Tagara Builders P/L v AP & L Services P/L

Link copied
Case Copied 31 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Application for Judicial Review)

TAGARA BUILDERS P/L v AP & L SERVICES P/L & ORS

[2015] SASC 30

Judgment of The Honourable Justice Blue

27 February 2015

ADMINISTRATIVE LAW - JUDICIAL REVIEW - GROUNDS OF REVIEW - JURISDICTIONAL MATTERS

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS

STATUTES - ACTS OF PARLIAMENT - STATUTORY POWERS AND DUTIES - CONSTRUCTION - CONFERRAL AND EXTENT OF POWER

Action for judicial review.

The plaintiff, Tagara Builders, entered into a contract with the first defendant, AP & L Services, for AP & L to supply and install ceilings and linings. Unbeknown to Tagara, AP & L did not hold a contractors licence in contravention of section 6 of the Building Work Contractors Act 1995 (SA). Section 6(2) disentitles an unlicensed contractor to any fee, other consideration or compensation under or in relation to a contract unless a court is satisfied that the contractor’s failure to be so authorised resulted from inadvertence only.

AP & L lodged monthly progress claims with Tagara. It sought adjudication under the Building and Construction Industry Security of Payment Act 2009 (SA) of its August and September 2014 progress claims. An adjudicator determined that it was entitled to payment of $42,963.79 in respect of the August progress claim. An adjudicator was appointed to adjudicate the September 2014 progress claim.

Upon learning that AP & L did not hold a contractor’s licence, Tagara instituted the action seeking an order quashing the adjudication of the August 2014 progress claim and prohibiting the consideration and determination of the September 2014 progress claim on the ground that the adjudicators did not have jurisdiction because the Building Work Contractors Act disentitled AP & L to the consideration under the contract.

Held:

1. An adjudicator does not have jurisdiction under the Building and Construction Industry Security of Payment Act if the claimant is disentitled to the consideration under the contract by section 6 of the Building Work Contractors Act (at [34], [35], and [51]).

2. Orders made quashing the adjudication determination in respect of the August 2014 progress claim and prohibiting further consideration or determination of the September 2014 progress claim (at [52]).

Building and Construction Industry Security of Payment Act 2009 (SA) s 3, s 4, s 7, s 8, s 9, s 10, s 11, s 12, s 13, s 17, s 22; Building and Construction Industry Security of Payment Act 1999 (NSW); Building and Construction Industry Payments Act 2004 (Qld) s 17, s 18, s 19; Builders Licensing Act 1986 (SA) s 39; Building Work Contractors Act 1995 (SA) s 6; Fast Track Rules 2014 (SA); Home Building Act 1989 (NSW) s 10, s 94; Queensland Building Services Authority Act 1991 (Qld) s 42, referred to.
Brodyn Pty Ltd v Davenport [2003] NSWSC 1019; Lamprell v The Guardians of the Poor of the Billericay Union, in the County of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Tagara Builders P/L v AP & L Services P/L and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] SASC 30
Decision Date

CaseChat Overview and Summary

Tagara Builders P/L and AP & L Services P/L were involved in a contractual dispute over payment claims for work carried out by AP & L Services under a subcontract. The dispute centred on the enforceability of the subcontract and the jurisdiction of an adjudicator appointed under the Building and Construction Industry Security of Payment Act 1999 (SA). AP & L Services was found to be unlicensed, which rendered the subcontract unenforceable under the Contractors Act 2008 (SA). This raised questions about the jurisdiction of the adjudicator appointed to adjudicate on the payment claims and the validity of the adjudicator's determination.

The primary legal issues were whether the jurisdiction of the adjudicator depended on the existence of a valid contract and whether the Contractors Act disentitled AP & L Services from receiving payment. The court had to determine if the adjudicator had the authority to make a determination when the underlying contract was unenforceable due to AP & L Services' lack of a contractor's licence. The court also needed to consider whether the statutory provisions allowed for an adjudicator to make a determination in the absence of an enforceable contract.

The court ruled that AP & L Services was disentitled from recovering the contract price under section 6(2) of the Contractors Act, as it was unlicensed. This disentitlement meant that AP & L Services was not entitled to payment under the Act, rendering the subcontract unenforceable. Consequently, the adjudicator appointed by the Institute of Arbitrators and Mediators Australia had no jurisdiction to make an adjudication determination, and the determination made by the adjudicator was void. Additionally, the adjudicator appointed for the second adjudication did not have the jurisdiction to proceed with the adjudication.

