SPI Electricity Pty Ltd v Australian Energy Regulator

Link copied
Case Copied 79 min read

FEDERAL COURT OF AUSTRALIA

SPI Electricity Pty Ltd v Australian Energy Regulator [2014] FCA 1012

Citation: SPI Electricity Pty Ltd v Australian Energy Regulator [2014] FCA 1012
Parties: SPI ELECTRICITY PTY LTD (ACN 064 651 118) (TRADING AS SP AUSNET) v AUSTRALIAN ENERGY REGULATOR
File number: VID 177 of 2013
Judge: FOSTER J
Date of judgment: 17 September 2014
Catchwords: ADMINISTRATIVE LAW – whether an electricity distributor in Victoria has made out any grounds of review under the Administrative Decisions (Judicial Review) Act 1977 (Cth) entitling it to relief under s 16 of that Act quashing or setting aside in part a regulatory decision made by the Australian Energy Regulator in respect of the distributor’s approved budget for the period 2012–2015 for the installation of advanced meters in residential premises and small business premises in Victoria pursuant to an Order in Council made by the Governor of Victoria on 28 August 2007 under ss 15A and 46D of the Electricity Industry Act 2000 (Vic).
Legislation: Administrative Decisions (Judicial Review) Act 1977 (Cth) ss 3, 5, 6, 10, 16(1)(a), s 16(1)(d)
National Electricity (Victoria) Act 2005 (Vic) ss 19, 20, 23, 27A, 29(2)
Electricity Industry Act 2000 (Vic) ss 15A, 46D
Order in Council dated 28 August 2007 (Vic) published in the Victoria Government Gazette No S200 (as amended)
Trade Practices Act 1974 (Cth)
Cases cited: Appeal by SPI Electricity Pty Ltd [2012] ACompT 11
Appeal by SPI Electricity Pty Ltd [2013] ACompT 7
Buck v Bavone (1976) 135 CLR 110
R v Hunt; Ex parte Sean Investments Pty Limited (1979) 180 CLR 322
Telstra Corporation Ltd v Australian Competition and Consumer Commission (2009) 176 FCR 153
Date of hearing: 30–31 May and 3 June 2013
Place: Sydney
Division: GENERAL DIVISION
Category: Catchwords
Number of paragraphs: 121
Counsel for the Applicant: Mr S Horgan SC and Mr C Furnell
Solicitor for the Applicant: Johnson Winter & Slattery
Counsel for the Respondent: Ms M Sloss SC and Mr C Horan
Solicitor for the Respondent: Australian Government Solicitor

IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

GENERAL DIVISION

VID 177 of 2013

BETWEEN:

SPI ELECTRICITY PTY LTD (ACN 064 651 118)
(TRADING AS SP AUSNET)
Applicant

AND:

AUSTRALIAN ENERGY REGULATOR
Respondent

JUDGE:

FOSTER J

DATE OF ORDER:

17 SEPTEMBER 2014

WHERE MADE:

SYDNEY

THE COURT ORDERS THAT:

1.The application be dismissed.

2.The applicant pay the respondent’s costs of and incidental to the application.

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

GENERAL DIVISION

VID 177 of 2013

BETWEEN:

SPI ELECTRICITY PTY LTD (ACN 064 651 118)
(TRADING AS SP AUSNET)
Applicant

AND:

AUSTRALIAN ENERGY REGULATOR
Respondent

JUDGE:

FOSTER J

DATE:

17 SEPTEMBER 2014

PLACE:

SYDNEY

REASONS FOR JUDGMENT

  1. By this proceeding, the applicant, SPI Electricity Pty Ltd (trading as SP AUSNet) (SPI) seeks judicial review of a regulatory decision made by the respondent, the Australian Energy Regulator (AER), on or…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read SPI Electricity Pty Ltd v Australian Energy Regulator and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] FCA 1012
Decision Date

CaseChat Overview and Summary

The case of SPI Electricity Pty Ltd v Australian Energy Regulator involved SPI, an electricity distributor in Victoria, challenging the Australian Energy Regulator's (AER) Amended Budget Determination. This determination, made following a remitter from the Australian Competition Tribunal (Tribunal), pertained to SPI's approved budget for the period 2012–2015 concerning the installation of advanced meters in residential and small business premises in Victoria. The budget was approved under an Order in Council made by the Governor of Victoria on 28 August 2007 under sections 15A and 46D of the Electricity Industry Act 2000 (Vic). The primary legal issue was whether SPI had grounds to seek relief under section 16 of the Administrative Decisions (Judicial Review) Act 1977 (Cth) to quash or set aside in part the AER’s Amended Budget Determination.

