link |
| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA538/2016 [2017] NZCA 409 |
| BETWEEN | ACE DEVELOPMENTS LIMITED |
| AND | ATTORNEY-GENERAL |
| Hearing: | 15 June 2017 (further material received 3 July 2017) |
Court: | French, Miller and Brown JJ |
Counsel: | F M R Cooke QC and G D Jones for Appellant |
Judgment: | 18 September 2017 at 12.00 pm |
JUDGMENT OF THE COURT
AThe application for leave to appeal is granted.
BThe appeal is dismissed.
CThe appellant must pay the respondent costs for a standard appeal on a band A basis together with usual disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by French J)
Table of Contents
Introduction [1]
Background [5]
The High Court decision at issue [15]
Two jurisdiction issues [22]
Is the proposed further evidence material to the appeal? [30]
Does the Canterbury Earthquake Recovery Act preclude [31]
compensation for relocation costs?
Are relocation costs “actual loss”? [39]
Are relocation costs “economic or consequential loss”? [41]
“Except as provided by this Act” [50]
Are Ace’s relocation costs recoverable under pt 5 of the [64]
Public Works Act?
Section 66 of the Public Works Act [67]
Section 68 of the Public Works Act [79]
Conclusion [82]
Outcome [87]
Introduction
Ace Developments Ltd owned land compulsorily acquired by the Crown under the Canterbury Earthquake Recovery Act 2011. The Associate Minister for Canterbury Earthquake Recovery determined that Ace should receive compensation for the taking based on the market value of the land. Ace disputes this and says compensation should be based on the costs of relocating its business.
Ace filed an appeal in the High Court against the Associate Minister’s determination. That appeal has yet to be heard.
This judgment is about an interlocutory application Ace made in the High Court seeking leave to adduce new evidence at the pending appeal. The application was declined by Gendall J, in part for reasons which if correct mean that Ace’s substantive appeal in that Court is doomed to fail.[1]
[1]Ace Developments Ltd v Attorney-General [2016] NZHC 2467 [High Court Decision].
That has prompted Ace to file an appeal in this Court against Gendall J’s interlocutory decision.
Background
Ace owned land and improvements situated at 115–117 Moorhouse Avenue, Christchurch. It developed the land for use as a car yard and as at 22 July 2014 was leasing the property to a car dealer. On 22 July 2014, the property was compulsorily acquired by the Crown under s 55 of the Canterbury Earthquake Recovery Act for the purposes of a proposed sports stadium.[2]
[2]The Crown compulsorily acquired the land on 22 July 2014 by proclamation: “Land Taken for Metro Sports Facility — Christchurch City” (31 July 2014) 82 New Zealand Gazette 2268. The land vested in the Crown on 14 August 2014.
Section 62 of the Canterbury Earthquake Recovery Act provides that a person who suffers loss resulting from the compulsory acquisition of land is entitled to compensation…
Continue reading Ace Developments Ltd v Attorney-General
Sign in free to access the full text
- AGLC
- Ace Developments Ltd v Attorney-General [2017] NZCA 409
- Case
- [2017] NZCA 409
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.