| CITATION: | WP & SB Cusack v Raceberry Pty Ltd [2013] QCAT 330 |
| PARTIES: | WP and SB Cusack Dilam Pty Ltd (Applicants) |
| V | |
| Raceberry Pty Ltd (Respondent) |
| APPLICATION NUMBER: | GAR197-12 |
| MATTER TYPE: | General administrative review matters |
| HEARING DATE: | 26 April 2013 |
| HEARD AT: | Brisbane |
| DECISION OF: | Richard Oliver, Senior Member |
| DELIVERED ON: | 2 July 2013 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Declare the contract entered into between the applicants and Stylebuilt Homes Australia Pty Ltd dated 3 March 2010 has been lawfully terminated. 2. The application is listed for a directions hearing on a date to be advised to the parties. |
| CATCHWORDS: | Home Warranty Insurance Scheme – where the insurance policy imposes and obligation on a homeowner to properly terminate the contract before the policy will respond to the claim – whether the contract was terminated lawfully under the contract – whether the contract was terminated otherwise at law – whether applicants elected to accept the builders repudiation – whether claim made in time. CGM investments Pty Ltd v Chelliah (2003) 196 ALR 548; Cheshire and Fifoot “Law of Contract” (8th Aust Ed, 2002) p. 42 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANTS: | Mr Cusack, solicitor |
| RESPONDENT: | Mr Turnbull, solicitor of HWL Ebsworth. |
REASONS FOR DECISION
The applicants are the owners of a house at Schmidt Road, Fernvale. They entered into a contract with Stylebuilt Factory Direct Homes Australia Wide Pty Ltd (“the builder”) for the construction of the house in March/April 2010. The house reached practical completion on 1 April 2011, however there was still work to be done by the builder. The builder went into liquidation in March 2012. The work was not completed so the applicants lodged a complaint with the Queensland Building Services Authority making a claim on the statutory Home Warranty Insurance Scheme (“Scheme”).
The Authority made a decision to reject the claim. In a letter to the applicants dated 2 May 2012 the Authority said the claim was out of time in that two years had passed since “the date of payment of the insurance premium or the date of entering into the contract (whichever is the earlier)”. As the premium was paid on 20 April 2010 the former ground is not relied upon, only the date of the contract. The applicants filed an application to review the decision of the Authority on 30 May 2012.
Subsequent to the filing of the application, the parties have agreed that the Tribunal should decide, as a preliminary issue, the question of whether there is a valid claim on the Scheme. That determination will depend on whether the contract was lawfully terminated by the applicants either in accordance with the terms of the building contract or otherwise at law. To…
Continue reading WP & SB Cusack v Raceberry Pty Ltd
Sign in free to access the full text
- AGLC
- WP & SB Cusack v Raceberry Pty Ltd [2013] QCAT 330
- Case
- [2013] QCAT 330
- Decision Date
CaseChat Overview and Summary
The court concluded that the contract was not terminated by performance or abandonment. It further found that the applicants did not terminate the contract lawfully under its terms. However, the court determined that the contract was lawfully terminated otherwise at law due to the builders' repudiation, as evidenced by their insolvency and the subsequent refusal of their administrators to fulfill contractual obligations. Despite this finding, the court noted that the timing of the applicants' claim remained contested, and the matter was relisted for further directions to address this issue.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.