The Court examined whether the AER’s Amended Budget Determination was a reviewable decision under the ADJR Act. It concluded that the determination was indeed a decision of an administrative character made under an enactment, specifically the National Electricity (Victoria) Act 2005 (NEV Act). This made the determination amenable to review under the ADJR Act. Additionally, SPI was deemed to be an aggrieved party, as defined by the ADJR Act, thereby satisfying the jurisdictional requirement for the Court to hear SPI’s application for review. The Court also noted that SPI's claims were not precluded by adequate alternative review mechanisms provided by other laws.

In its decision, the Court found that the Tribunal had already provided sufficient grounds for its dismissal of SPI’s appeal. Consequently, the Court dismissed SPI’s application for review of the AER’s Amended Budget Determination. The Court also ordered that SPI pay the AER’s costs associated with the application.

Orders

Orders of the court

1. The application be dismissed.

2. The applicant pay the respondent’s costs of and incidental to the application.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

In preparing these Reasons for Judgment, I have assumed that readers of these reasons will have already read both the first the second Tribunal decisions. Notwithstanding that assumption, it will be necessary from time to time to refer to passages from both of those decisions and also to cover some ground which has been covered in detail in those decisions. BACKGROUND SPI is one of five registered distribution network service providers (DNSPs) in the State of Victoria. Each of those DNSPs has the exclusive right for a specified regulatory period to provide electricity distribution services in its allocated geographical areas. The Tribunal attached to its second decision as Attachment “A” a map of Victoria showing the particular geographical area allocated to each DNSPs. SPI’s allocated area covers a large part of eastern and north-eastern Victoria. The AER’s Amended Budget Determination was made by the AER on remitter from the Tribunal. In broad terms, the AER was required by reason of that remitter to re-assess aspects of the continued funding for the rollout of advanced metering infrastructure (AMI) in Victoria. SPI was and is an AMI distributor. On 28 February 2011 SPI submitted to the AER its Budget Application for the period 2012–2015 (original budget application) in respect of its participation in the program for the rollout of AMI in Victoria. That program was being carried out pursuant to an Order in Council made by the Governor of Victoria in Council under s 15A and s 46D of the Electricity Industry Act 2000 (Vic) on 28 August 2007 (as amended from time to time) (the AMI order). On 31 October 2011, the AER issued its final determination in relation to SPI’s original budget application and also in relation to the budget applications of the other Victorian DNSPs. This final determination is entitled Victorian Advanced Metering Infrastructure Review 2012–15 budget and charges application. I shall refer to this determination as the AER’s original final determination. By this determination, the AER reduced SPI’s claimed budget by $72.2 million. On 30 November 2011, SPI appealed to the Tribunal pursuant to s 29(2) of the NEV Act against certain aspects of the AER’s original final determination. On 26 April 2012, by its first decision, the Tribunal set aside the AER’s original final determination insofar as it related to certain particular aspects of that determination. The Tribunal remitted the AER’s original final determination to the AER to be reconsidered in accordance with the Tribunal’s Reasons for Decision set out in the first Tribunal decision. Thereafter, SPI and the AER engaged in a process which they considered best met the requirements of the remitter from the Tribunal. That process was an iterative process which replicated the “propose/response” process deployed in other areas of electricity regulation. That process began in early May 2012 and was not completed until early 2013 when the AER issued its Amended Budget Determination.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

On 1 August 2013 the Tribunal dismissed SPI’s appeal. The Tribunal published its Reasons for Decision on the same day (Appeal by SPI Electricity Pty Ltd [2013] ACompT 7) (the second Tribunal decision). Because the Tribunal dismissed SPI’s appeal, it has become necessary for the Court to determine SPI’s claims for relief in the present proceeding. By these Reasons for Judgment, I determine those claims. In preparing these Reasons for Judgment, I have assumed that readers of these reasons will have already read both the first the second Tribunal decisions. Notwithstanding that assumption, it will be necessary from time to time to refer to passages from both of those decisions and also to cover some ground which has been covered in detail in those decisions. BACKGROUND SPI is one of five registered distribution network service providers (DNSPs) in the State of Victoria. Each of those DNSPs has the exclusive right for a specified regulatory period to provide electricity distribution services in its allocated geographical areas. The Tribunal attached to its second decision as Attachment “A” a map of Victoria showing the particular geographical area allocated to each DNSPs. SPI’s allocated area covers a large part of eastern and north-eastern Victoria. The AER’s Amended Budget Determination was made by the AER on remitter from the Tribunal. In broad terms, the AER was required by reason of that remitter to re-assess aspects of the continued funding for the rollout of advanced metering infrastructure (AMI) in Victoria. SPI was and is an AMI distributor. On 28 February 2011 SPI submitted to the AER its Budget Application for the period 2012–2015 (original budget application) in respect of its participation in the program for the rollout of AMI in Victoria. That program was being carried out pursuant to an Order in Council made by the Governor of Victoria in Council under s 15A and s 46D of the Electricity Industry Act 2000 (Vic) on 28 August 2007 (as amended from time to time) (the AMI order). On 31 October 2011, the AER issued its final determination in relation to SPI’s original budget application and also in relation to the budget applications of the other Victorian DNSPs. This final determination is entitled Victorian Advanced Metering Infrastructure Review 2012–15 budget and charges application. I shall refer to this determination as the AER’s original final determination. By this determination, the AER reduced SPI’s claimed budget by $72.2 million. On 30 November 2011, SPI appealed to the Tribunal pursuant to s 29(2) of the NEV Act against certain aspects of the AER’s original final determination. On 26 April 2012, by its first decision, the Tribunal set aside the AER’s original final determination insofar as it related to certain particular aspects of that determination. The Tribunal remitted the AER’s original final determination to the AER to be reconsidered in accordance with the Tribunal’s Reasons for Decision set out in the first Tribunal decision.

