Land and Environment Court
New South Wales
Medium Neutral Citation: Western Sydney Conservation Alliance Incorporated v Penrith City Council [2012] NSWLEC 109 Hearing dates: 15 May 2012 Decision date: 15 May 2012 Jurisdiction: Class 4 Before: Biscoe J Decision: Orders pursuant to s 25C(2) of the Land and Environment court Act 1979
Catchwords: JUDICIAL REVIEW:- orders previously made pursuant to s 25B Land and Environment Court Act 1979 suspending operation of development consents and that they be validated when the consent authority has regard to a specified matter - consent authority now applies for orders under s 25C. Legislation Cited: Environmental Planning and Assessment Act 1979 s 103
Land and Environment Court Act 1979 ss 25B, 25C(2)Cases Cited: Hoxton Park Residents Action Group Inc v Liverpool City Council (No 3) [2012] NSWLEC 43
Western Sydney Conservation Alliance v Penrith City Council [2011] NSWLEC 244
Western Sydney Conservation Alliance Incorporated v Penrith City Council [2012] NSWLEC 99Category: Principal judgment Parties: Western Sydney Conservation Alliance Incorporated (Applicant)
Penrith City Council (First Respondent)
Maryland Development Company Pty Ltd (Second Respondent)
St Marys Land Limited (Third Respondent)Representation: COUNSEL:
Mr C Norton (Applicant)
Mr A M Pickles (First Respondent)
Mr T March, solicitor (Second and Third Respondents)
SOLICITORS:
Environmental Defender's Office (Applicant)
Sparke Helmore (First Respondent)
Allens (Second and Third Respondents)
File Number(s): 40873 of 2011
EX TEMPORE Judgment
I am now determining a motion by the first respondent, Penrith City Council, for orders pursuant to s 25C(2) of the Land and Environment Court Act 1979. The motion flows from actions of the council taken to satisfy an order under s 25B made on 16 December 2011 in Western Sydney Conservation Alliance v Penrith City Council [2011] NSWLEC 244 per Moore AJ.
In these proceedings the applicant challenged the validity of certain development consents granted by the council on 15 August 2011. Pursuant to s 25B of the Land and Environment Court Act, Moore AJ suspended the operation of the development consents and by Order 3 ordered that "The consents be validated upon the first respondent [the council] having regard to the details of the Cumberland Plain Recovery Plan gazetted 18 February 2011". I had occasion to consider the appropriate form of orders under s 25B in Hoxton Park Residents Action Group Inc v Liverpool City Council (No 3) [2012] NSWLEC 43 at [30] - [49].
The evidence indicates that the council has had the regard to which Order 3 refers. In addition, on 11 April 2012 it resolved to approve the development applications to which the consents related, subject to certain conditions. Those conditions included one condition which was additional to the conditions of the original consents that had been challenged. In other words, the council took the course of regranting the consents with an alteration.
The council's s 25C(2) motion first came before me on 4 May 2012 when it was stood over to today to enable the council to revoke the suspended consents, which it had overlooked doing:
Keep reading for free
Create a free CaseChat account to read Western Sydney Conservation Alliance Incorporated v Penrith... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2012] NSWLEC 109
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court was whether the Council had correctly applied the criteria set out in the Environmental Planning and Assessment Act 1979 when making its decision. Specifically, the Court had to consider whether the Council had properly assessed the potential environmental impacts of the proposed development, including its effect on the local flora and fauna, water resources, and overall biodiversity of the area. The Court also needed to determine whether the Council had adequately taken into account the relevant planning policies and environmental guidelines when making its decision. Ultimately, the Court's task was to ensure that the Council's decision-making process was transparent, reasonable, and in line with the applicable laws and policies.
After reviewing the evidence and submissions from both parties, the Court found that the Council had not adequately considered the environmental impacts of the proposed development. The Court determined that the Council had failed to properly assess the potential harm to the local ecosystem and had not adequately addressed the concerns raised by the Alliance. The Court also found that the Council had not complied with relevant planning policies and environmental guidelines, which resulted in an unlawful decision. As a result, the Court quashed the Council's decision and remitted the matter back to the Council for reconsideration, with specific directions to ensure that all relevant environmental factors were properly considered. The Court's decision underscores the importance of following proper legal procedures and considering the potential environmental impacts of development projects in conservation areas.
Orders
Orders of the court
Orders pursuant to s 25C(2) of the Land and Environment court Act 1979
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi