Viterra Operations Ltd (T/A ABB Grain & Handling) v Ewing International Limited Partnership (No 2)

Link copied
Case Copied 28 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Appeals to a Single Judge)

VITERRA OPERATIONS LTD (T/A ABB GRAIN & HANDLING) v EWING INTERNATIONAL LIMITED PARTNERSHIP (No 2)

[2011] SASC 83

Judgment of The Honourable Justice Sulan

13 May 2011

ARBITRATION - THE AWARD - EFFECT AND PERFORMANCE - GENERALLY

ARBITRATION - THE AWARD - FORM AND CONSTRUCTION OF THE AWARD - GENERALLY

Appeal against two arbitration awards made in respect of a dispute between the parties relating to eight silos - appellant contends that Arbitrator made determination in First Interim Award as to entitlement to damages - whether findings in Second Interim Award made without advising parties and without inviting them to lead further evidence or make further submissions to clarify position - whether failure to afford procedural fairness.

Further issue as to admissibility of expert report - whether Arbitrator failed to inform parties of admission for limited purpose.

Whether appellant had sufficient notice of the issue of payment for cones - whether appellant should have applied to re-open.

Held:  Appeal allowed.  Matter referred to Arbitrator for further determination.

Fair Trading Act 1987 (SA), referred to.
Escobar v Spindaleri & Anor (1986) 7 NSWLR 51, applied.
Kioa v West (1995) 159 CLR 550; Morgan Belle Pty Ltd v API Services (Vic) Pty Ltd [2005] SASC 488; Decor Ceilings Pty Ltd v Cox Constructions Pty Ltd [2005] SASC 146, considered.

VITERRA OPERATIONS LTD (T/A ABB GRAIN & HANDLING) v EWING INTERNATIONAL LIMITED PARTNERSHIP (No 2)
[2011] SASC 83

Civil

  1. SULAN J:             This appeal is limited to certain findings and conclusions of an Arbitrator, the subject of two interim arbitrations awards dated 17 May 2010 and 21 September 2010 respectively.  The appellant, Viterra Operations Ltd (formerly Ausbulk Limited trading as ABB Grain Storage and Handling) (“Ausbulk”), sought permission to appeal against certain findings and conclusions of the Arbitrator.  Ewing International Limited Partnership (“Ewing”) opposed the application for permission to appeal.  On 22 November 2010, I granted permission.  I published my reasons dated 25 November 2010.[1] Ewing sought permission to appeal my decision to the Full Court.  On 11 March 2011, the Full Court refused permission to appeal.[2]

    [2]    [2011] SASFC 13.

    Background

  2. Ewing and Ausbulk entered into a contract on 24 January 2006 (the first agreement), in which Ewing agreed to construct eight grain storage silos at Pelican Point.  The subject of the appeal relates to the construction of what are known as Bisalloy cone sections, which were to form the bottom and lower sections of each silo.  During construction, deformations appeared.  The parties were in dispute. In late 2006 work ceased.  Each party alleged the other was in breach of the contract.  On 16 February 2007, an agreement was reached to resolve the dispute (the second agreement). 

    The second agreement

  3. The second agreement, in its preamble, acknowledged that Ausbulk and Ewing had entered into a contract, dated 13 December 2005, that certain disputes had arisen between the parties and, as a consequence, Ausbulk issued…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Viterra Operations Ltd (T/A ABB Grain & Handling) v Ewing In... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] SASC 83
Decision Date

CaseChat Overview and Summary

Viterra Operations Ltd (trading as ABB Grain & Handling) and Ewing International Limited Partnership were engaged in a dispute concerning eight silos. The matter was referred to arbitration, resulting in two interim awards. Viterra, the appellant, challenged both awards, arguing that the Arbitrator made a determination on the entitlement to damages in the First Interim Award and that the Second Interim Award was made without proper procedural fairness. Specifically, Viterra contended that the Arbitrator did not advise the parties and did not invite them to lead further evidence or make further submissions to clarify the position.

The legal issues before the court involved the effect and performance of the arbitration awards and the form and construction of the awards, particularly in relation to procedural fairness. The court had to determine whether the Arbitrator's failure to clarify his findings in the First Interim Award and his reliance on the Currie and Brown Report amounted to a failure to afford procedural fairness. This required an examination of the Arbitrator's process and whether the parties were given a fair opportunity to respond to the issues raised in the awards.

In considering these issues, the court found that the Arbitrator's findings in the First Interim Award were ambiguous and that the parties had differing interpretations of those findings. The court concluded that the Arbitrator should have called the parties to clarify his views on the meaning of his First Interim Award. This would have allowed Viterra to seek to reopen its case and call further evidence. The court also noted that the Arbitrator's reliance on the Currie and Brown Report without making clear its intended use denied Viterra the opportunity to make further submissions and to re-apply to reopen its case. The court found that these failings resulted in a denial of procedural fairness and mandated that the matters should be referred back to the Arbitrator for further determination.

The court did not dismiss the appeal outright but found that the issues of the First Interim Award's ambiguity and the procedural fairness in the Second Interim Award warranted further consideration by the Arbitrator. The final orders were that the appeal be allowed in part, and the matters concerning the First Interim Award's ambiguity and procedural fairness in the Second Interim Award be remitted to the Arbitrator for further determination.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

It is in accordance with the principles referred to that I have determined the issues in this appeal.Conclusion After the First Interim Award, there had been a dispute between the parties about the Arbitrator’s conclusions. It is clear, having read the submissions, that, on the one hand, Mr O’Sullivan took the view that the Arbitrator had determined Ausbulk’s entitlement to damages for the defective Bisalloy cones. No further issue arose about whether Ausbulk had paid Ewing and was entitled to repayment of the amount claimed. Further, insofar as it was necessary to rely on the Currie and Brown Report, Ausbulk relied upon it. Mr Jenner contended that the Arbitrator had not determined the question of whether Ausbulk had paid Ewing for the cones. Further, that Ausbulk could not rely on the Currie and Brown Report because it had not been tendered. I have read the relevant extracts from the submissions. It seems that on the relevant issues, and in their submissions in respect of the Second Interim Award, the parties were like ships passing in the night. Both parties were entitled to rely upon the position that they understood pertained after the First Interim Award. It was evident to the Arbitrator that there were differences in the interpretation of his findings. He acknowledged that the findings in the First Interim Award were ambiguous. I consider it is unfortunate that the Arbitrator failed to call the parties before him to clarify the position. He received voluminous written submissions. I consider he should have recalled the parties and made it clear to them what his views were as to the meaning of his First Interim Award. If that had been clear, then it would have been open to Ausbulk to seek to reopen its case and call further evidence. Further, if the Arbitrator’s conclusion in respect of the use he intended to make of the Currie and Brown Report had been clear, then the question of whether the author was to be called could have been resolved. I consider that the failure of the Arbitrator to make his position clear to the parties denied Ausbulk the opportunity to make further submissions and to re‑apply to re-open its case. In that regard, I consider that Ausbulk did not know the case against it. Counsel for Ausbulk genuinely believed the issue of payment of the cones had been determined. The Arbitrator acknowledged the ambiguity in his First Interim Report on that issue. Counsel should have been informed by the Arbitrator that he considered the issue of quantum had not been resolved. In my opinion, these were matters that should be referred to the Arbitrator for further determination. It is a question for the Arbitrator whether he permits Ausbulk to re-open its case and what evidence, if any, he will allow.Notice of contention Ewing seeks leave to prosecute an alternative contention. Ewing contends that the Arbitrator should not have had regard to the Currie and Brown Report for any purpose, as the report was not relevantly in evidence before him.

Ratio Decidendi

Legal Principle Established