Viterra Operations Ltd (Trading as ABB Grain Storage and Handling) v Ewing International Limited Partnership

Link copied
Case Copied 29 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Appeals to a Single Judge: Permission to Appeal)

VITERRA OPERATIONS LTD (TRADING AS ABB GRAIN STORAGE AND HANDLING) v EWING INTERNATIONAL LIMITED PARTNERSHIP

[2010] SASC 328

Judgment of The Honourable Justice Sulan

21 December 2010

ARBITRATION - THE AWARD - FORM AND CONSTRUCTION OF THE AWARD - ERROR OF LAW ON THE FACE OF THE AWARD - GENERALLY

ARBITRATION - THE AWARD - APPEAL OR JUDICIAL REVIEW - PROCEDURE - APPLICATIONS FOR APPEAL OR JUDICIAL REVIEW

Appellant seeks permission to appeal against two arbitration awards made in respect of a dispute between the parties relating to the construction of eight silos - whether there was manifest error of law on the face of the award.

Appellant contends that the arbitrator determined the admissibility of an expert report for a limited purpose, without the appellant having had an opportunity to make submissions on the issue.

As a consequence of misunderstanding of the arbitrator's determination in the first award, the appellant was denied the opportunity of calling further evidence to establish its loss and damage.

Appellant submits that, on the face of the award, there was denial of natural justice.

Held:  That there was manifest error of law on the face of the award.

Respondent seeks permission to cross-appeal - whether manifest error of law on the face of the second award in the arbitrator's construction of the agreement between the parties in attempting to resolve the dispute - the interpretation of the agreement by the arbitrator was arguably correct - no manifest error of law established - application for permission to cross-appeal refused.

Commercial Arbitration and Industrial Referral Agreements Act 1986 (SA) s 35; Evidence Act 1929 (SA) s 45A, referred to.
Promenade Investments Pty Ltd v State of New South Wales (1991) 26 NSWLR 184, applied.
Leighton Contractors Pty Ltd v South Australian Superannuation Fund Investment Trust (1994) 63 SASR 444; Escobar v Spindaleri & Ors (1986) 7 NSWLR 51, considered.

VITERRA OPERATIONS LTD (TRADING AS ABB GRAIN STORAGE AND HANDLING) v EWING INTERNATIONAL LIMITED PARTNERSHIP
[2010] SASC 328

Civil:        Permission to Appeal

  1. SULAN J:             Pursuant to s 38(5) of the Commercial Arbitration and Industrial Referral Agreements Act 1986 (SA), the appellant, Ausbulk, and the respondent, Ewing each seek permission to appeal against the first interim award and the second interim award made in respect of a dispute between the parties relating to the construction of eight silos. The first interim award was made on 17 May 2010, and the second interim award was made on 21 September 2010.

    Principles on an application for permission to appeal

  2. Section 38 of the Commercial Arbitration and Industrial Referral Agreements Act 1986 provides:

    38 – Judicial review of awards

    (1)Without prejudice to the right of appeal conferred by subsection (2), the Court shall not have jurisdiction to set aside or remit an award on the ground of error of fact or law on the face of the award.

    (2)Subject to subsection (4), an appeal shall…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Viterra Operations Ltd (Trading as ABB Grain Storage and Han... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2010] SASC 328
Decision Date

CaseChat Overview and Summary

In the case of Viterra Operations Ltd (Trading as ABB Grain Storage and Handling) v Ewing International Limited Partnership, the court was tasked with determining whether an error of law was present on the face of an arbitration award. The dispute centred on the construction of eight silos, where the method of construction resulted in deformations, posing a significant risk of collapse. The arbitration award in question addressed various claims and counterclaims, including Ausbulk’s entitlement to damages and the admissibility of expert reports. Ausbulk argued that the arbitrator's failure to provide sufficient reasons and the limited admissibility of expert reports constituted a manifest error of law, while Ewing contested the admissibility of the reports on which Ausbulk relied.

The primary legal issues before the court involved the interpretation and construction of the arbitration award, specifically whether the arbitrator's decisions demonstrated a manifest error of law. Ausbulk contended that the arbitrator's limited consideration of the Currie and Brown Report, which was intended to value the work and interest, amounted to an error of law because Ausbulk was not given an opportunity to argue the admissibility of the report. Additionally, Ausbulk argued that the arbitrator's failure to provide sufficient reasons for the admissibility of the expert reports also constituted an error of law. Ewing, on the other hand, maintained that the arbitrator's decisions were not manifestly erroneous and that the admissibility of the reports was correctly limited.

The court determined that the arbitrator's decision to admit the Currie and Brown Report on a restricted basis, without hearing full argument from Ausbulk, demonstrated a manifest error of law. The court accepted Ausbulk's argument that it was denied the opportunity to argue the admissibility of the report, which was a significant point of contention. Furthermore, the court found that the arbitrator's failure to provide sufficient reasons for the limited admissibility of the expert reports also amounted to a manifest error of law. Consequently, the court concluded that Ausbulk should be granted permission to appeal the arbitration award.

In light of the court's findings, the case was remitted back to the original arbitrator for reconsideration, taking into account the full arguments from both parties regarding the admissibility of the expert reports and the reasons for the limited admissibility. This decision underscored the importance of providing adequate reasons and opportunities for argument in arbitration proceedings to ensure a fair and transparent process.

