Court of Appeal
Supreme Court
New South Wales
- Summary available
- Amendment notes
Medium Neutral Citation: The Owners – Strata Plan No 84674 v Pafburn Pty Ltd [2023] NSWCA 301 Hearing dates: 1 November 2023 Date of orders: 13 December 2023 Decision date: 13 December 2023 Before: Ward P at [1];
Adamson JA at [2];
Basten AJA at [18]Decision: (1) Grant the appellant leave to appeal from the judgment in the Equity Division given on 23 February 2023.
(2) Allow the appeal and set aside the orders in the Equity Division.
(3) In place thereof:
(a) pursuant to the amended notice of motion filed on behalf of the plaintiff on 15 December 2022, strike out paragraphs 20-24, 27-29A of the first amended technology and construction list response filed by the defendants on 21 September 2022;
(b) order that the defendants pay the plaintiff’s costs of the motion.
(4) Order that the respondents pay the appellant’s costs of the proceedings in this Court.
Catchwords: APPEAL – leave to appeal – interlocutory order refusing to strike out defence – defence pleaded plaintiff’s claim apportionable – issue of general public importance – significant impact on course of trial
TORT – duty of care – statutory duty for construction work – extension of duty to subsequent owners of land – duty non-delegable – whether claim is apportionable under Pt 4 of Civil Liability Act 2002 (NSW) – claim by owners corporation for defective works – Design and Building Practitioners Act 2020 (NSW), s 37(1)
WORDS AND PHRASES – “non-delegable duty – “tort” – “vicarious liability”
Legislation Cited: Anti-Discrimination Act 1977 (NSW), ss 53, 113 (now 108)
Civil Liability Act 2002 (NSW), s 3C, Pt 1A, ss 5A, 5H, Div 7, s 5Q, Pt 4, ss 34, 35, 36, 39
Design and Building Practitioners Act 2020 (NSW), Pt 4, ss 36, 37, 39, 40, 41, Sch 1, cl 5
Environmental Planning and Assessment Act 1979 (NSW), s 6.20
Home Building Act 1989 (NSW), Pt 2C
Interpretation Act 1987 (NSW), ss 34, 35
Law Reform (Miscellaneous Provisions) Act 1965 (NSW), Pt 3, s 8
Law Reform (Vicarious Liability) Act 1983 (NSW), ss 5, 6, 8
Supreme Court Act 1970 (NSW), s 101
Wrongs Act 1936 (SA), s 27A
Cases Cited: Astley v AusTrust Ltd (1999) 197 CLR 1; [1999] HCA 6
Belous v Willetts [1970] VR 45
Boensch v Pascoe (2019) 268 CLR 593; [2019] HCA 49
Boulus Constructions Pty Ltd v Warrumbungle Shire Council (No 2) [2022] NSWSC 1368
Brodie v Singleton Shire Council (2001) 206 CLR 512; [2001] HCA 29
Byrne and Frew v Australian Airlines Ltd (1995) 185 CLR 410; [1995] HCA 24
Carmarthenshire County Council v Lewis [1955] AC 549
Commissioner of Police v Estate of Russell (2002) 55 NSWLR 232; [2002] NSWCA 272
Commissioner of Police v Mohamed [2009] NSWCA 432
The Commonwealth v Introvigne (1982) 150 CLR 258; [1982] HCA 40
Keep reading for free
Create a free CaseChat account to read The Owners Strata Plan No 84674 v Pafburn Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWCA 301
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court of Appeal was whether the appellant's claim, which alleged a breach of a statutory duty for construction work and sought to extend that duty to subsequent owners, constituted a "tort" for the purposes of the *Civil Liability Act 2002* (NSW). This determination was crucial to whether the respondent's defence, which sought to apportion liability, could stand. The court also considered the nature of the duty owed by builders and whether it was non-delegable.
The Court of Appeal reasoned that the claim, as pleaded, was not one that could be characterised as a "tort" in the traditional sense for the purposes of apportionment under the *Civil Liability Act 2002* (NSW). The court found that the claim was primarily based on a breach of statutory duty, and the principles of apportionment under that Act were not applicable to such claims. The court emphasised that the duty owed by a builder in this context was non-delegable, meaning the builder remained responsible for the work regardless of who performed it.
Consequently, the Court of Appeal granted leave to appeal, allowed the appeal, and set aside the orders of the Equity Division. The court ordered that the relevant paragraphs of the respondent's defence be struck out and that the respondent pay the appellant's costs of the motion and the appeal.
Orders
Orders of the court
(1) Grant the appellant leave to appeal from the judgment in the Equity Division given on 23 February 2023.
(2) Allow the appeal and set aside the orders in the Equity Division.
(3) In place thereof:
(a) pursuant to the amended notice of motion filed on behalf of the plaintiff on 15 December 2022, strike out paragraphs 20-24, 27-29A of the first amended technology and construction list response filed by the defendants on 21 September 2022;
(b) order that the defendants pay the plaintiff’s costs of the motion.
(4) Order that the respondents pay the appellant’s costs of the proceedings in this Court.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.