QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Usher v Innovation Pools Pty Ltd [2024] QCAT 305
PARTIES:
ROBBIE JON USHER (applicant)
ELIZABETH KAY USHER
(applicant)
v
INNOVATION POOLS PTY LTD (respondent)
APPLICATION NO/S:
BDL308-22
MATTER TYPE:
Building matters
DELIVERED ON:
1 August 2024
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
A/Member D Brown
ORDERS:
1. Innovation Pools Pty Ltd is to pay Robbie Usher and Elizabeth Usher $30,819.17 within 30 days, which consists of:
(a) Damages of $30,452.17 consisting of:
(i) $23,760.00 to replace the retaining wall and boundary fence;
(ii) $4,510.44 for new approvals and certification;
(iii) $1,430.00 for the engineering report;
(iv) $600.00 for temporary fencing; and
(v) $151.73 for replacement pumps.
(b) Costs in the amount of $367.00 for the filing fee.
2. The counter application is dismissed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – where contract for swimming pool – where heavy rain event – whether work is defective – whether the owner was entitled to recover for damage caused by the building contractor for defective work – where claim for solatium sought – where restitution in the return of deposit sought – where interest claimed on damages.
Queensland Building and Construction Commission Act 1991 (Qld)
Queensland Building and Construction Commission Regulations 2018 (Qld)
Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Baltic Shipping Company v Dillon (1993) 176 CLR 344
Bellgrove v Eldridge [1954] HCA 36
Edwards v Sovereign Homes (QLD) Pty Ltd [2020] QCATA 146Mann v Paterson Construction PtyLtd [2019] HCA 32
Miller v Lida Build Pty Ltd [2015] QCATA 137
Stewart v Scott trading as Fantasy Pools Brisbane [2020] QCAT 110
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 253 ALR 1
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act2009 (Qld)
REASONS FOR DECISION
Background
The applicants, Mr Robbie Usher and Mrs Elizabeth Usher, lodged an application for a domestic building dispute on 18 October 2022 seeking the respondent, Innovation Pools Pty Ltd, pay them $66,045.25 being damages in the amount of $63,191.25, restitution in the amount of $2,487.00 and costs of the filing fee in the amount of $367.00.
The applicants entered into a contract with the respondent company for the construction of a concrete pool in their Rochedale South property on 4 September 2021. The work commenced on 1 October 2021. The contract amount was $50,470.00 The applicants have made payments of $16,071.71, which included an initial deposit of $2,487.00.
Between 1 October 2021 and 5 October 2021 the excavation of the pool was undertaken. Between 5 October and 11 October work was undertaken on the excavation site, including plumbing and commencing installation of the steel reinforcement. On 11 October 2021 in anticipation of rainfall the respondent covered the area with a black…
Continue reading Usher v Innovation Pools Pty Ltd
Sign in free to access the full text
- AGLC
- Usher v Innovation Pools Pty Ltd [2024] QCAT 305
- Case
- [2024] QCAT 305
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the work performed by the defendants was indeed defective, and if so, whether the plaintiffs were entitled to recover damages for the resulting damage to their property. The court also needed to assess the claim for solatium, the restitution of the deposit, and the interest on the damages claimed by the plaintiffs. The defendants denied the allegations of defective work and argued that they had performed the contract to the required standard.
The court found that the defendants had indeed performed defective work, which resulted in damage to the plaintiffs' property during a heavy rain event. The court awarded the plaintiffs damages in the amount of $30,452.17 for the cost of repairs to the retaining wall and boundary fence, new approvals and certification, an engineering report, temporary fencing, and replacement pumps. The court also awarded costs of $367.00 for the filing fee, bringing the total amount to $30,819.17. The plaintiffs' claim for solatium and the return of the deposit was dismissed, as was their claim for interest on the damages. The defendants' counter application was also dismissed.
Orders
Orders of the court
1. Innovation Pools Pty Ltd is to pay Robbie Usher and Elizabeth Usher $30,819.17 within 30 days, which consists of:
(a) Damages of $30,452.17 consisting of:
(i) $23,760.00 to replace the retaining wall and boundary fence;
(ii) $4,510.44 for new approvals and certification;
(iii) $1,430.00 for the engineering report;
(iv) $600.00 for temporary fencing; and
(v) $151.73 for replacement pumps.
(b) Costs in the amount of $367.00 for the filing fee.
2. The counter application is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.