Land and Environment Court
New South Wales
Medium Neutral Citation: Western Sydney Conservation Alliance v Penrith City Council [2011] NSWLEC 244 Hearing dates: 31 October 2011, 1 and 3 November 2011 Decision date: 16 December 2011 Jurisdiction: Class 4 Before: Moore AJ Decision: 1. That the operation of the consents to DA 11/0514, DA 11/0515, DA 11/0516 and DA 11/0517 be suspended in part.
2. The operation of the consents not be suspended to the extent necessary to carry out such development as is reflected in the undertaking of the second and third respondents noted in paragraph 7 of these orders.
3. The consents be validated upon the first respondent having regard to the details of the Cumberland Plain Recovery Plan gazetted 18 February 2011.
4. The application otherwise be dismissed.
5. Each party pay its own costs.
6. The second and third respondents be released from the undertaking given on 13 October 2011.
7. The Court notes the undertaking given to the Court by the second and third respondents, through their solicitor that they will not, by themselves their servants or agents or assigns, carry out development for the residential subdivision of land at the Western Precinct of the St Marys Release Area known as "Jordan Springs, Villages 2" pursuant to DA 11/0514, DA 11/0515, DA 11/0516 or DA 11/0517, other than within the areas identified as "Required Infrastructure Areas" marked in orange on the plan attached to the short minutes of order submitted by the second and third respondents on 13 December 2011.
Catchwords: JUDICIAL REVIEW - whether consideration of recovery plan necessary - whether consideration given to particular recovery plan Legislation Cited: The Environmental Planning and Assessment Act 1979 (NSW)
The Threatened Species Conservation Act 1995 (NSW)Cases Cited: Aldous v Greater Taree City Council (2009) 167 LGREA 13
Homemakers Supacenta-Belrose Pty Ltd v Warringah Council (No 2) (2008) 158 LGERA 90
Newcastle & Hunter Valley Speleological Society Inc v Upper Hunter Shire Council [2010] NSWLEC 48
Timbarra Protection Coalition Inc v Ross Mining NL (1999) 46 NSWLR 55
Zhang v Canterbury City Council (2001) 51 NSWLR 589Category: Principal judgment Parties: Western Sydney Conservation Alliance Inc (Applicant
Penrith City Council (First Respondent)
Maryland Development Company Pty Ltd (Second Respondent)
St Mary's Land Limited (Third Respondent)Representation: Mr C D Norton (Applicant)
Mr A M Pickles (First Respondent)
Mr N A Hemmings QC (Second and Third Respondents)
Environmental Defender's Office (NSW) (Applicant)
Sparke Helmore (First Respondent)
Allens Arthur Robinson (Second and Third Respondents)
File Number(s): 40873 of 2011
Judgment
Introduction
Metropolitan Sydney occupies much of the Cumberland Plain. On the Cumberland Plain the Juniper-leaved Grevillia and the Pultenaea parviflora are vulnerable and endangered flora species respectively. Similarly the Cumberland Land Snail is an endangered fauna species. Likewise the River-flat Eucalyptus Forest is an endangered ecological community while the Cumberland Plain Woodland is a critically endangered community . The Threatened Species Conservation Act 1995 (NSW) ("TSC Act") serves to protect these and other endangered species of…
Keep reading for free
Create a free CaseChat account to read Western Sydney Conservation Alliance v Penrith City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWLEC 244
- Decision Date
CaseChat Overview and Summary
The legal issues before the court involved whether the Council had properly exercised its discretion in issuing the development approvals, and whether the Cumberland Plain Recovery Plan should have been taken into account in the decision-making process. The court needed to determine whether the approvals were invalid or should be suspended, and whether the Conservation Alliance was entitled to the relief sought.
The court found that the Council had failed to properly consider the Cumberland Plain Recovery Plan in issuing the approvals, and that the approvals were therefore invalid. However, the court did not grant a full suspension of the operation of the consents. Instead, it ordered a partial suspension, allowing the Council to proceed with development within certain areas identified as "Required Infrastructure Areas". The court also directed the Council to validate the consents upon considering the Cumberland Plain Recovery Plan. The Conservation Alliance's application was dismissed in all other respects, and each party was ordered to bear its own costs.
The court's orders reflect a balanced approach, recognising the need for development while also protecting the environment. The court's decision highlights the importance of considering relevant planning instruments, such as the Cumberland Plain Recovery Plan, in the decision-making process for development approvals.
Orders
Orders of the court
1. That the operation of the consents to DA 11/0514, DA 11/0515, DA 11/0516 and DA 11/0517 be suspended in part.
2. The operation of the consents not be suspended to the extent necessary to carry out such development as is reflected in the undertaking of the second and third respondents noted in paragraph 7 of these orders.
3. The consents be validated upon the first respondent having regard to the details of the Cumberland Plain Recovery Plan gazetted 18 February 2011.
4. The application otherwise be dismissed.
5. Each party pay its own costs.
6. The second and third respondents be released from the undertaking given on 13 October 2011.
7. The Court notes the undertaking given to the Court by the second and third respondents, through their solicitor that they will not, by themselves their servants or agents or assigns, carry out development for the residential subdivision of land at the Western Precinct of the St Marys Release Area known as "Jordan Springs, Villages 2" pursuant to DA 11/0514, DA 11/0515, DA 11/0516 or DA 11/0517, other than within the areas identified as "Required Infrastructure Areas" marked in orange on the plan attached to the short minutes of order submitted by the second and third respondents on 13 December 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi