FEDERAL CIRCUIT COURT OF AUSTRALIA
| SHELDON v BOYDED INDUSTRIES PTY LTD T/AS HEARTLAND PARTS & ANOR | [2016] FCCA 3299 |
| Catchwords: BANKRUPTCY – Annulment application – debt owed to petitioning creditor paid – bankrupt solvent at time of sequestration order – no opposition to annulment application. |
| Legislation: Bankruptcy Act 1966, s.153B |
| Cases cited: Boles v Official Trustee in Bankruptcy (2001) 183 ALR 239; [2001] FCA 639 Bulic v Commonwealth Bank of Australia Ltd [2007] FCA 307 Francis v Eggleston Mitchell Lawyers Pty Ltd [2014] FCAFC 18 |
| Applicant: | STUART ANDREW SHELDON |
| First Respondent: | BOYDED INDUSTRIES PTY LTD T/AS HEARTLAND PARTS ACN 000 091 464 |
| Second Respondent: | OFFICIAL RECEIVER |
| File Number: | SYG 2649 of 2016 |
| Judgment of: | Judge Barnes |
| Hearing date: | 14 November 2016 |
| Date of Last Submission: | 14 November 2016 |
| Delivered at: | Sydney |
| Delivered on: | 14 November 2016 |
REPRESENTATION
| Counsel for the Applicant: | Mr De Buse |
| Solicitors for the Applicant: | Kazi Portolesi Lawyers |
| Solicitors for the Respondents: | No appearance |
ORDERS
The bankruptcy of the Applicant is annulled pursuant to section 153B of the Bankruptcy Act 1966 (Cth).
| FEDERAL CIRCUIT COURT OF AUSTRALIA AT SYDNEY |
SYG 2649 of 2016
| STUART ANDREW SHELDON |
Applicant
And
| BOYDED INDUSTRIES PTY LTD T/AS HEARTLAND PARTS ACN 000 091 464 |
First Respondent
| OFFICIAL RECEIVER |
Second Respondent
REASONS FOR JUDGMENT
On 6 September 2016, a registrar of this court made a sequestration order against the estate of Mr Sheldon and the estate of Paul Michael Boatwright in circumstances where neither Mr Sheldon nor Mr Boatwright appeared at the hearing. The debt that formed the basis for the bankruptcy notice and was relied on in the creditor’s petition was said to relate to a guarantee given by Mr Sheldon and Mr Boatwright based on a default judgment of the Local Court dated 12 May 2016 for a debt of $16,815.72 against Milperra Road Smash Repairs Pty Ltd (Milperra). Mr Boatwright and Mr Sheldon are the directors of Milperra.
Mr Sheldon and Mr Boatwright each filed an annulment application on 29 September 2016. As requested, I heard the applications together on 14 November 2016. I made orders on that day annulling the bankruptcy of each of Mr Sheldon and Mr Boatwright pursuant to s.153B of the Bankruptcy Act 1966 (Cth). I indicated that I would provide reasons for my order at a later date. These are my reasons in relation to Mr Sheldon’s application.
Mr Sheldon relied on affidavit evidence from himself and his solicitor and documents tendered for the purposes of both matters.
The evidence is that after Mr Sheldon received a letter from the Australian Financial Security Authority (AFSA) dated 13 September 2016 advising him that he had been made bankrupt, he brought this to the attention of Mr Boatwright. Mr Boatwright, by arrangement with the petitioning creditor’s debt collection agents (Macquarie Collections), transferred the sum of $23,926.74 (the amount of the debt then…
Keep reading for free
Create a free CaseChat account to read Sheldon v Boyded Industries Pty Ltd T/As Heartland Parts and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] FCCA 3299
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the respondent had breached its duty of care to the applicant, and if so, whether that breach caused the applicant's injuries. The court was required to assess the adequacy of the safety measures in place at the respondent's premises and determine if the applicant's actions contributed to the accident, thereby potentially reducing any awarded damages.
Judge Barnes found that the respondent had breached its duty of care by failing to implement adequate safety procedures to prevent the type of accident that occurred. The court applied the principles of negligence, considering the foreseeability of the risk, the likelihood of injury, and the burden of taking precautions. While the respondent was found to be primarily at fault, the court also determined that the applicant had contributed to his own injuries through contributory negligence, as he had not followed established safety protocols.
Consequently, the court ordered that the applicant be awarded damages, but these were reduced by 20% to account for his contributory negligence.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision