SUPREME COURT OF QUEENSLAND
CITATION:
Thistle Investment Pty Ltd v MXL Investment Pty Ltd [2024] QSC 247
PARTIES:
THISTLE INVESTMENT PTY LTD ACN 056 657 268 AS TRUSTEE UNDER INSTRUMENT 711113027
(applicant)
v
MXL INVESTMENT PTY LTD ACN 634 258 610(respondent)
FILE NO:
BS 3531/24
DIVISION:
Trial
PROCEEDING:
Trial (commenced by originating application)
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
21 October 2024
DELIVERED AT:
Brisbane
HEARING DATE:
20 September 2024
JUDGE:
Freeburn J
ORDER:
1. The application filed on 20 March 2024 is refused.
2. I will hear the parties on costs.
CATCHWORDS:
REAL PROPERTY – TORRENS TITLE – LEASES – GENERALLY – where the defendant was assigned a lease in a hotel – where the hotel was in poor condition before the lease was assigned – where, during the lease, the plaintiff lessor complained that the hotel was in poor condition – where subsequently, the plaintiff sought to terminate the lease – where the plaintiff was first required to serve a notice to remedy breach that complied with s 124 Property Law Act 1974 (Qld) – where the plaintiff served a notice with defects, one being a report attached as an annexure identifying all remedial work to be done at termination, not to remedy a breach – where the notice stated the defendant was to undertake all remedial works, including those identified in the report – whether the plaintiff validly terminated the lease – whether there is sufficient evidence to establish that the defendant breached the lease
Property Law Act 1974 (Qld), s 124
Blewett v Blewett [1936] 2 All ER 188, explained
Elsafty Enterprises Pty Ltd v Mermaids Café & Bar Pty Ltd[2007] QSC 394, cited
Guillemard v Silverthorne (1908) LT 584, explained
Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service [2010] NSWCA 268, distinguished
Re Automotive and General Industries Ltd v Bryson Industries (Vic) Pty Ltd (2012) V ConvR 54-801, explainedSylvester v Ostrowska [1959] 1 WLR 1060, explained
COUNSEL:
SW Trewavas for the applicant
J Trost for the respondent
SOLICITORS:
OMB Solicitors for the applicant
Stephens & Tozer for the respondent
Background
Just a stone’s throw from the court building, in the Brisbane CBD, just near the Turbot Street overpass, is a building known as “The Explorers Inn”. It is a four storey red brick building built in 1916.[1] The hotel provides what is described as ‘affordable accommodation’. The building is owned by the applicant company, Thistle Investment Pty Ltd.
[1]The building comprises a basement, ground floor and three upper levels.
In April 2015 Thistle leased the building to Brisbane Holidays Pty Ltd. About 18 months later Brisbane Holidays assigned its interest as lessee to Feng Group Investments Pty Ltd. Then, in November 2022, Feng Group assigned its interest as lessee to the respondent, MXL Investment Pty Ltd. And so MXL became the lessee in November 2022, although it may be that the physical transfer of the operations of the hotel occurred…
Keep reading for free
Create a free CaseChat account to read Thistle Investment Pty Ltd v MXL Investment Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QSC 247
- Decision Date
CaseChat Overview and Summary
The court considered the notice served by Thistle and found it to be defective. The notice required MXL to undertake remedial work that was not necessary to remedy a breach, but rather to address the general condition of the hotel at termination. The court noted that the notice expressly required MXL to carry out work specified in both Annexure A and in a PEP report, even though the PEP report included 'make good' work not required by the lease and could not be achieved within the time permitted in the notice. The court held that the content of the PEP report in so far as it sought to demonstrate MXL’s obligation to 'make good' had no relevance to Thistle’s claim that MXL was in breach of its repair or other obligations under the lease as at the date the notice was served. The court further held that the PEP report included tasks that were substantial and would take much longer than the 28 days specified in the notice, which rendered the notice invalid. The court concluded that the Form 7 did not validly terminate the lease.
The application filed by Thistle on 20 March 2024 was refused. The court will hear the parties on costs.
Orders
Orders of the court
1. The application filed on 20 March 2024 is refused.
2. I will hear the parties on costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
That point can be demonstrated by the very first item listed in the schedule of ‘make good’ works: “Removal of tenants, fixtures and fittings: Remove fixtures and fittings complete (Cabinetry, blinds, fixtures and fittings) Make good to all disturbed surfaces.” That item of the PEP report relied on clause 17.2 of the lease. However, that provision is as follows:The Tenant may and, if required by the Landlord, must remove from the Premises or the Building any property of the Tenant, including the Tenant’s Property,[30] at the expiration or sooner termination of this Lease. The Tenant must repair any damage caused to the Premises by the Tenant removing the Tenant’s Property. [emphasis added][30]The expression “Tenant’s Property” is defined as the fixtures, fittings, furnishings and equipment (if any) at any time installed in the Premises as specified in item 18 of Schedule 1. That item refers the reader to Schedule 4 which contains a lengthy list of furniture, fittings and equipment. And so, MXL’s ‘make good’ obligation in clause 17.2 is only engaged if there is a termination of the lease and, on that termination of the lease, MXL chooses to remove its property or Thistle requires the removal of MXL’s property. On any view the lease had not been terminated as at 6 December 2023 when the Form 7 was served on MXL. There was therefore no factual basis for the engagement of clause 17.2 as at 6 December 2023. Therefore, the content of the PEP report in so far as it sought to demonstrate MXL’s obligation to ‘make good’ had no relevance to Thistle’s claim that, as at 6 December 2023, MXL was in breach of its repair or other obligations under the lease. It is necessary to look at the PEP report in a little more detail. Some samples of the items in the PEP report’s schedule, entitled “Schedule of Make Good Works”, are as follows:[31][31]The examples in the schedule have been simplified for present purposes. There are literally hundreds of items like those, although many do actually refer to items requiring repair rather than items that are ‘make good’ items. That said, the ‘make good’ and repair tasks listed in the PEP report were substantial undertakings. The PEP report estimated that the cost of the work would be $402,583 and would involve a 13 week program.[32] That contrasts with the maximum period of 28 days remedying the breaches as specified in the text of the Form 7.[33] [32]PEP report, pg 7. [33]The covering letter from Thistle’s solicitors specified 4 January 2024 as the final day for the remedial work – which is 29 days after 6 December 2023. The result is that the Form 7 expressly required MXL to carry out the remedial work specified in both Annexure A and in the PEP report in circumstances where the PEP report comprehended ‘make good’ work not required by the lease and not able to be achieved in the time permitted in the Form 7. Thistle sought to save the Form 7:[34]The PEP Solutions report of 16 June 2023 was merely a document referred to in the Form 7, to further particularise the works required by the Respondent to remedy the breaches identified in Annexure A to Form 7. Insofar as the PEP Solutions report of 16 June 2023 went beyond the requirements contained in Annexure A, it was irrelevant. [34]Thistle’s further submissions, [2].