QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Todd v Lennon-Muscat & Anor [2025] QCATA 93
PARTIES:
MARK JAMES TODD (applicant/appellant)
v
PAUL LENNON-MUSCAT (respondent)
CHRISTOPHER HICKMAN (respondent)
APPLICATION NO/S:
APL309-23
ORIGINATING APPLICATION NO/S:
BDL265-21MATTER TYPE:
Appeals
DELIVERED ON:
21 October 2025
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Brown
ORDERS:
1. Leave to appeal is granted;
2. The appeal is allowed;
3. The decision of the Tribunal dated 28 August 2023 is varied as follows:
Order 1 is set aside and in lieu thereof it is ordered that Paul Lennon-Muscat must pay Mark James Todd the sum of $39,761.77 within 14 days of the date of this decision.
CATCHWORDS:
APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – ERROR OF LAW – WHAT IS – GENERALLY – question of law – whether tribunal erred in assessing appellant’s entitlement to damages – original claim against second respondent dismissed on basis of no contractual relationship and no duty of care owed – where tribunal found second respondent had not received payment directly from appellant and whether this precluded order for repayment in circumstances where second respondent not licenced to undertake building work – errors of fact – claim for rectification work confined to cost of removal of defective work – error in interpretation of s 42 of Queensland Building and Construction Commission Act 1991 (Qld) – appeal on question of mixed law and fact – rehearing
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – GENERAL – appellant paid first respondent to perform building work – appellant subsequently became aware respondents were unlicenced to perform building work under Queensland Building and Construction Commission Act 1991 (Qld) – first respondent refused to repay deposit – appellant claimed against each respondent for repayment of monies paid, rectification and costs – claim against first respondent allowed – claim against second respondent dismissed
Civil Liability Act 2003 (Qld), s 9, s 11
Queensland Building and Construction Commission Act1991 (Qld), s 42
Queensland Building and Construction Commission Regulation 2018 (Qld), s 54Queensland Civil and Administrative Tribunal Act2009 (Qld), s 142(1), s 146, s 147
Cachia v Grech [2009] NSWCA 232
Ericson v Queensland Building Services Authority [2013] QCA 391
Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388
Greer & Anor v Mt Cotton Constructions Pty Ltd [2018] QCATA 196
Harrison and Anor v Meehan [2016] QCATA 197
Harrison v Meehan [2017] QCA 315
James v Tottman (No.2) [2022] QCATA 10
Marshall v Marshall [1999] 1 Qd R 173
McIver Bulk Liquid Haulage Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577
M.Todd v Muscat & Hasan Construction Pty Ltd & Ors [2023] QCAT 332QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal…
Continue reading Todd v Lennon-Muscat
Sign in free to access the full text
- AGLC
- Todd v Lennon-Muscat [2025] QCATA 93
- Case
- [2025] QCATA 93
- Decision Date
CaseChat Overview and Summary
The legal issues the court needed to decide included whether the tribunal erred in assessing the appellant’s entitlement to damages, and if so, whether this constituted an error of law or mixed law and fact warranting a rehearing. The court also needed to determine whether the tribunal's interpretation of section 42 of the Queensland Building and Construction Commission Act 1991 (Qld) was correct, and if the claim for rectification work was properly confined to the cost of removal of defective work.
The court found that the tribunal erred in its interpretation of section 42, which led to an incorrect assessment of the appellant’s entitlement to damages. The error in interpretation was deemed to be one of law, as it involved a misinterpretation of statutory provisions. The court also found that the claim for rectification work should not have been confined to the cost of removal of defective work, and that this was another error of law. Consequently, the appeal was allowed, and the decision of QCAT was varied to order the second respondent to pay the appellant the sum of $39,761.77 within 14 days of the date of the decision.
The final orders included granting leave to appeal, allowing the appeal, and varying the QCAT decision to require the second respondent to pay the appellant within a specified timeframe.
Orders
Orders of the court
1. Leave to appeal is granted;
2. The appeal is allowed;
3. The decision of the Tribunal dated 28 August 2023 is varied as follows:
Order 1 is set aside and in lieu thereof it is ordered that Paul Lennon-Muscat must pay Mark James Todd the sum of $39,761.77 within 14 days of the date of this decision.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.