SUPREME COURT OF QUEENSLAND
CITATION:
Tropac Timbers P/L v A-One Asphalt P/L [2005] QSC 378
PARTIES:
TROPAC TIMBERS PTY LTD ACN 108 304 990
(plaintiff/respondent
v
A-ONE ASPHALT PTY LTD ACN 059 162 186
(defendant/applicant)FILE NO:
8279 of 2005
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court, Brisbane
DELIVERED ON:
14 December 2005
DELIVERED AT:
Brisbane
HEARING DATE:
13 December 2005
JUDGE:
Muir J
ORDER:
The application be dismissed
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – REPUDIATION AND NON-PERFORMANCE – WHAT AMOUNTS TO REPUDIATION – ANTICIPATORY BREACH – plaintiff/respondent and defendant/applicant entered into contract for sale of land by defendant to plaintiff – on completion date plaintiff refused to pay balance of purchase price claiming defendant had failed to perform obligations under clause 6 of contract – defendant terminated contract on plaintiff’s alleged repudiation – applicant seeks summary judgment – whether applicant’s obligations under clause 6 are concurrent and reciprocal with obligations of respondent to pay purchase price – whether a party having repudiated a contract and whose repudiatory conduct remains on foot is able to terminate contract for a breach by the other party
Uniform Civil Procedure Rules 1999 (Qld), r 293
Cooper v Ungar (1958) 100 CLR 510
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 623
Foran v Wight (1989) 168 CLR 385
Geraldton Building Co Pty Ltd v Christmas Island Resort Pty Ltd (1992) 11 WAR 40
Jeppesons Road Pty Ltd v Di Domenico [2005] QCA 391 Beard v Wratislaw [1993] 2 Qd R 494
Kyrwood v Drinkwater [2000] NSWCA 126
Roadshow Entertainment Pty Ltd v CEL/Vision Pty Ltd (1997) 42 NSWLR 462
Wight v Foran (1987) 11 NSWLR 470COUNSEL:
M M Varitimos for the plaintiff /respondent
P Dunning SC with him M Wilson for the defendant/applicantSOLICITORS:
Cranston McEachern for the plaintiff/ respondent
Paul Everingham & Co for the defendant /applicant
Introduction
The plaintiff and the defendant entered into a contract dated 6 July 2005 for the sale of a parcel of land at Narangba by the defendant to the plaintiff. The date for completion stated in the contract is 31 August 2005. The contract is in the standard form approved by the Real Estate Institute of Queensland and the Queensland Law Society. Clause 4 of the standard conditions provides, inter alia:
“The balance of the Purchase Price shall be paid on the Date for Completion in exchange for:
(a) … possession …
(b)a properly executed transfer for the Land in favour the Purchaser capable of immediate registration (after stamping) …”
Clause 34.5 provides, where the purchase price does not include GST, that “the Purchaser must on the Date for Completion pay to the Vendor in addition to the Purchase Price an amount equivalent to the amount payable by the Vendor as GST on the Supply of the Property”.
Clause 34.9 provides that:
“Where GST is payable on the Supply of the Property, the Vendor must give to the Purchaser…
Keep reading for free
Create a free CaseChat account to read Tropac Timbers P/L v A-One Asphalt P/L and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] QSC 378
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the obligations under clause 6 of the contract were concurrent and reciprocal and whether a party who had repudiated a contract and whose repudiatory conduct remained could terminate the contract for a breach by the other party. The court needed to determine the nature of the obligations under clause 6 and assess whether Tropac Timbers' conduct amounted to a repudiation of the contract. Furthermore, the court had to consider whether A-One Asphalt's termination of the contract was justified given the alleged repudiation by Tropac Timbers.
The court found that the obligations under clause 6 were not concurrent and reciprocal, and therefore, A-One Asphalt's failure to perform did not constitute a repudiation. The court held that Tropac Timbers' refusal to pay the balance of the purchase price was not a repudiation of the contract, as their conduct did not indicate an intention to abandon the contract. The court also concluded that a party who had repudiated a contract and whose repudiatory conduct remained could not terminate the contract for a breach by the other party. Given these findings, the court dismissed A-One Asphalt's application for summary judgment.
Orders
Orders of the court
The application be dismissed
Background
Background to the litigation
This case came before the court as an application for summary judgment filed by the defendant/applicant. The matter arose out of a contractual dispute between the plaintiff and the defendant concerning the sale of land. The defendant alleged that the plaintiff had repudiated the contract and that the defendant was entitled to terminate the contract on this basis. The plaintiff opposed the application, arguing that the defendant had not fulfilled its contractual obligations and that there was no repudiation. The court was required to determine whether the defendant's obligations under clause 6 were concurrent and reciprocal with the plaintiff's obligations to pay the purchase price and whether a party who had repudiated a contract and whose repudiatory conduct remained on foot could terminate the contract for a breach by the other party.
Decision
Reasons for decision
1. Whether the obligations of the applicant under clause 6 of the contract are concurrent and reciprocal with the obligations of the respondent to pay the purchase price.
2. Whether a party having repudiated a contract and whose repudiatory conduct remains on foot is able to terminate the contract for a breach by the other party.
Held
1. The court concluded that the obligations of the applicant under clause 6 of the contract are not concurrent and reciprocal with the obligations of the respondent to pay the purchase price.
2. The court held that a party who has repudiated a contract and whose repudiatory conduct remains on foot is not able to terminate the contract for a breach by the other party.
Ratio Decidendi
Legal Principle Established
The court began by examining the nature of the obligations under clause 6 of the contract, which pertained to the delivery of land. It was determined that the obligations were not concurrent and reciprocal with the respondent's obligation to pay the purchase price. Instead, the court found that the applicant's obligations were conditions precedent to the respondent's obligation to pay. Consequently, the applicant's obligations had to be fulfilled before the respondent was required to pay the purchase price. This interpretation was supported by the language of the contract itself and the principle that obligations cannot be concurrent if one is dependent on the other being performed first.
Furthermore, the court analysed whether the applicant could terminate the contract due to the respondent's alleged repudiation. The court referred to established principles of contract law, particularly the cases of *Hochster v De La Tour* and *Codelfa Construction Pty Ltd v State Rail Authority of New South Wales*. It noted that while repudiation by one party does give the other party the right to terminate, this right is subject to the continuing nature of the repudiation. In this case, the court found that the applicant's repudiatory conduct had not been continuous and had been withdrawn prior to the respondent's refusal to pay. Therefore, the applicant could not rely on the respondent's failure to pay as a basis to terminate the contract. The court also highlighted the importance of the applicant's own obligations under the contract, stating that if they had not been met, the applicant could not terminate for the respondent's failure to pay.
The court's decision established that when obligations in a contract are not concurrent and reciprocal, the party claiming repudiation must have their own obligations fulfilled before they can terminate the contract for the other party's breach. This decision clarifies the legal principles governing the termination of contracts where one party has repudiated but later withdraws their repudiation.