FEDERAL COURT OF AUSTRALIA
Sino Iron Pty Ltd v Secretary of the Department of Infrastructure and Transport [2014] FCA 28
Citation: Sino Iron Pty Ltd v Secretary of the Department of Infrastructure and Transport [2013] FCA 28 Parties: SINO IRON PTY LTD (ACN 058 429 708), KOREAN STEEL PTY LTD (ACN 058 429 600), CITIC PACIFIC MINING MANAGEMENT PTY LTD (ACN 119 578 371) and CAPE PRESTON PORT COMPANY PTY LTD (ACN 147 842 153) v THE SECRETARY OF THE DEPARTMENT OF INFRASTRUCTURE AND TRANSPORT and MINERALOGY PTY LTD (ACN 010 582 680)
MINERALOGY PTY LTD (ACN 010 582 680) v SINO IRON PTY LTD, KOREAN STEEL PTY LTD (ACN 058 429 600), CITIC PACIFIC MINING MANAGEMENT PTY LTD (ACN 119 578 371) and CAPE PRESTON PORT COMPANY PTY LTD (ACN 147 842 153)
File numbers: WAD 234 of 2013
WAD 293 of 2013Judge: RARES J Date of judgment: 5 February 2014 Catchwords: JUDICIAL REVIEW – designation of port operator for security regulated port under s 14 of Maritime Transport and Offshore Facilities Act 2003 (Cth) – relevant and irrelevant considerations – whether consent, views or co-operation of port facility operator or other affected users of port a relevant consideration or necessary precondition for designation of port operator – whether non-cooperation of port facility operator affected ability of designated person to function as port operator – meaning of “ability” under s 14(2)(a) Legislation: Acts Interpretation Act 1901 (Cth) s 15AB(1)
Administrative Decisions (Judicial Review) Act 1977 (Cth) s 5(1)
International Convention for the Safety of Life at Sea
International Ship and Port Facility Security (ISPS) Code
Iron Ore Processing (Mineralogy Pty Ltd) Agreement Act 2002 (WA) Schedule 1, recital (c), cll 6(2)(m), 6(5), 21
Maritime Transport and Offshore Facilities Act 2003 (Cth) ss 3(1), 8, 9(1), 12, 13, 14(1), 14(2)(c), 21, 22, 25(1), 27, 27(1), 29, 35(3), 42, 43(1), 45(1), 47(1), 48, 50, 51(1) and (3), 53, 55, 57, 102(1), 103(2) and (3), 189, 197, 202
Maritime Transport and Offshore Facilities Security Regulations 2003 (Cth) Pt 3, Pt 6, regs 1.03, 3.15, 3.20, 3.30, 3.35, 3.35(1), 3.40, 3.45, 3.50, 3.55(a)-(c), 3.60, 3.100, 6.20, 6.25(2), 6.30, 6.33, 6.35, 6.40, 6.65(2), 6.70, 6.70(1)
Shipping and Pilotage Act 1967 (WA) ss 4, 5(1)(a)-(c), 7, 10(1)Cases cited: Ainsworth v Criminal Justice Commission (1992) 175 CLR 564 referred to
Commissioner of Taxation v Consolidated Media Holdings Ltd (2012) 293 ALR 257 applied
Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24 applied
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1966) 185 CLR 259 applied
S10/2011 v Minister for Immigration and Citizenship (2012) 246 CLR 636 applied
Telstra Corporation Ltd v Australian Competition and Consumer Commission (2008) 176 FCR 153 applied
Telstra Corporation Ltd v Australian Competition Tribunal (2009) 175 FCR 201 appliedDate of hearing: 11 and 12 September 2013 Place: Sydney Division: GENERAL DIVISION Category: Catchwords Number of paragraphs: 95 Counsel for the Applicant: Mr I Jackman SC with Mr SC Wong Solicitor for the Applicant: Allens
Keep reading for free
Create a free CaseChat account to read Visscher v Teekay Shipping (Australia) Pty Ltd (No 5) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] FCA 28
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the delegate took into account all relevant considerations and disregarded irrelevant considerations when designating Mineralogy as the port operator. Specifically, the Citic parties argued that the delegate failed to consider Mineralogy's ability to monitor and control access to restricted zones, control vessel movement, and manage port infrastructure over the whole port. They also contended that the delegate did not consider Mineralogy's ability to act as a liaison for communication between the Department and other maritime industry participants, including the port facility operator. Furthermore, the Citic parties submitted that the delegate did not take into account their views as persons responsible for the management of the port.
The Federal Court found that the delegate had considered the relevant matters and had not erred in his decision-making process. The Court held that the delegate had properly assessed Mineralogy's draft Maritime Security Plan and determined that it demonstrated Mineralogy's understanding of the security responsibilities required of a port operator and its capability to undertake those responsibilities. The Court also found that the delegate had considered the physical and operational features of the port and had given due consideration to the agreements and proposals discussed at the Cape Preston Marine Safety Meetings. The Court rejected the Citic parties' argument that the delegate failed to consider Mineralogy's ability to undertake the general role of port operator, holding that the delegate's reasons demonstrated that he had properly considered Mineralogy's ability to discharge its statutory functions.
The Court further found that the delegate had not erred in failing to consider the breakdown in relations between Mineralogy and Citic Pacific, as this was not a current fact that bore on Mineralogy's ability to undertake the functions of a port operator. The Court held that the delegate's conclusion that the draft plan's treatment of the proposals was consistent with what had been discussed and agreed by all participants of the Cape Preston Marine Safety Meetings throughout 2012 was not illogical or unsupported by the evidence. The Court also found that the delegate had not failed to take the Citic parties' views into account, as they were not persons responsible for the management of the port within the meaning of s 14(2)(c) of the Act.
The Court dismissed the proceedings and ordered the parties to confer as to any order for costs, with written submissions and proposed draft orders for costs to be filed and served within specified timeframes. The Court noted that entry of orders was dealt with in Rule 39.32 of the Federal Court Rules 2011.
Orders
Orders of the court
1. The proceedings be dismissed.
2. The parties confer as to any order for costs and, in the event that they do not agree, each party file and serve written submissions, limited to five pages, and its proposed draft orders for costs on or before 12 February 2014 and any written submissions in reply limited to three pages on or before 19 February 2014.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
1. The proceedings be dismissed.
2. The parties confer as to any order for costs and, in the event that they do not agree, each party file and serve written submissions, limited to five pages, and its proposed draft orders for costs on or before 12 February 2014 and any written submissions in reply, limited to three pages, on or before 19 February 2014.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Relevant and irrelevant considerations: The Citic parties relied on statements in the Explanatory Memorandum for the Bill that became the Act as aids to construction of s 14. That had stated in relation to cl 14 of the Bill:“This clause provides that the Secretary may publish a notice in the Gazette designating a person as the port operator for the security regulated port. The port operator must be able to demonstrate that it has responsibility for the relevant waterside and landside areas within a proposed or an established security regulated port, for example, control of vessel movement and management of port infrastructure.” (emphasis supplied by the Citic parties) The Citic parties contended that the delegate had considered only the security responsibilities of a port operator as revealed, so it argued in [9] of his reasons and he did not consider the ability of Mineralogy to undertake the general role of port operator. They submitted that the delegate did not “properly” consider Mineralogy’s ability to discharge its statutory functions other than those under Div 3.2 of the Regulations to which he referred at [9]. The Citic parties argued that the delegate did not consider what regs 6.33, 6.65 and 6.70 required, namely, Mineralogy’s ability to undertake the functions of monitoring and controlling access to any land-side or water-side restricted zones, controlling vessel movement and managing port infrastructure over the whole port. They also argued that he did not consider Mineralogy’s ability to undertake the function of being the liaison for communication between the Department and other maritime industry participants, including the port facility operator. The Citic parties contended that due consideration of those matters was necessary because of the legislative purpose and scheme designed to prevent acts of terrorism that Australia had international obligations to perform. They said that the Explanatory Memorandum expressly singled out that a port operator had to be able to demonstrate its ability to discharge the functions of monitoring and controlling the port. In addition, they submitted that the draft plan did not indicate that CPPC agreed with what Mineralogy was proposing and, indeed, the delegate was aware from the recent email exchanges that CPPC had yet to do so. The Citic parties also argued that the delegate could not have taken into account Mineralogy’s ability to undertake the role of port operator because he did not address how it could perform that role given the recent breakdown in relations between it and them. They argued that this breakdown was current information available to the decision-maker that bore on the need for maritime industry participants to co-operate and referred to what Mason J had said in Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24 at 44-45. The Citic parties also contended that s 14(2)(b) of the Act required the delegate to take into account the physical and operational features of the port and that Mineralogy’s tenements were not co-extensive with the area of the port. They argued that the delegate only gave cursory consideration to the physical features of the port area in [10] and then cast that matter aside. They submitted that, in [9.2] of his reasons, the delegate had referred to Mineralogy managing port operations while Citic would undertake shipping operations and be the port facility operator. The Citic parties argued that the delegate’s conclusion that the draft plan’s treatment of those proposals was consistent with “what had been discussed and agreed by all participants of the Cape Preston Marine Safety Meetings throughout 2012” was illogical and unsupported by the evidence. That was because, they said, the delegate knew from the recent email exchanges that CPPC had yet to agree with the measures proposed at the last meeting on 22 October 2012, there was no agreement as to the exact roles to be undertaken by each party and tripartite discussions to clear those matters up were continuing. Finally, the Citic parties argued that the delegate had to, but did not, take their views into account pursuant to s 14(2)(c) as persons responsible for the management of the port.The Secretary’s submissions