QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Kusters v Queensland Building and Construction Commission [2024] QCAT 592
PARTIES:
TONY KUSTERS (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
APPLICATION NO:
GAR260-20
MATTER TYPE:
Building matters
DELIVERED ON:
13 December 2024
HEARING DATE:
24 September 2024
HEARD AT:
Brisbane
DECISION OF:
Member Scott-Mackenzie
ORDERS:
The internal review decision of Queensland Building and Construction Commission made 8 June 2020 a domestic building contract between Nigel Gary Borresen and Leonie Jane Borresen and Western Downs Plumbing and Building Supplies trading as ShedsnHomes Ipswich dated 4 September 2017 had been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme is confirmed.
CATCHWORDS:
GENERAL ADMINISTRATIVE REVIEW – BUILDING – INTERNAL REVIEW OF DECISION A DOMESTIC BUILDING CONTRACT HAS BEEN VALIDLY TERMINATED – whether owners in substantial breach of the contract – whether owners precluded from terminating the contract – whether contractor in substantial breach of the contract – whether owners validly terminated the contract
Queensland Building and Construction Commission Act 1991 (Qld), s 85A, s 86, s 87, s 67Y
Queensland Building and Construction Commission Regulation 2003 (Qld) (now repealed), sch 2C, sch 6, s 1, s 4, s 6
Queensland Civil and Administrative Act 2009 (Qld), s 17, s 24
Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63
Demir v Vision Built Pty Ltd (Building and Property) [2024] VCAT 1073
DJJ Promotions Pty Ltd v Gianacopoulos [2019] VCAT 177
Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No. 3) [2012] VSC 99
WP & SB Cusack v Raceberry Pty Ltd [2013] QCAT 330
Mazelow Pty Ltd v Herberton Shire Council [2003] 1 Qd R 174
Queensland Building Services Authority v Fox [2005] QDC 129
Stojanovski v Australian Dream Homes [2015] VSC 404
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
Ms Cooper of Counsel, instructed by HWL Ebsworth Lawyers
REASONS FOR DECISION
Application
On 20 July 2020 the applicant (‘Mr Kusters’) made application to the Tribunal to review a decision of the respondent (‘QBCC’) made 8 June 2020 (‘internal review decision’) that a domestic building contract between Nigel Gary Borresen and Leonie Jane Borresen (‘Mr and Mrs Borresen’ together and ‘Mr Borresen’ and ‘Mrs Borresen’ separately) and Western Downs Plumbing and Building Supplies trading as ShedsnHomes Ipswich (‘Western Downs’) dated 4 September 2017 had been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme (‘application’).
Background
The following facts are not in dispute.
On 4 September 2017 Mr and Mrs Borresen and Western Downs Plumbing and Building Supplies trading as ShedsnHomes Ipswich entered a Master Builders Queensland Residential Building Contract – Level 2 (‘building contract’) for the construction of a domestic residential building (‘building work’) at 90 Tatham Road, Haigslea (‘site’).
The contractor’s licence number specified in the building contract was that issued to Western Downs Irrigation and Building Supplies Pty Ltd. Mr Kusters is a former director and representative…
Keep reading for free
Create a free CaseChat account to read Kusters v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QCAT 592
- Decision Date
CaseChat Overview and Summary
The court first considered whether Mr and Mrs Borresen were in substantial breach of the contract, which would have precluded them from terminating under clause 20.3 of the contract. The court found that while Mr and Mrs Borresen took possession of the site and installed internal walls without permission, these actions did not amount to a substantial breach. The court noted that the defects identified were due to the contractor's failure to comply with the engineering design, and the changes to the mezzanine floor layout were not structural in nature. Furthermore, the court held that Mr and Mrs Borresen were not interfering with Western Downs' work but were attempting to complete the construction due to the contractor's delays and deficiencies.
Subsequently, the court assessed whether Mr and Mrs Borresen validly terminated the contract. The court found that Western Downs was in substantial breach of the contract due to multiple failures, including not completing the work diligently, not rectifying defective work, and not paying subcontractors. These breaches led to the conclusion that Western Downs repudiated the contract. Therefore, Mr and Mrs Borresen's termination of the contract was deemed valid.
In conclusion, the court confirmed the QBCC's decision that the domestic building contract was validly terminated, allowing a claim for non-completion under the statutory insurance scheme.
Orders
Orders of the court
The internal review decision of Queensland Building and Construction Commission made 8 June 2020 a domestic building contract between Nigel Gary Borresen and Leonie Jane Borresen and Western Downs Plumbing and Building Supplies trading as ShedsnHomes Ipswich dated 4 September 2017 had been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme is confirmed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The statutory insurance scheme is established by part 5 of the QBCC Act. The assistance available under the scheme is that prescribed by regulation.[4] The assistance a consumer for residential construction work is entitled to claim under the scheme if the work is incomplete is set out in part 2 of schedule 2C to the QBCC Regulation.[5] Relevantly, assistance for the reasonable cost of completing residential construction work is provided for in division 2 of part 2 of schedule 2C. The division applies to a consumer for residential construction work if, inter alia:(a)the work is carried out under a fixed price residential lot contract; and(b)the contract within two years after the day work starts under the contract; and(c)the work is incomplete.Consideration[4]QBCC Act, s 67Y.[5]QBCC Regulation, s 1(1).Issues The issues to be decided by the Tribunal are narrowly focused. First, were Mr and Mrs Borresen in substantial breach of the building contract when they purported to give to Mr Kusters notice of termination and thereby precluded from terminating the contract by clause 20.3? (Issue one) Secondly, on the assumption Mr and Mrs Borresen were not precluded from terminating the contract, did Mr and Mrs Borresen validly terminate the contract? (Issue two)Building contract Access to the site is provided for in clause 7.3 of the building contract. The party nominated in item 13 of the schedule to the contract is responsible for providing and maintaining access to the site for any persons, vehicles or machinery reasonably necessary for carrying out the building work. The person so nominated is the ‘Owner’. Clause 11.12 of the building contract prohibits the owner from interfering with the carrying out of the building work. Subclause (a) provides:The Owner must not obstruct, interfere with or hinder the carrying out of the Works. The Owner must take all reasonable steps to prevent all others from obstructing, interfering with or hindering the carrying out of the Works. The consequences of the owner taking possession of the works when not entitled to do so are provided for in clause 17.10. It provides:If the Owner takes Possession of the Works when not entitled to do so under this Contract, the Works are deemed to have reached Practical Completion without any defects or omissions on the Day that the Owner takes Possession, and the Owner is liable to the Contractor for any loss or damage that the Contractor may incur or suffer as a result. Possession is defined in clause 1 of the building contract. It means:... when the Works, or any part of the Works, are taken over, occupied or used by the Owner or the Owner’s employees, other contractors or agents ... The owner’s rights to terminate the building contract are set out in clause 20. Clause 20.1 provides:If the Contractor:(a) fails to proceed with the Works with due diligence or in a competent manner;(b) unlawfully suspends the carrying out of the Works;(c) refuses or persistently neglects to remove or remedy defective work or improper materials so that the progress of the Works is significantly, adversely affected;(d) is unable to complete the Works;(e) fails to effect or maintain any insurance policy required by this contract; or(f) is otherwise in Substantial Breach of this contract,the Owner may give a written notice to the Contractor by hand, registered post or facsimile transmission:(g) describing each alleged Substantial Breach of this Contract by the Contractor; and(h) stating the Owner’s intention to terminate this Contract unless the Contractor remedies the alleged Substantial Breach or Breaches within ten (10) Business Days after receiving the Owner’s notice.