Ratio Decidendi

Legal Principle Established

The contentions which I have summarised at [37]–[41] above were developed further in SPI’s written submissions.CONSIDERATION AND DECISIONJurisdiction Section 5(1) of the ADJR Act provides that a person who is aggrieved by a decision to which the ADJR Act applies may seek review of that decision in this Court or in the Federal Circuit Court of Australia upon any one or more of the grounds specified in s 5(1)(a) to (i), some of which are further explained by subs (2) and (3) of s 5. The expression “… decision to which this Act applies …” also appears in s 6(1) which deals with reviewable conduct engaged in for the purpose of making such a decision. That expression is defined in s 3(1) of the ADJR Act in the following terms:decision to which this Act applies means a decision of an administrative character made, proposed to be made, or required to be made (whether in the exercise of a discretion or not and whether before or after the commencement of this definition):(a)under an enactment referred to in paragraph (a), (b), (c) or (d) of the definition of enactment; or(b)by a Commonwealth authority or an officer of the Commonwealth under an enactment referred to in paragraph (ca) or (cb) of the definition of enactment;other than:(c) a decision by the Governor‑General; or(d) a decision included in any of the classes of decisions set out in Schedule 1.Note:Regulations for the purposes of section 19 can declare that decisions that are covered by this definition are not subject to judicial review under this Act. The definition of “enactment” in s 3(1) of the ADJR Act covers the NEV Act and any instrument made under that Act (s 3(a) and subpars (ca) and (cb) of the definition of enactment). Sections 19, 20, 23 and 27A of the NEV Act together operate to confer upon the AER the relevant functions and powers of the Essential Services Commissioner of Victoria under the AMI order. Those functions and powers include assessing, approving or rejecting and determining the approved budget of a DNSP such as SPI. The AER’s Amended Budget Determination is not within the classes of decision specified in Schedule 1 to the ADJR Act as decisions to which the ADJR Act does not apply. For these reasons, because the AER’s original final determination was a decision made under the AMI order, it is amenable to review under the ADJR Act. The AER’s Amended Budget Determination was also such a decision and, for the same reasons, is also amenable to review under the ADJR Act. There is no doubt that SPI is an aggrieved person within the meaning of s 5(1) and s 6(1). Accordingly, this Court has jurisdiction to deal with SPI’s application for review of the AER’s Amended Budget Determination. Discretionary Refusal of Relief (s 10(2)(b)(ii) of the ADJR Act) Section 10 of the ADJR Act relevantly provides:10 Rights conferred by this Act to be additional to other rights(1)The rights conferred by sections 5, 6 and 7 on a person to make an application to the Federal Court or the Federal Circuit Court in respect of a decision, in respect of conduct engaged in for the purpose of making a decision or in respect of a failure to make a decision:(a)are in addition to, and not in derogation of, any other rights that the person has to seek a review, whether by the court, by another court, or by another tribunal, authority or person, of that decision, conduct or failure; and(2) Notwithstanding subsection (1):…(b)the Federal Court or the Federal Circuit Court may, in its discretion, refuse to grant an application under section 5, 6 or 7 that was made to the court in respect of a decision, in respect of conduct engaged in for the purpose of making a decision, or in respect of a failure to make a decision, for the reason:(i)that the applicant has sought a review by the court, or by another court, of that decision, conduct or failure otherwise than under this Act; or(ii)that adequate provision is made by any law other than this Act under which the applicant is entitled to seek a review by the court, by another court, or by another tribunal, authority or person, of that decision, conduct or failure.(3)In this section, review includes a review by way of reconsideration, re‑hearing, appeal, the grant of an injunction or of a prerogative or statutory writ or the making of a declaratory or other order.