Orders

Orders of the court

Background

Background to the litigation

Ausbulk relies upon both the failure of the arbitrator to give sufficient reasons and his failure to give the parties an opportunity to argue what was the effect of his conclusions in respect of Ausbulk’s entitlement to damages as constituting an error of law. Further, it submits that the arbitrator’s failure to give sufficient reasons in respect of the admissibility, or limited admissibility, of expert reports sought to be tendered at the hearing amounts to an appealable error of law.Background The dispute involves the construction of eight silos which were to be used as temporary facilities for the storage of wheat. The issues the subject of this application relate to the construction of Bisalloy cone sections which were to form the bottom and lower sections of each silo. During construction, deformations appeared which, for reasons I do not need to elaborate, resulted in a significant risk that the structure would collapse. The relevant contract between Ausbulk and Ewing was entered into on 24 January 2006 (the first contract). Ewing is a company which had experience in the construction of petroleum tanks in New Zealand. It had no previous experience in the construction of grain silos in Australia. The method of construction involved assembling various parts and then constructing the silo, which involved resting the Bisalloy cones near the base of the silo. After construction had commenced, problems were observed, which included the deformations referred to earlier. The design engineer inspected the work and formed the view that there was a risk to life and recommended that the works be suspended. Pursuant to the first contract, a direction was given by the superintendent of works on or about 8 October 2006. A number of issues were raised by the superintendent, including a safety issue. Further, a direction was given requiring Ewing to comply with a safety standard referred to as AS4100. The parties were in dispute and work essentially halted. On 16 February 2007, an agreement was reached (the second agreement) by which Ausbulk agreed to pay $1.2 million in settlement of various claims. It was also agreed that Ausbulk, in consultation with Ewing, would appoint an independent consultant to value the work and interest as to any monies due and not paid to Ewing. That review was to be conducted as soon as possible. The independent consultant, Currie and Brown, who are quantity surveyors, prepared a report referred to as the Currie and Brown Report. A further dispute arose in respect of the second agreement. It is unnecessary to set out in detail the matters which were in dispute. On 14 June 2007, Ausbulk terminated the first contract on three bases, namely, (1) a failure by Ewing to comply with safety directions; (2) failure by Ewing to comply with a direction to build the cones to the standard of AS4100; and (3) a failure by Ewing to remobilise. Ewing regarded the termination as unlawful and filed a notice of dispute on 1 November 2007. It claimed an amount of approximately $6 million. Ausbulk counterclaimed in the amount of $19.8 million, and sought a return of the $1.2 million paid on 16 February. It claimed the cost of rectification of the Bisalloy cones in the amount of $631,684. It asserted that it had paid Ewing for the cones. Ewing denied that it had been proved that it had been paid the amount claimed. In the first interim award, the arbitrator concluded that both Ewing and Ausbulk were not entitled to damages for breach of contract. He concluded that Ausbulk’s termination of the contract was wrongful. He referred the question of whether Ausbulk is entitled to the return of the sum of $1.2 million claimed by it in its counterclaim and the cost of the replacement of cones, together with the question of any interest and costs, for further argument.

Evidence

Evidence before the court

Ausbulk further contends that the report is admissible pursuant to s 45A of the Evidence Act 1929 (SA), which provides:45A – Admission of business records in evidence(1) An apparently genuine document purporting to be a business record – (a)shall be admissible in evidence without further proof; and(b)shall be evidence of any fact stated in the record, or any fact that may be inferred from the record (whether the inference arises wholly from the matter contained in the record, or from that matter in conjunction with other evidence).(2) A document shall not be admitted in evidence under this section if the court is of the opinion – (a)that the person by whom, or at whose direction, the document was prepared can and should be called by the party tendering the document to give evidence of the matters contained in the document; or(b)that the evidentiary weight of the document is slight and is outweighed by the prejudice that might result to any of the parties from the admission of the document in evidence; or(b)that it would be otherwise contrary to the interests of justice to admit the document in evidence.(3) For the purpose of determining the evidentiary weight, if any, of a document admitted in evidence under this section, considering shall be given to the source from which the document is produced, the safeguards (if any) that have been taken to ensure its accuracy, and any other relevant matters.(4) In this section –business means business, occupation, trade or calling and includes the business of any governmental body or instrumentality;business record means – (a)any book of account or other document prepared or used in the ordinary course of a business for the purpose of recording any matter relating to the business; or(b)any reproduction of any such record by photograph, photostatic, lithographic or other like process. Ewing contends that there was never an application for the report to be tendered and, if there had been such an application, it would have failed. It is not necessary for me to finally determine that question, but I indicate that, in concluding that permission should be granted, I have not considered it necessary to consider that argument. I conclude that Ausbulk should be granted permission to appeal. On the face of the award, it is unclear to me exactly how the arbitrator determined to deal with the Currie and Brown Report on a limited basis. In my view, the argument by Ausbulk that it was denied the opportunity to argue the admissibility of the report has merit. I accept that, once permission to appeal has been granted, it will be necessary for me to consider the submissions of both parties to the arbitrator, and that may throw greater light on both parties’ contentions. In my view, the arbitrator’s decision to admit the report on a restricted basis, without hearing full argument, demonstrates a manifest error of law on the face of the award.Cross-appeal Ewing submits that there is a manifest error of law on the face of the award in the arbitrator’s construction of Clause 3 of the second agreement.

Decision

Reasons for decision

Ratio Decidendi

Legal principle established