| SUPREME COURT OF VICTORIA COURT OF APPEAL |
| S EAPCI 2022 0055 |
| RW & ME SMITH PTY LTD (ACN 105 445 645) | Applicant |
| v | |
| BORAL RESOURCES (VIC) PTY LTD (ACN 004 620 731) | Respondent |
---
| JUDGES: | McLEISH, NIALL and MACAULAY JJA |
| WHERE HELD: | Melbourne |
| DATE OF HEARING: | 27 March 2023 |
| DATE OF JUDGMENT: | 11 August 2023 |
| MEDIUM NEUTRAL CITATION: | [2023] VSCA 182 |
| JUDGMENT APPEALED FROM: | RW & ME Smith Pty Ltd v Boral Resources (Vic) Pty Ltd [2022] VCC 729 (Judge A Ryan) |
---
CONTRACT – Construction – Summary termination – Meaning of ‘Cartage Works’ in cartage contract – Whether applicant’s repair of equipment at respondent’s plant fell within meaning of ‘Cartage Works’ – Whether trial judge erred finding respondent entitled to summarily determine cartage contract due to applicant’s alleged default in performing ‘Cartage Works’ – Error established – Appeal allowed.
CONTRACT – Construction – Scope of release clauses – Whether wide general words of release confined to apply only to specific subject matter – Properly construed relevant clauses only released and indemnified respondent from claims arising from short-term contract made after termination of principal contract – Respondent unable to rely on release in claim against it for breach of principal contract.
Grant v John Grant & Sons Pty Ltd (1954) 91 CLR 112 applied; Wardman v Macquarie Bank Ltd [2023] FCAFC 13 considered.
---
| Counsel | |||
| Applicant: | Mr LEP Magowan | ||
| Respondent: | Ms MJ O’Sullivan KC with Mr O Fagir | ||
Solicitors | |||
| Applicant: | Aitken Partners | ||
| Respondent: | Australian Business Lawyers & Advisors | ||
TABLE OF CONTENTS
Introduction
Grounds of appeal and issues
Factual background
The Agreement
Incident on 9 July 2015
Boral’s investigation and response
The Second Deed
Judge’s reasons
Breach of Agreement
Unconscionability and estoppel
Termination of Agreement
Second Deed
Goodwill
Loss and damage
Were the repair works ‘Cartage Works’?
Whether a truck was being loaded at the time of the incident
The construction of ‘Cartage Works’
Did the applicant breach the Agreement and enliven Boral’s right of summary termination?
Was Boral precluded from terminating the Agreement for some other reason?
Did the applicant release Boral from the claim for wrongful termination?
Submissions
Analysis and conclusion
Was it unconscionable for Boral to rely upon the release in the Second Deed?
Would Boral have terminated the Agreement on three months’ notice?
Conclusion and orders
MCLEISH JA
NIALL JA
MACAULAY JA:
Introduction
RW & ME Smith Pty Ltd (the applicant), is a company owned by Robert Smith, a truck driver, and his wife. The applicant delivered concrete for the respondent, Boral Resources (Vic) Pty Ltd (‘Boral’), under a cartage agreement (‘the Agreement’). On 9 July 2015, Mr Smith and another employee of the applicant helped employees of Boral replace a broken drive chain on an elevator at Boral’s concrete plant. The broken chain was preventing Boral from loading concrete onto trucks. After the successful repair, and the plant resuming operations, Boral summarily terminated the Agreement because of what it alleged was the applicant’s serious misconduct when assisting with the repair. Despite the summary termination, and with…
Keep reading for free
Create a free CaseChat account to read RW & ME Smith Pty Ltd v Boral Resources (Vic) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2023] VSCA 182
- Decision Date
CaseChat Overview and Summary
The primary legal issues for the court to determine were whether the applicant’s repair of equipment at the respondent’s plant fell within the meaning of ‘Cartage Works’ in the cartage contract, and whether the release clause in the termination deed was broad enough to release the respondent from the applicant’s claims for breach of the principal contract. The court also had to consider whether the trial judge erred in finding that the respondent was entitled to terminate the contract and to recover damages.
The court found that the trial judge erred in concluding that the applicant’s repair of equipment at the respondent’s plant fell within the meaning of ‘Cartage Works’. The court held that the applicant’s actions did not constitute ‘Cartage Works’ and that the respondent was not entitled to summarily terminate the contract on this basis. The court also found that the release clause in the termination deed only applied to the short-term contract made after the termination of the principal contract, and did not release the respondent from the applicant’s claims for breach of the principal contract. The court held that the trial judge erred in finding that the respondent was entitled to recover damages for the applicant’s alleged breach of the principal contract.
The court allowed the applicant’s appeal and set aside the decision of the Supreme Court of Victoria. The court found that the respondent was not entitled to summarily terminate the cartage contract or to recover damages for the applicant’s alleged breach of the principal contract. The court ordered that the respondent pay the applicant’s costs of the appeal.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi