SUPREME COURT OF QUEENSLAND
CITATION: Thiess Services P/L v Mirvac Queensland P/L [2006] QCA 50 PARTIES: THIESS SERVICES PTY LTD ACN 010 725 247
(applicant/respondent/appellant)
v
MIRVAC QUEENSLAND PTY LIMITED
ACN 060 411 207
(respondent/applicant/respondent)FILE NO/S: Appeal No 10901 of 2005 Appeal No 10902 of 2005 SC No 4205 of 2005 SC No 4276 of 2005 DIVISION: Court of Appeal PROCEEDING: General Civil Appeal ORIGINATING
COURT:Supreme Court at Brisbane DELIVERED ON: 3 March 2006 DELIVERED AT: Brisbane HEARING DATE: 15 February 2006 JUDGES: de Jersey CJ, McPherson and Williams JJA
Separate reasons for judgment of each member of the Court,
each concurring as to the order madeORDER: Each appeal dismissed with costs to be assessed CATCHWORDS: CONTRACTS – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – IMPLIED TERMS – TERMS ESSENTIAL TO ENABLE PERFORMANCE – where the appellant entered into a contract with the respondent to remediate contaminated land for a sum of money – where the land had formerly been the site of industrial activities which resulted in the soil being contaminated – where a contractual document required the appellant to render the land suitable for use and to ensure its removal from the contaminated land register – where appellant contends that full remediation could not be efficiently, economically or reasonably achieved – whether a term surrounding economic viability/feasibility could be implied into the contract – whether external documents not incorporated into the contract could lessen the obligation of the appellant under the contract Environmental Protection Act 1994 (Qld), s 396
Integrated Planning Act 1997 (Qld)Codelfa Construction Pty Ltd v State Rail Authority of NSW
(1981 - 1982) 149 CLR 337, followed
Davis Contractors Ltd v Fareham Urban District Council
[1956] AC 696, followed
Re an arbitration between Carr and The Shire of Wodonga
[1925] VLR 238, followed
Sirius International Insurance Co (Publ) v FAI General
Insurance Ltd (2004) 1 WLR 3251, citedCOUNSEL: R A Holt SC, with D Logan, for the appellant
W Sofronoff QC, with D Williams, for the respondentSOLICITORS: Minter Ellison for the applicant
Freehills for the respondent
de JERSEY CJ: The appellant sought a declaration as to the extent of its obligation under a written contract of 25 September 2003 between itself as contractor and the respondent as principal. It was a lump sum contract obliging the appellant to remediate 17 hectares of substantially contaminated land at Newstead, Brisbane, the site of a former gasworks. The issue is whether the appellant’s obligation was absolute, that is, to render the land suitable for any use; or whether, as the appellant essentially contended, it need discharge that obligation only if it could be done economically. The appellant’s application for a declaration to that latter effect was dismissed by the learned primary Judge, who made a declaration on the respondent’s cross-application upholding the construction for which the respondent contended. The appellant appeals against the dismissal of its application (appeal no 10901/05), and against the declaration made on the respondent’s cross- application…
Keep reading for free
Create a free CaseChat account to read Thiess Services Pty Ltd v Mirvac Queensland Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] QCA 50
- Decision Date
CaseChat Overview and Summary
The court's analysis focused on the principles of contract interpretation, particularly the implication of terms. The court examined whether the contract could be read in a way that made it commercially viable for Thiess Services to perform its obligations. The court held that no term implying economic viability or feasibility could be added to the contract, as the obligations were clear and unambiguous. Furthermore, the court ruled that external documents not incorporated into the contract could not alter the contractual obligations of Thiess Services.
In its judgment, the court dismissed the appeals, finding that the contract was clear in its terms and that Thiess Services was obligated to fully remediate the land as per the agreement. The court emphasised the importance of contractual clarity and the principle that external documents not included in the contract cannot modify its terms. The final orders were that each appeal was dismissed, and Thiess Services was to bear the costs of the appeals, to be assessed.
Orders
Orders of the court
Each appeal dismissed with costs to be assessed
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.