Allen & Taylor v Queensland Building and Construction Commission

Link copied
Case Copied 63 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Allen & Taylor v Queensland Building and Construction Commission  [2020] QCAT 63

PARTIES:

REECE ALLEN

and

CHANTELL TAYLOR

(applicants)

v

QUEENSLAND BUILDING & CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S:

GAR136/18

MATTER TYPE:

General administrative review matters

DELIVERED ON:

27 February 2020

HEARING DATE:

28 August 2019

HEARD AT:

Brisbane

DECISION OF:

Member Richard Oliver

ORDERS:

The decision of the Queensland Building and Construction Commission is confirmed.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – CONTRACTS TERMINATION UNDER THE CONTRACT – TERMINATION UNDER THE GENERAL LAW – HOME WARRANTY INSURANCE SCHEME – where applicants entered in to a building construction contract with a registered builder – where works delayed and time for practical completion extended – where applicants dissatisfied with the building work – where applicants gave to the builder a Notice under the building construction contract – where builder responded to the Notice – where contract terminated by applicants – where the applicants made an insurance claim for incomplete building work on the statutory Home Warranty Insurance Scheme – where the respondents rejected the claim on the grounds that the applicants had not properly terminated the building construction contract with the builder in terms of insurance policy under the Home Warranty Insurance Scheme – whether the builder responded to the Notice by the stipulated time on the Notice – whether the builder’s response to the Notice was a reasonable response in the circumstances – whether the applicants properly terminated the building construction contract with the builder – whether the applicants lawfully terminated the building construction contract under the general law – whether the applicant’s termination of the building construction contract was a repudiation – whether the builder’s termination for repudiation was lawful.

Queensland Building and Construction Commission Act 1991 (Qld), Part 5, s 67X, Schedule 1B s 34

Building Act

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 20

Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99

Renard Constructions (ME) Pty Limited v Minister for Public Works (1992) 26 NSWLR 234
Shepherd v Felt & Textile Industries of Australia (1931) 45 CLR 359
Stojanovski v Australian Dream Homes [2015] VSC 404
Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623

Keswick Developments Pty Ltd ve Keswick Island Pty Ltd [2012] 2 Qld R 114.

APPEARANCES & REPRESENTATION:

Applicants:

R. Allen, Solicitor for the applicants

Respondent:

S. Seefield of Counsel, instructed by the Queensland Building and Construction Commission

REASONS FOR DECISION

  1. On 17 February 2016 the applicants entered into a building construction contract (‘the contract’) with Contrast Constructions Pty Ltd (‘Contrast’) for the construction of a residential dwelling in Paddington, Brisbane. The contract price for the house was $1,896,000.00. Work commenced soon after but by late 2017 the parties were in dispute. On 17 November 2017 the applicants terminated the contract. They then made…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Allen & Taylor v Queensland Building and Construction Commis... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QCAT 63
Decision Date

CaseChat Overview and Summary

The applicants, Allen and Taylor, brought a case against the Queensland Building and Construction Commission in the Queensland Civil and Administrative Tribunal. They entered into a building construction contract with a registered builder and were dissatisfied with the work being done. They issued a Notice under the contract to the builder, who responded, but the applicants terminated the contract. They subsequently made an insurance claim under the Home Warranty Insurance Scheme, which was rejected by the Commission on the basis that the applicants did not properly terminate the contract in terms of the insurance policy. The applicants sought to argue that the termination was proper both under the contract and at general law.

The primary issues before the court were whether the builder responded to the Notice by the stipulated time, whether the response was reasonable, whether the applicants properly terminated the building construction contract, whether the termination was lawful under the contract and at general law, and whether the termination constituted a repudiation by the builder. The court had to determine if the builder's response to the Notice was adequate and if the applicants had the right to terminate the contract.

The court found that the builder's response to the Notice was reasonable and satisfactory, and therefore the applicants did not have the right to terminate the contract. The court also found that the termination of the contract by the applicants was not lawful under the contract or at general law. The court held that the builder's conduct did not amount to a repudiation of the contract, as the builder's response to the Notice and the intention to complete the project demonstrated an intention to perform the contract.

The decision of the Queensland Building and Construction Commission was confirmed, and the applicants' claim was dismissed.

Orders

Orders of the court

The decision of the Queensland Building and Construction Commission is confirmed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

In the circumstances pertaining at the time of the issue of the show cause notice, I am satisfied that Contrast’s response to it was reasonable and satisfactory. Conclusion on the Notice to Show Cause When looked at objectively,[44] the complaints of the applicants at the time of issuing the Notice, particularly when the works were 70% complete with further work to do to bring the whole project together, each of the responses to the notice addressed the applicants’ concerns. The responses were not so inadequate that they gave rise to a right to terminate the contract. In so far as it might be said that they are breaches, the breaches were not, having regard to the test referred to above, substantial breaches within the meaning of clause 39 of the contract.[44]Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234. The applicants submit that if the Tribunal is satisfied that Contrast has provided a satisfactory response to the Notice, then there still remains a right, because of other substantial breaches, to terminate the contract. It is in this context that the applicants rely on Sheppard’s case to justify the termination as a result of breaches of contract only ascertained after the applicants took possession of the building site. The further grounds are adopted from the applicants’ written submissions. The applicants make a general submission that Contrast’s attitude throughout its performance under the contract so disregards its contractual obligations that it amounts to repudiation. In particular they submit that Mr Durkin’s evidence was such that he did not believe Contrast was bound by the terms of the contract with respect to time, quality, engagement of approved subcontractors and the statutory requirements of the National Construction Code, the Building Act and the QBCC Act.[45][45]Applicants’ Submissions, paragraph 201. Authority is cited for the proposition[46] that the approach is whether the conduct of one party is such as to convey to a reasonable person, in the situation of the other party, renunciation either of the contract as a whole or of a fundamental obligation under it. The submission flies in the face of what actually occurred up to the issuing of the Notice. Firstly, the works were about 70% complete; secondly, until there was a change in the cabinet supplier the WUC were proceeding as efficiently as possible taking into account the agreed extensions of time and the delay in responses to requests for information from the Superintendent. Furthermore, Contrast’s response to the Show Cause Notice and the fact that I found the response reasonable in the circumstances, evinced a clear intention on the part of Contrast that it wanted to continue to take the works to practical completion and finish the project. These objective facts support the conclusion that the intention of Contrast when viewed by ‘a reasonable person’ did not demonstrate a ‘disavowal either of the contract as a whole or of a fundamental obligation under it’.[47][46]Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61, [44].[47]Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623 at 658 also see Keswick Developments Pty Ltd ve Keswick Island Pty Ltd [2012] 2 Qld R 114 at [57].

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.