Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: The Owners – Strata Plan 91959 v JD Projects (NSW) Pty Ltd [2025] NSWCATCD 41 Hearing dates: 16 December 2025 Date of orders: 11 June 2025 Decision date: 11 June 2025 Jurisdiction: Consumer and Commercial Division Before: R Collins, Senior Member Decision: (1) Whole Sun Property Developments Pty Ltd is liable to cause the following works to be carried out by 5 January 2026:
(a) the scope of the works set out in the Expert Building Defect Report by Endeavour Engineering dated 27 June 2024 in the applicant’s tender bundle at tab 7 for the following items:
(i) Cantilevered Glass Balustrades – section 6.2;
(ii) Insufficient balcony drainage – section 6.3 and item UG06.2 of the Scott Schedule;
(iii) Corroding door jams – section 6.4;
(iv) Waterproofing of podium slab – section 6.5 and item B.5 of the Scott Schedule; and
(v) Items UG08.1, UG08.2, R.1 and B.2 of the Scott Schedule.
(b) the scope of works set out in the Fire Safety Compliance Assessment Report by Fahrenheit Global dated 27 June 2024 in the applicant’s tender bundle at tab 8 for Items no 1, 3, 4, 8, 9, 11, 12, 13, 18, and 19 of the Scott Schedule;
(c) where the items in (a) and (b) require a regulated design, causing a suitably qualified design practitioner under the Design and Building Practitioners Act 2020 to approve the design;
(d) Payment of relevant fees for any local council or other statutory authority approval that is required for the scope of works in (a) and (b),
together, “the Rectification Works”.
(2) The application for work orders under section 48O of the HB Act is otherwise dismissed.
(3) The proceedings against the first and second respondent are dismissed because they are withdrawn.
(4) The developer is to pay the owners corporation’s costs as agreed or assessed on the basis set out in the legal costs legislation (as set out in s 3A of the Legal Profession Uniform Law Application Act 2014 (NSW)) within 28 days of the date of these orders.
Catchwords: BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — Statutory warranty — Due care and skill
BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — Major defect – Major element
Legislation Cited: Civil and Administrative Tribunal Act 2013
Home Building Act 1989 (NSW)
Legal Profession Uniform Law Application Act 2014 (NSW)
Cases Cited: Ghazal v Masterton Homes Pty Ltd [2018] NSWCATAP 227
Rodny v Stricke [2020] NSWCATAP 20
Ericon Buildings Pty Limited v The Owners Strata Plan No 96597 [2020] NSWCATAP 265
Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185
Haines v Bendall [1991] HCA 15
Bellgrove v Eldridge [1954] HCA 36
Ashby v Slipper [2014] FCAFC 15
The Owners – Strata Plan No 66375 v King [2018] NSWCA 170
The Owners – Strata Plan No 93227 v InStyle Developments Pty Ltd [2023] NSWCATCD 154
Ashton v Stevenson; Stevenson…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan 91959 v JD Projects (NSW) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NSWCATCD 41
- Decision Date
CaseChat Overview and Summary
The legal issues before the tribunal involved the interpretation and application of the statutory warranty under the Home Building Act 1989 (NSW). Specifically, the tribunal needed to determine whether the defects identified in the building constituted major defects within the meaning of the Act, and whether the developer had fulfilled its obligations to remedy those defects. The tribunal also considered the meaning of 'major element' as defined in the Act, and the extent of the developer's liability under the statutory warranty.
The tribunal found that several defects identified in the building were indeed major defects, as they impaired the structural integrity, safety, health, or amenity of the building. The tribunal considered expert reports and evidence from both parties in making these determinations. The tribunal emphasised that the statutory warranty requires the developer to ensure that the building is constructed with due care and skill, and that any major defects are rectified. The tribunal held that the developer had failed to meet this obligation in respect of the identified defects. Accordingly, the tribunal made orders requiring the developer to rectify the defects and to pay the costs of the proceedings.
In summary, the tribunal ordered the developer to carry out specified rectification works, to obtain necessary approvals, and to pay the costs of the owners corporation. The tribunal dismissed the application for work orders in respect of other defects and dismissed the proceedings against other respondents as they were withdrawn.
Orders
Orders of the court
(1) Whole Sun Property Developments Pty Ltd is liable to cause the following works to be carried out by 5 January 2026:
(a) the scope of the works set out in the Expert Building Defect Report by Endeavour Engineering dated 27 June 2024 in the applicant’s tender bundle at tab 7 for the following items:
(i) Cantilevered Glass Balustrades – section 6.2;
(ii) Insufficient balcony drainage – section 6.3 and item UG06.2 of the Scott Schedule;
(iii) Corroding door jams – section 6.4;
(iv) Waterproofing of podium slab – section 6.5 and item B.5 of the Scott Schedule; and
(v) Items UG08.1, UG08.2, R.1 and B.2 of the Scott Schedule.
(b) the scope of works set out in the Fire Safety Compliance Assessment Report by Fahrenheit Global dated 27 June 2024 in the applicant’s tender bundle at tab 8 for Items no 1, 3, 4, 8, 9, 11, 12, 13, 18, and 19 of the Scott Schedule;
(c) where the items in (a) and (b) require a regulated design, causing a suitably qualified design practitioner under the Design and Building Practitioners Act 2020 to approve the design;
(d) Payment of relevant fees for any local council or other statutory authority approval that is required for the scope of works in (a) and (b),
together, “the Rectification Works”.
(2) The application for work orders under section 48O of the HB Act is otherwise dismissed.
(3) The proceedings against the first and second respondent are dismissed because they are withdrawn.
(4) The developer is to pay the owners corporation’s costs as agreed or assessed on the basis set out in the legal costs legislation (as set out in s 3A of the Legal Profession Uniform Law Application Act 2014 (NSW)) within 28 days of the date of these orders.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.