SUPREME COURT OF QUEENSLAND
CITATION:
JYP Jiang Pty Ltd v CAV Gasworks Pty Ltd [2025] QSC 134
PARTIES:
JYP JIANG PTY LTD (ACN 618 883 122) AS TRUSTEE FOR THE JYP JIANG FAMILY TRUST
(Plaintiff)
v
CAV GASWORKS PTY LTD (ACN 603 728 338) AS TRUSTEE FOR THE CAV GASWORKS TRUST
(Defendant)
And
YIPING JIANG(Defendant added by counterclaim)
FILE NO/S:
BS 10017 of 2024
DIVISION:
Trial Division
PROCEEDING:
Trial
DELIVERED ON:
12 June 2025
DELIVERED AT:
Brisbane
HEARING DATE:
1 May 2025
JUDGE:
Bowskill CJ
ORDERS:
1. Judgment for the plaintiff on its claim in accordance with paragraph [80] of the reasons published today.
2. The counterclaim is dismissed.
3. The parties are directed to provide an appropriate form of order consistent with the reasons published today, including the calculation of interest.
4. The court will hear the parties as to costs.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – REPUDIATION AND NON-PERFORMANCE – REPUDIATION – GENERAL PRINCIPLES – where the defendant is the developer of a multi-storey commercial and residential building – where the plaintiff entered into a contract with the defendant, prior to the construction of the building, to purchase two sub-penthouses “off the plan” – where by clause 8 of the contract there was a sunset date by which either party could end the contract if the steps necessary to create separate title for the purchased lots had not happened – where clause 8 of the contract obliged the defendant to give notice to the plaintiff once it became aware those things had been done, but also provided that it “need not” give the notice until satisfied all of the defendant’s obligations under the contract could be met within 14 days of the notice – where clause 8 provided a right to terminate where the defendant “cannot” give the notice by the specified date – where the defendant was aware the separate title requirements had been met prior to the sunset date, but did not give the requisite notice to the plaintiff – where the defendant subsequently purported to terminate the contract, on the basis that a certificate of occupancy for the purchased lots was not yet available and so it could not complete the contract because it could not give the plaintiff vacant possession – where the defendant subsequently entered into, and completed, contracts to sell each of the lots to third parties, for more than double the contract price – whether on the proper construction of clause 8 of the contract the defendant was entitled to terminate the contract – whether the defendant was entitled to rely on another clause of the contract to justify its termination – whether the plaintiff breached the contract by lodging a caveat over one of the lots the subject of the contract – whether the defendant was entitled to terminate the contract for the plaintiff’s breach and retain the deposit
DAMAGES – ASSESSMENT OF DAMAGES IN ACTIONS FOR BREACH OF…
Keep reading for free
Create a free CaseChat account to read JYP Jiang Pty Ltd v CAV Gasworks Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] QSC 134
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the defendant was entitled to terminate the contract under clause 8 and whether it could rely on another clause to justify the termination. The court also had to consider whether the plaintiff had breached the contract by lodging a caveat over one of the lots and whether the defendant could terminate the contract and retain the deposit for the plaintiff’s breach. Furthermore, the court had to assess the appropriate measure of damages for the plaintiff, considering the expert valuer's evidence on the market value of the lots.
The court found that the defendant was not entitled to terminate the contract under clause 8, as it had failed to provide the required notice within the specified time. The court also ruled that the defendant could not rely on another clause to justify the termination. Regarding the plaintiff’s breach, the court found that lodging a caveat did not constitute a breach severe enough to warrant termination and retention of the deposit. In terms of damages, the court accepted the expert valuer's evidence and calculated the difference between the contract price and the market value of the lots as at the date the contract would have completed but for the defendant’s repudiation.
The court ordered judgment for the plaintiff on its claim and dismissed the defendant’s counterclaim. The parties were directed to provide an appropriate form of order consistent with the reasons published, including the calculation of interest. The court scheduled a hearing to determine the costs.
Orders
Orders of the court
1. Judgment for the plaintiff on its claim in accordance with paragraph [80] of the reasons published today.
2. The counterclaim is dismissed.
3. The parties are directed to provide an appropriate form of order consistent with the reasons published today, including the calculation of interest.
4. The court will hear the parties as to costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.