The court ordered that the determination made by Mr Covino was void and that Mr Fullerton had no jurisdiction to proceed with the second adjudication. Tagara Builders P/L was granted orders in the nature of certiorari and prohibition against the adjudication process.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

The issues for consideration are:1Does the jurisdiction of an adjudicator under the Act depend on there being in existence a contract in respect of which the claimant is not disentitled to the consideration by other legislation? 2Does the Contractors Act so disentitle APL? Background In March 2014, Tagara and APL entered into a subcontract (the Contract) for APL to supply and install ceilings and linings for a two storey Specialist Learning Centre at Noarlunga Downs for $355,000. The Contract provided for progress claims to be submitted on the 26th day of each month. APL served monthly progress claims in the form of payment claims under section 13 of the Act. APL was dissatisfied with Tagara’s payment schedule served in response to its August 2014 progress claim and applied for adjudication under section 17 of the Act (the First Adjudication). The second defendant Tony Covino was appointed adjudicator by the fourth defendant The Institute of Arbitrators and Mediators Australia (IAMA). On 3 December 2014, Mr Covino determined under section 22 of the Act that the amount payable by Tagara in respect of the August progress claim was $42,963.79 plus GST (the Determination). APL was dissatisfied with Tagara’s payment schedule served in response to its September 2014 progress claim and applied for adjudication (the Second Adjudication). On 10 December 2014, the third defendant Colin Fullerton was appointed adjudicator by IAMA. On 11 December 2014, Tagara learnt that APL did not hold a contractors licence. On 15 December 2014, Tagara instituted this action seeking to quash the Determination and prohibition in respect of the Second Adjudication. The sole director of APL, Trudi Hotstone, held a contractors licence at all material times, but it was subject to conditions that the value of any contract was not to exceed $280,000 and building work was not to exceed one storey. The supervisor employed by APL, Alan Schnaars, was registered as a building work supervisor, but as a supervisor for Ms Hotstone and not APL. APL accepts that, unless and until a court makes a determination under section 6(2)(b) of the Contractors Act that it is satisfied that APL's failure to be authorised resulted from inadvertence only (excusal), section 6(2) provides that APL is not entitled to any fee or other consideration under the Contract. However, APL contends that this does not deprive an adjudicator of jurisdiction under the Act and, upon the point being raised during an adjudication, an adjudicator is required to note the point but proceed to make an adjudication on the merits without further regard to the point. On its part, Tagara accepts that section 6(2) of the Contractors Act does not preclude APL bringing an action for restitution notwithstanding that APL does not hold a contractors licence, but contends that the Contract as such is unenforceable by APL and this deprives an adjudicator of jurisdiction under the Act. APL contends that its failure to be licensed was inadvertent within the meaning of the Act. Tagara takes issue with this contention. It is agreed that I am to determine this action on the basis that no finding is made one way or the other on this question and that a court has not made a determination under section 6(2)(b) of the Contractors Act.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

BLUE J
When the Queensland Court of Appeal decided Cant Contracting Pty Ltd v Casella,[32] section 42 had already been amended to afford a remedy in the nature of quantum meruit. Each of section 42 of the Queensland Building Services Authority Act and section 6 of the Contractors Act prescribes the consequences of entry into a building contract by an unlicensed contractor, namely that the contractor is disentitled from recovering the contract price but is not precluded from bringing an action in the nature of quantum meruit. Whether such a contract be characterised as “illegal” or not has no effect upon the consequences. Contrary to the submission of APL, the reasoning of the Queensland Court of Appeal in Cant Contracting Pty Ltd v Casella[33] remains applicable to the South Australian legislation.[32] [2007] 2 Qd R 13.[33] Ibid.Conclusion APL is and at all material times has been disentitled by section 6(2) of the Contractors Act to payment of the contract price or other consideration under the Contract for performing work. It was therefore not entitled to payment of any progress payments within the meaning of section 13 of the Act. IAMA had no jurisdiction to appoint Mr Covino or Mr Fullerton as adjudicators. Mr Covino had no jurisdiction to make an adjudication determination and the Determination is void. Mr Fullerton has no jurisdiction to embark upon a determination of the Second Adjudication. Tagara is entitled to orders in the nature of certiorari and prohibition.

Ratio Decidendi

Legal Principle Established

Established by: BLUE J

Full text does not contain this section.