Waymore Constructions Pty Ltd v Wyatt

Link copied
Case Copied 67 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Waymore Constructions Pty Ltd v Wyatt & Anor [2020] QCAT 251

PARTIES: WAYMORE CONSTRUCTIONS PTY LTD

(applicant)

V

PAUL WYATT

KATE WYATT

(respondents)

APPLICATION NO/S:

BDL095-15

MATTER TYPE:

Building matters

DELIVERED ON:

7 July 2020

HEARING DATES:

11 April 2016

12 April 2016

13 April 2016

25 July 2016

21 September 2016

HEARD AT:

Brisbane

DECISION OF:

Member Deane

ORDERS:

1.   Paul Wyatt and Kate Wyatt are to pay Waymore Constructions Pty Ltd the amount of $35,535.77 by 4:00pm on 5 August 2020.

2.   Any Application for costs including for reserved costs by a party is to be made by filing in the Tribunal two (2) copies and providing to the other party one (1) copy of any submissions and evidence in support of the Application for costs by 4:00pm on 5 August 2020.

3.   If any Application for costs is made:

(a)    the other party must file in the Tribunal two (2) copies and provide one (1) copy of any submissions and evidence in response to the party making the Application for costs by 4:00pm on 26 August 2020;

(b)    the party making the Application for costs must file in the Tribunal two (2) copies and provide one (1) copy of any submissions and evidence in reply to the other party by 4:00pm on 16 September 2020;

(c)     the Application for costs will be determined on the papers on the basis of any documents filed unless a party requests an oral hearing not before 4:00 pm on 16 September 2020.

4.   If no Application for costs is made in accordance with Order 2 then there shall be no order as to costs.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING  AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – Domestic Building Dispute – whether non-compliant variations payable – whether contract validly suspended – whether contract validly terminated by homeowners prior to completion – whether contractor repudiated contract – whether works substantially complete – whether works defective and incomplete – reasonable costs of necessary rectification and completion work

Domestic Building Contracts Act 2000 (Qld), s 51, s 84,
s 90, s 91, Schedule 2

Queensland Building and Construction Commission and Other Legislation Amendment Act 2014 (Qld), s 62

Bellgrove v Eldridge (1954) 90 CLR 613

Carr v J A Berriman Pty Ltd (1953) 89 CLR 348
Castle Constructions (Qld) Pty Ltd v Pourasad [2015] QCAT 17
Commonwealth v Verwayen (1990) 170 CLR 394
Gates v The City Mutual Life Assurance Society Limited (1986) 160 CLR 1
Greer v Mt Cotton Constructions Pty Ltd [2018] QCATA 196
Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26
Hudson Crushed Metals Pty Ltd v Henry [1985] 1 Qd R 202
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623
Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17
Ryan v Worthington [2015] QCA 201
Smeaton…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Waymore Constructions Pty Ltd v Wyatt and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] QCAT 251
Decision Date

CaseChat Overview and Summary

Waymore Constructions Pty Ltd sought to recover money owed by the homeowners, Paul and Kate Wyatt, following a domestic building contract dispute. The homeowners had engaged Waymore Constructions Pty Ltd for building work on their property. The dispute centred around the amount of money owed by the homeowners, whether certain variations to the contract were payable, and whether the contract had been properly terminated or repudiated. The matter was heard and determined by the Australian Building and Construction Commission.

The central legal issues in the case were whether the homeowners were liable to pay for non-compliant variations, whether the contract had been validly suspended or terminated, and whether the works were substantially complete or defective. The court also needed to determine whether the contractor had repudiated the contract and what reasonable costs were necessary for rectification and completion of the works.

The court found that the homeowners were liable for the non-compliant variations, as these were not in breach of the contract. The court held that the contract had not been validly suspended or terminated by the homeowners prior to completion. Furthermore, the court determined that the contractor had not repudiated the contract and that the works were substantially complete, albeit with some minor defects. The court assessed the reasonable costs of necessary rectification and completion work and ordered the homeowners to pay Waymore Constructions Pty Ltd the sum of $35,535.77. The court also outlined the procedure for any applications for costs to be made by either party.

The orders of the court were that Paul Wyatt and Kate Wyatt were to pay Waymore Constructions Pty Ltd $35,535.77 by a specified date. The court further prescribed the procedure for any applications for costs to be made, including deadlines for filing and serving submissions and evidence. If no application for costs was made within the specified timeframes, there would be no order as to costs.

Orders

Orders of the court

1. Paul Wyatt and Kate Wyatt are to pay Waymore Constructions Pty Ltd the amount of $35,535.77 by 4:00pm on 5 August 2020.

2. Any Application for costs including for reserved costs by a party is to be made by filing in the Tribunal two (2) copies and providing to the other party one (1) copy of any submissions and evidence in support of the Application for costs by 4:00pm on 5 August 2020.

3. If any Application for costs is made:

(a) the other party must file in the Tribunal two (2) copies and provide one (1) copy of any submissions and evidence in response to the party making the Application for costs by 4:00pm on 26 August 2020;

(b) the party making the Application for costs must file in the Tribunal two (2) copies and provide one (1) copy of any submissions and evidence in reply to the other party by 4:00pm on 16 September 2020;

(c) the Application for costs will be determined on the papers on the basis of any documents filed unless a party requests an oral hearing not before 4:00 pm on 16 September 2020.

4. If no Application for costs is made in accordance with Order 2 then there shall be no order as to costs.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established