CITATION: Castle Constructions (Qld) Pty Ltd v Pourasad [2015] QCAT 17
PARTIES: Castle Constructions (Qld) Pty Ltd
(Applicant)v Kaveh Pourasad
(Respondent)
APPLICATION NUMBER: BDL199-13
MATTER TYPE: Building matters
HEARING DATE: 21 – 22 August 2014, 25 September 2014 and 2 October 2014
HEARD AT: Brisbane
DECISION OF: Acting Senior Member Howard
DELIVERED ON: 21 January 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. Kaveh Pourasad must pay to Castle Constructions Pty Ltd the sum of $7499.33 by 4:00pm on 19 February 2015 in exchange for the certificates set out in order 2.
2. Castle Constructions Pty Ltd must give to Kaveh Pourasad the form 21 final certificate and all associated certificates for the house at 57 Messara Circuit, Durack by 4:00pm on 19 February 2015 in exchange for the payment of the amount in order 1.
3. Either party may file submissions in support of any claim for legal costs including a detailed breakdown of the costs claimed by 4:00pm on 19 February 2015.
4. If either party files submissions in accordance with order 3 above, the other party must file its submissions in response by 4:00pm on 12 March 2015.
5. Any claim/s for costs will be determined on the papers without an oral hearing not before 12 March 2015.
6. If no submissions are received from a party concerning their claim for costs in accordance with order 3 above, then the application for costs will be dismissed.
CATCHWORDS: DOMESTIC BUILDING DISPUTE – where builder claim final payment and for costs of variations, as well as interest and costs under the contract – where homeowner counter-claims for damages for rectification and incomplete works – whether homeowner took possession before practical completion – whether contract terminated by builder or homeowner – whether termination under contract or at common law – whether substantial compliance with practical completion – whether variations instructed – whether variations should be approved by Tribunal under Domestic Building Contracts Act 1999 – whether defective or incomplete building works
Domestic Building Contracts Act 1999 (Qld), s 44
Bellgrove v Eldridge (1954) 90 CLR 613
Bettini v Gye (1876) 1 QBD 183
Bolton v Mahadeva [1972] 1 WLR 1009
Cooper v Ungar (1958) 100 CLR 510
D Galambos & Son Pty Ltd v McIntyre (1974) ACTR 10
Hoenig v Isaacs [1952] All ER 176
Holland v Wiltshire (1954) 90 CLR 409
Kelly v Desnoe [1985] 2 Qd R 477
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Nina’s Bar & Bistro v MBE Corporation [1984] 3 NSWLR 613
Quinn Villages Pty Ltd v Mulherin [2006] QCA 433
Shevill v Builders Licensing Board (1982) 149 CLR 620APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Kava Piran, director, Castle Constructions (Qld) Pty Ltd represented Castle Constructions (Qld) Pty Ltd.
RESPONDENT: Mr Kaveh Pourasad represented himself. REASONS FOR DECISION
[1]This proceeding concerns a domestic building dispute. Essentially, Castle Constructions Pty Ltd (the builder) claims its final payment under a domestic building contract, the costs of variations together with costs of debt…
Continue reading Castle Constructions (Qld) Pty Ltd v Pourasad
Sign in free to access the full text
- AGLC
- Castle Constructions (Qld) Pty Ltd v Pourasad [2015] QCAT 17
- Case
- [2015] QCAT 17
- Decision Date
CaseChat Overview and Summary
The legal issues that the court had to decide were whether the homeowner had taken possession of the property before practical completion, whether the contract was terminated by the builder or the homeowner, whether the termination was under the contract or at common law, whether there was substantial compliance with practical completion, whether variations were instructed, and whether the variations should be approved by the Tribunal under the Domestic Building Contracts Act 1999. The court also had to determine whether the building works were defective or incomplete.
The court held that the homeowner had taken possession of the property before practical completion. The court found that the contract was terminated by the homeowner, and not by the builder. The court held that the termination was under the contract, and not at common law. The court found that there was substantial compliance with practical completion, and that the variations were instructed. The court held that the variations should be approved by the Tribunal under the Domestic Building Contracts Act 1999. The court found that the building works were incomplete, and that the homeowner was entitled to damages for the rectification and incomplete works.
The court ordered that the homeowner must pay the builder the sum of $7499.33 by 4:00pm on 19 February 2015 in exchange for the certificates set out in order 2. The builder must give to the homeowner the form 21 final certificate and all associated certificates for the house at 57 Messara Circuit, Durack by 4:00pm on 19 February 2015 in exchange for the payment of the amount in order 1. Either party may file submissions in support of any claim for legal costs including a detailed breakdown of the costs claimed by 4:00pm on 19 February 2015. If either party files submissions in accordance with order 3 above, the other party must file its submissions in response by 4:00pm on 12 March 2015. Any claim/s for costs will be determined on the papers without an oral hearing not before 12 March 2015. If no submissions are received from a party concerning their claim for costs in accordance with order 3 above, then the application for costs will be dismissed.
Orders
Orders of the court
1. Kaveh Pourasad must pay to Castle Constructions Pty Ltd the sum of $7499.33 by 4:00pm on 19 February 2015 in exchange for the certificates set out in order 2.
2. Castle Constructions Pty Ltd must give to Kaveh Pourasad the form 21 final certificate and all associated certificates for the house at 57 Messara Circuit, Durack by 4:00pm on 19 February 2015 in exchange for the payment of the amount in order 1.
3. Either party may file submissions in support of any claim for legal costs including a detailed breakdown of the costs claimed by 4:00pm on 19 February 2015.
4. If either party files submissions in accordance with order 3 above, the other party must file its submissions in response by 4:00pm on 12 March 2015.
5. Any claim/s for costs will be determined on the papers without an oral hearing not before 12 March 2015.
6. If no submissions are received from a party concerning their claim for costs in accordance with order 3 above, then the application for costs will be dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.