The Owners - Strata Plan 91959 v JD Projects (NSW) Pty Ltd

Link copied
Case Copied 37 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: The Owners – Strata Plan 91959 v JD Projects (NSW) Pty Ltd [2025] NSWCATCD 41
Hearing dates: 16 December 2025
Date of orders: 11 June 2025
Decision date: 11 June 2025
Jurisdiction:Consumer and Commercial Division
Before: R Collins, Senior Member
Decision:

(1)      Whole Sun Property Developments Pty Ltd is liable to cause the following works to be carried out by 5 January 2026:

(a)      the scope of the works set out in the Expert Building Defect Report by Endeavour Engineering dated 27 June 2024 in the applicant’s tender bundle at tab 7 for the following items:

(i)    Cantilevered Glass Balustrades – section 6.2;

(ii)   Insufficient balcony drainage – section 6.3 and item UG06.2 of the Scott Schedule;

(iii)   Corroding door jams – section 6.4;

(iv)   Waterproofing of podium slab – section 6.5 and item B.5 of the Scott Schedule; and

(v)   Items UG08.1, UG08.2, R.1 and B.2 of the Scott Schedule.

(b)      the scope of works set out in the Fire Safety Compliance Assessment Report by Fahrenheit Global dated 27 June 2024 in the applicant’s tender bundle at tab 8 for Items no 1, 3, 4, 8, 9, 11, 12, 13, 18, and 19 of the Scott Schedule;

(c)      where the items in (a) and (b) require a regulated design, causing a suitably qualified design practitioner under the Design and Building Practitioners Act 2020 to approve the design;

(d)      Payment of relevant fees for any local council or other statutory authority approval that is required for the scope of works in (a) and (b),

   together, “the Rectification Works”.

(2) The application for work orders under section 48O of the HB Act is otherwise dismissed.

(3)      The proceedings against the first and second respondent are dismissed because they are withdrawn.

(4) The developer is to pay the owners corporation’s costs as agreed or assessed on the basis set out in the legal costs legislation (as set out in s 3A of the Legal Profession Uniform Law Application Act 2014 (NSW)) within 28 days of the date of these orders.

Catchwords:

BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — Statutory warranty — Due care and skill

BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — Major defect – Major element

Legislation Cited:

Civil and Administrative Tribunal Act 2013

Home Building Act 1989 (NSW)

Legal Profession Uniform Law Application Act 2014 (NSW)

Cases Cited:

Ghazal v Masterton Homes Pty Ltd [2018] NSWCATAP 227

Rodny v Stricke [2020] NSWCATAP 20

Ericon Buildings Pty Limited v The Owners Strata Plan No 96597 [2020] NSWCATAP 265

Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185

Haines v Bendall [1991] HCA 15

Bellgrove v Eldridge [1954] HCA 36

Ashby v Slipper [2014] FCAFC 15

The Owners – Strata Plan No 66375 v King [2018] NSWCA 170

The Owners – Strata Plan No 93227 v InStyle Developments Pty Ltd [2023] NSWCATCD 154

Ashton v Stevenson; Stevenson…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Owners - Strata Plan 91959 v JD Projects (NSW) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWCATCD 41
Decision Date

CaseChat Overview and Summary

The Owners - Strata Plan 91959 initiated proceedings against JD Projects (NSW) Pty Ltd, along with other respondents, in the New South Wales Civil and Administrative Tribunal (NCAT). The dispute pertains to alleged defects in a residential building, which the applicants claim fall under the statutory warranty provisions of the Home Building Act 1989 (NSW). The applicants sought orders for rectification of the defects, along with other relief.

The legal issues before the tribunal involved the interpretation and application of the statutory warranty under the Home Building Act 1989 (NSW). Specifically, the tribunal needed to determine whether the defects identified in the building constituted major defects within the meaning of the Act, and whether the developer had fulfilled its obligations to remedy those defects. The tribunal also considered the meaning of 'major element' as defined in the Act, and the extent of the developer's liability under the statutory warranty.

The tribunal found that several defects identified in the building were indeed major defects, as they impaired the structural integrity, safety, health, or amenity of the building. The tribunal considered expert reports and evidence from both parties in making these determinations. The tribunal emphasised that the statutory warranty requires the developer to ensure that the building is constructed with due care and skill, and that any major defects are rectified. The tribunal held that the developer had failed to meet this obligation in respect of the identified defects. Accordingly, the tribunal made orders requiring the developer to rectify the defects and to pay the costs of the proceedings.

In summary, the tribunal ordered the developer to carry out specified rectification works, to obtain necessary approvals, and to pay the costs of the owners corporation. The tribunal dismissed the application for work orders in respect of other defects and dismissed the proceedings against other respondents as they were withdrawn.

Orders

Orders of the court

(1) Whole Sun Property Developments Pty Ltd is liable to cause the following works to be carried out by 5 January 2026:

(a) the scope of the works set out in the Expert Building Defect Report by Endeavour Engineering dated 27 June 2024 in the applicant’s tender bundle at tab 7 for the following items:

(i) Cantilevered Glass Balustrades – section 6.2;

(ii) Insufficient balcony drainage – section 6.3 and item UG06.2 of the Scott Schedule;

(iii) Corroding door jams – section 6.4;

(iv) Waterproofing of podium slab – section 6.5 and item B.5 of the Scott Schedule; and

(v) Items UG08.1, UG08.2, R.1 and B.2 of the Scott Schedule.

(b) the scope of works set out in the Fire Safety Compliance Assessment Report by Fahrenheit Global dated 27 June 2024 in the applicant’s tender bundle at tab 8 for Items no 1, 3, 4, 8, 9, 11, 12, 13, 18, and 19 of the Scott Schedule;

(c) where the items in (a) and (b) require a regulated design, causing a suitably qualified design practitioner under the Design and Building Practitioners Act 2020 to approve the design;

(d) Payment of relevant fees for any local council or other statutory authority approval that is required for the scope of works in (a) and (b),

together, “the Rectification Works”.

(2) The application for work orders under section 48O of the HB Act is otherwise dismissed.

(3) The proceedings against the first and second respondent are dismissed because they are withdrawn.

(4) The developer is to pay the owners corporation’s costs as agreed or assessed on the basis set out in the legal costs legislation (as set out in s 3A of the Legal Profession Uniform Law Application Act 2014 (NSW)) within 28 days of the date of these orders.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.